Council archive · source document
IC0213NAM0001_SC14279_130304_IR_DL_dvb_signed · MCU12/0208
Attached to the e-mail DNRM Information Request - MCU12/0208.
Notice
Information request
This notice is issued by the Department of Natural Resources and Mines pursuant to section 276 of the Sustainable
Planning Act 2009 (“the Act”).
Northbrook Corporation Pty Ltd cc. Chief Executive Officer
C/- Planning Initiatives Sunshine Coast Regional Council
PO Box 1774 Locked Bag 72
NEW FARM QLD 4005 SUNSHINE COAST MAIL CENTRE QLD 4560
.
Attention: Peter Catchlove Attention: Denis Wallace
DNRM references: IC0213NAM0001_SC14279
Assessment Manager ref.: MCU12/0208
Applicant reference: 1529
1. The Chief Executive, Department of Natural Resources and Mines (DNRM) as a concurrence agency
requests the applicant to give further information needed to assess the application. That further
information is stated in the attached information request.
2. Application details
Date properly referred to DNRM: 8 February 2013
Development approval for: Preliminary approval for material change of use under section 242 of
the Sustainable Planning Act 2009 to vary the effect of the Noosa Plan
and Maroochy Plan 2000 planning schemes for a mixed community
title development.
Aspects of development: Material change of use - Clearing vegetation (Sustainable
Planning Regulation 2009 - Schedule 7, table 3, item 10)
Material change of use – Particular development on SCL or
potential SCL (Sustainable Planning Regulation 2009 - Schedule
7, table 3, item 27)
Property/Location description: Lot 2 RP160983, Lot 2 SP179590, Lot 7 RP46782, Lot 53 SP163571,
Lot 11 SP250714, Lot 12 RP893393 & Lot 1667 M37772 (Eenie Creek
Rd, 99 & 191 Hollet Rd, Noosaville & 106-142 Tidswell Road, Weyba
Downs)
3. The application will lapse unless the applicant gives the assessment manager or concurrence agency a
response to the information request under section 278 of the Act which requires such response to
include a written notice to the requesting authority stating:
(a) all of the information requested is provided; or
(b) part of the information requested is provided, and to proceed with assessment of the
application; or
(c) the applicant does not intend to supply any of the information requested, and to proceed with
assessment of the application.
Page 1 of 7 • 091217
Department of Natural Resources and Mines
ABN 59 020 847 551
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalFull text of the other 6 pages
Page 2
Notice
Information request
4. A response to the information request must be given to the Project Manager, at the address stated
below.
Delegate Enquiries:
Daniel Leo
Department of Natural Resources and Mines
Centenary Square Building
Currie Street, Nambour QLD 4560
PO Box 573, Nambour QLD 4560
Telephone + 61 7 5451 2287
Dale Bell Facsimile + 61 7 5451 2260
Senior Planning Officer Email [email protected]
Planning Services (SEQ North & WBB) Website www.dnrm.qld.gov.au
Land Services – South Region
04 March 2013
Attachment – Information Request
Notice of Response to Information Request
Page 2 of 7 • 091217 Department of Natural Resources and Mines
Page 3
Notice
Information request
Information Request
1. Strategic Cropping Land (SCL)
Introduction
The proposed development is for a material change of use (MCU) and requires referral to the Department of
Natural Resources and Mines (DNRM) as per, schedule 7, table 3, item 27 of the Sustainable Planning
Regulation 2009. The proposed development will be assessed against SPP 1/12 Protection of Queensland’s
strategic cropping land (SPP 1/12).
In the application you have elected to treat the land as SCL for the purposes of this application (Question 3 of
IDAS form 35—Strategic cropping land). As indicated on Form 35, where the land is potential SCL and the
applicant has elected to treat the land as if it were SCL for the purposes of the development application, the
assessment will be based on the land being SCL (as per section 84 of the Strategic Cropping Land Act 2011).
Should you choose to dispute that the land is SCL, you will need to submit an SCL validation application. An
SCL validation application is not an application under the Sustainable Planning Act 2009. The SCL validation
application must be made under the Strategic Cropping Land Act 2011. The outcome of an SCL validation
application can not be considered as part of the MCU application, until a decision on the validation application
has taken effect and you change the MCU application as per section 351 of the Sustainable Planning Act 2009.
Results of preliminary assessment
MCU applications that involve particular development on SCL are assessed based on the extent/location of the
development footprint in relation to the SCL on the subject lot under the relevant section of SPP 1/12. For SCL
assessment purposes, footprint has the same meaning as Schedule 26 of the Sustainable Planning Regulation
2009. For preliminary approvals unless demonstrated otherwise, the development extent as per the plan of
development is taken to be the footprint of the development.
The proposed development has a footprint greater than 3000 m2 and is located within the strategic cropping
land management area. Section 4.5 of SPP 1/12 states that development that is for a MCU in the management
area, only complies with the requirements of SPP 1/12 if it satisfies the requirements in section 4.2.2 of the
SPP.
Additional information required to assess the application
Further information is required to demonstrate how the proposed development will satisfy SPP 1/12—
specifically how the proposal meets s4.2.2 (d) of SPP 1/12 and should include but is not limited to a report that
demonstrates:
That the development provides a public benefit and no other site is suitable for the particular purpose
(overriding need).
How permanent impacts on SCL have been avoided to the greatest extent possible.
How permanent impacts on SCL have been minimised where impacts could not be avoided.
The location and area of permanently impacted land and the mitigation value (s139 Strategic Cropping
Land Act 2011) including:
- Map/s or plan/s (at an appropriate scale),[1] showing all areas of SCL and the location/extent of all
footprint components.
- Calculate of the area of the footprint and the mitigation value.
1
Maps and plans at a property level provided to DNRM must contain either fixed identifiable features or include digital cadastral boundaries
Page 3 of 7 • 091217 Department of Natural Resources and Mines
Page 4
Notice
Information request
How the applicant proposes to mitigate the impacts on SCL or potential SCL where they cannot be
avoided. Mitigation has the meaning defined in s138 of the Strategic Cropping Land Act 2011 and for
permanently impacted land, means that either of the following, or a combination of the following has taken
place for the land’s mitigation value2 –
- A payment to the mitigation fund.
- The entering into of a mitigation deed.
2. Vegetation Management Act 1999
Introduction
The proposed development is for a material change of use (MCU) and requires referral to the Department of
DNRM as per, Material change of use - Clearing vegetation (Sustainable Planning Regulation 2009 - Schedule
7, table 3, item 10).
The DNRM assesses Material Change of Use applications using the Concurrence Agency Policy for Material
Change of Use (MCU) 21 October 2009 (MCU Policy). A copy of relevant vegetation Policies and Codes can be
accessed at www.dnrm.qld.gov.au .
For developments that result in the clearing of remnant vegetation, applications are also assessed against the
Regional Vegetation Management Code for South East Queensland Bioregion – version 2.1, 30 November
2012 (RVM Code). Please note that DNRM is directed to consider clearing as a result of the MCU. This
application requires assessment against the above mentioned MCU Policy and RVM Code.
A copy of the current Regional Ecosystem Map – v6.1 can be downloaded at www.derm.qld.gov.au/remap .
Results of preliminary assessment
The referral of your application was not accompanied by sufficient information demonstrating compliance with
the MCU Policy and RVM Code.
It is apparent from the submitted Property Vegetation Management Plan (PVMP) and information that the intent
of the project is to avoid clearing remnant vegetation by ensuring infrastructure is adequately setback from
vegetation. The exception is the clearing proposed for access to the site from Hollett Road.
A preliminary assessment has been conducted based on provided plans, specifically the Master Plan, Proposal
Plan, Structure Plan and Koala Habitat and Vegetation Offset areas. There is an inconsistency in these plans in
identifying the extent of development proposed which results in uncertainty about the amount of vegetation
clearing required.
Additional information required to assess the application
Further information is required to be submitted to DNRM which includes:
A plan and GIS shapefile of the setbacks proposed between mapped remnant vegetation and proposed
infrastructure around all mapped remnant vegetation.
Clarify the tracks to be created through mapped remnant vegetation – in particular any new roads
proposed through the endangered remnant vegetation on lot 11. Picture below is from the provided
‘Illustrative Concept Master Plan’.
2
Mitigation Value is defined in s139 of the Strategic Cropping Land Act 2011.
Page 4 of 7 • 091217 Department of Natural Resources and Mines
Page 5
Notice
Information request
Clarify whether Stage 4 identified on the ‘Proposal Plan’ is part of the development proposal. If
development is proposed in this area, please address the Regional Vegetation Management Code with
regard to clearing in a least concern regional ecosystem. Below is a snap shot of the area in question
(outlined in red) on the Proposal Plan.
Clarify the extent and location of the ‘rural settlement zone’ and ‘retirement village’ identified on submitted
plans. Below is a snap shot of the submitted ‘Precinct Plan – MP-006 [C]’ identifying Precinct J as ‘rural
residential lot’ and Precinct L as ‘retirement living / aged care’.
Page 5 of 7 • 091217 Department of Natural Resources and Mines
Page 6
Notice
Information request
Clarify whether rural allotments are proposed within lot 53 along the boundary of lot 902 SP163309. Below
is a snap shot of provided ‘Precinct Plan – MP – 006 [D]’ with area in question circled in red.
Page 6 of 7 • 091217 Department of Natural Resources and Mines
Page 7
Notice of Response to Information Request
Northbrook Corporation Pty Ltd
C/- Planning Initiatives
PO Box 1774
NEW FARM QLD 4005
DNRM References: IC0213NAM0001_SC14279
Planning Services, South Region
Department of Natural Resources and Mines
PO Box 573
NAMBOUR QLD 4560
Dear Sir/Madam
DEVELOPMENT APPLICATION FOR PRELIMINARY APPROVAL FOR MATERIAL CHANGE OF
USE UNDER SECTION 242 OF THE SUSTAINABLE PLANNING ACT 2009 – LOT 2 RP160983,
LOT 2 SP179590, LOT 7 RP46782, LOT 53 SP163571, LOT 11 SP250714, LOT 12 RP893393 &
LOT 1667 M37772 (EENIE CREEK RD, 99 & 191 HOLLET RD, NOOSAVILLE & 106-142
TIDSWELL ROAD, WEYBA DOWNS) – RESPONSE TO INFORMATION REQUEST
I am responding to your Information Request by:
Enclosing all of the information requested.
Enclosing part of the information requested and asking that the requesting authority proceed
with the assessment of the application.
Advising that I do not intend to supply any of the information requested and asking that the
requesting authority proceed with the assessment of the application.
Signed
________________________________________ [Signature]
________________________________________ [Print name]
________________________________________ [Date]
Used in these records
IC0213NAM0001_SC14279_130304_IR_DL_dvb_signed.pdfRelated documentApplication case desk ↗
About this file
- File size
- 457 KB (small file)
- File type
No other editions are linked here.