Attachment 2- Cultural Heritage Due Diligence Assessment MCU12/0208
The Duty of Care Guidelines (The DoC Guidelines) are based on the concept of ground disturbance, both the
previous ground disturbance to a location, and the proposed ground disturbance which will be carried out by
the intended project. In summary, the type of ground disturbance is classified into five (5) categories under
The DoC Guidelines which are as follows;
CATEGORY 1 – No Ground Surface Disturbance. This means exactly that, there is no further
ground surface disturbance, and therefore no threat to physical Aboriginal Heritage. Proposed works
that are assessed as falling into this category may proceed without further investigation.
CATEGORY 2 – No Additional Surface Disturbance. This means that ground surface disturbance
has occurred in the past, and the proposed activities is the same or similar to what has occurred
previously. Examples given of a Category 2 disturbance are grazing cattle on paddocks already used
for grazing cattle, and maintaining and using pre-existing roads and vehicle track.
CATEGORY 3 - Developed Area. Similar to Category 2, in that disturbance of the proposed works
will be impacting an area already disturbed somewhat. Category 3 specifically applies to works of
infrastructure in areas of infrastructure, e.g. sewer maintenance, road upgrades, electrical
infrastructure etc.
CATEGORY 4 – Areas previously subject to Significant Ground Disturbance. This category
particularly applies to landscapes that initially may not fall into the proceeding categories but in which
Aboriginal Cultural Heritage is unlikely to be harmed. An example of a Category 4 landscape would be
regenerated forest after extensive timber logging had occurred. Care must be taken, however, with
this category as residual Aboriginal Cultural Heritage value may remain, particularly ceremonial or
mythological value which may not have been impacted by the “Significant Ground Disturbance”.
CATEGORY 5 – Any activity or area that does not fall into the preceding categories.
“Significant Ground Disturbance” as mentioned in Category 4 means:
(a) disturbance by machinery of the topsoil or surface rock layer of the ground such as by ploughing,
drilling, creating bore holes, or dredging; and
(b) the removal of native vegetation by disturbing root systems and exposing underlying soil.
The three key characteristics that need to be considered when assessing degrees of disturbance in regards to
Duty of Care by the Proponent are:
EV.241 Noosa on Weyba: CH Due Diligence Assessment 13
Prepared for Steve MacRae Development Services
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalUsed in these records
Attachment 2- Cultural Heritage Due Diligence Assessment MCU12/0208Related documentApplication case desk ↗
About this file
- File size
- 3.4 MB (large file)
- File type
No other editions are linked here.
Original file
Log in to download the original file
The download may take up to a minute.