Minor Change Report 51997 2256 02 [As Published] · 51997.2256.02
Figure 3: Existing approved ‘turn around’ area
Figure 4: Existing approved ‘turn around’ area being utilised as a carpark
Council’s Coordinator Engineering has reviewed the proposal to utilise the existing approved
turning bay as an additional carpark and confirms that the space may be utilised, provided it is
dedicated as a staff parking bay only (in association with the uses proposed within Lot 28 (ie
Reception Area etc)), as the bay is a non-standard bay due to the proximity to the building wall on
the left (refer to Figure 4), and as such the bay cannot be utilised by visitors/customers to the site.
In addition, Council’s Coordinator Engineering has no concerns regarding the removal of the
turning bay, provided the carpark is to be utilised by visitors to the site only, and is not open to the
public (refer to below assessment of Condition 20).
Therefore, the proposal to amend Condition 19 is supported in part, with the condition to read as
follows:
19. Provision of at least 35 off-street car parking spaces, comprising 27 covered spaces
and 8 uncovered spaces, and access thereto which are to be provided with a sealed
pavement and designed, drained, constructed and maintained in accordance with the
Planning Scheme AS2890.1 1993 edition, Council's Policies and to the reasonable
satisfaction of the Shire Engineer.
(a) The Lot 28 carpark is to be utilised by Staff of the accommodation building oonly
and must not be made available to guests or visitors to the site.
Page 6 of 9
Document Set ID: 22315507
Version: 7, Version Date: 18/04/2023
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalLog in to download the original file
The download may take up to a minute.