Noosa Civic
Construction Environmental Management Plan
Tasks Actions / Monitoring Timing Responsibility
Machinery clean down from the site to prevent the spread from the site
Details of monitoring and inspection procedures to prevent the spread of
fire ants.
Minimise the introduction and Ensure that all equipment, boots and vehicles used in weed-infested areas are Ongoing Contractor
dispersal of weeds and other washed down thoroughly before moving into weed-free areas of the site.
exotic species.
Use mulch (foliage and branches Stockpile cleared and pruned vegetation on-site for later use in rehabilitation Ongoing Contractor
of cleared native vegetation only) initiatives.
for stabilisation of bare ground Do not mulch weeds and non-native vegetation where it has potential to mix with
exposed during construction native vegetation mulch.
activities.
Prior to clearing/mulching vegetation, initiate chemical spraying of all declared weeds
to avoid application as part of the rehabilitation strategy.
Undertake site preparation (i.e. In areas where revegetation occurs amongst existing native trees, shrubs and Ongoing Contractor
soil treatment) and revegetation in groundcovers, implement the following procedure to minimise the potential damage to
a manner which avoids the native species.
unnecessary removal or damage 1. Mark all native tree and shrub species (including emergent woody vegetation) in the
to native species. revegetation area with flagging tape or conspicuous marker stakes.
2. Carefully undertake brush-cutting around these plants in order to reduce the grass
cover in preparation for soil improvement treatment.
3. During soil treatment and site preparation works, avoid root disturbance to retained
native woody vegetation by providing a set-back from the trunk of retained plants. The
set-back will depend on the size of each specimen, but should be in the vicinity of
0.5–2m.
Record keeping. Ensure all records and reports are made available to relevant administering authorities Ongoing Contractor
upon request.
Corrective actions. Should there be non-compliance with the stated performance indicators the following Ongoing Contractor
corrective actions are to be implemented:
identification of the cause of the non-compliance;
implementation of appropriate mitigation measures as determined by the
Principal in consultation with the Contractor and relevant experts (where
required); and
Noosa Civic Version 1 November 2014
Appendix B - Construction EMP.docx Page 18
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalVery large file: the download may take a few minutes. If you are on mobile data, it is best to wait until you are on Wi-Fi.
Searchable page text hides email addresses. Original files are unchanged and may show email addresses.