CC-3668 RFI Response
8. The hydraulic consultant will provide details of how the rainwater tanks will be plumbed into the
building for re-use. An overflow pipe from the rainwater tanks has been provided on the revised
plans; please refer to CC-3668 Revision DR6 for details.
Figure 1 – Bioretention Basin A
Figure 2 – Bioretention Basin B
Should you have any queries please contact the undersigned at our Bundaberg office.
Yours faithfully
Sid Olive
for and on behalf of
EMPIRE ENGINEERING Pty Ltd
Att(s) Empire Engineering Concept Plans – CC-3668 CON REV DR6
MUSIC Model Files – CC-3668 MUSIC Revision D