Council archive · source document
Minor Change Existing Approval MCU21 0117 02 & OPW21 1099 02 (As Published) · OPW21/0199.02
Attachment 2—Changed referral agency conditions
2402-39295 SPD
(Under secton 56(1\b)(i) of the Planning Act 2016 the following conditions must be attached to any development
approval relating to this application) (Copies of the documents referenced below are found at Attachment 5)
No. | Conditions
| Condition timing
Material change of use for a multiple dwelling
10.9.4.2.4.1—Material change of use of premises near a state transport corridor—The chief executive
administering the Planning Act 2016 nominates the Director-General of Transport and Main Roads to
be the enforcement authority for the development to which this development approval relates for the
administration and enforcement of any matter relating to the following conditions:
1.
(a) Carry out the development generally in accordance with the
Eee Teeth Rail Nes :
prepared by Danad Moors dated 27.2021, report number
{Environmental Traffic and Rail Noise Level Impact
Asses: David Moore & Associates
Ltd dated 17 Jan 2024, reference R23089.docx/D3819 Rev 0.
In particular —
(i) construct @ 2 metre and 1.8 metre noise barrier in the
(b) The noise barrier must be designed in accordance with:
(i) the Department of Transport and Main Roads’ Road
Traffic Noise Management Code of Practice, Chapter 5°
Specifications MRS15 and MRTS15; and
(ii) Standard Drawings Road Msnual, Part 13.
(c) RPEQ certification must be provided to North Coast Region via
North.Coast [email protected] or 5451 7055 within the
Department of Transport and Main Roads, confirming that the
has been constructed in accordance with parts (a)
and (b) of this condition.
Prior to the
commencement of use
and to be maintained at
all times.
(8) Stormwater management of the development must ensure no
worsening or actionable nuisance to the state-controlled road.
(b) Any works on the land must not:
(i) create sny new discharge points for stormwater runoff
onto the state-controlled road;
(ii) interfere with and/or cause damage to the existing
stormwater drainage on the state-controlled road;
(iii) surcharge any existing culvert or drain on the state-
controlled road;
{iv) reduce the quality of stormwater discharge onto the
state-controlled road.
(c) RPEQ certification with supporting documentation must be
provided to North Coast Region via
North.Coast [email protected] or 5451 7055 within the
(s)
At all times.
(b)
At all times.
{c)
Prior to the
commencement of use.
Document Set ID: 24681870
Version: 7, Version Date: 17/04/2026
Sate Assessment and Referral Agency
Page 5 of 9
Page 26 of 31
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalUsed in these records
Minor Change Existing Approval MCU21 0117 02 & OPW21 1099 02 (As Published).pdfRelated documentApplication case desk ↗
Minor Change Existing Approval MCU21 0117 02 & OPW21 1099 02 (As Published).pdfRelated documentApplication case desk ↗
About this file
- File size
- 924 KB (small file)
- File type
No other editions are linked here.