Skip to the record
Accept no imitations.

Original source · versioned page text

MCU14/0106 Appendix E - Engineering Report

of 175

Page text shows just the words. Original shows the document exactly as it was published.

Page text read automatically using OCR, there may be inaccuracies

Very large file: it may take a few minutes

The original of this document is very large (24.1 MB). Opening the original or downloading it may take a few minutes. Please be patient and don't click again. The page text is quick to read. If you are on mobile data, it is best to wait until you are on Wi-Fi.

Original PDF page 122, section 1. The text section number identifies this passage in the reader.

Noosa Civic
Construction Environmental Management Plan



 Tasks                               Actions / Monitoring                                                                    Timing    Responsibility
                                     local residents in the area.
                                     Ensure trucks and vehicles are loaded and unloaded on-site only.
 Worksite haulage routes.            Site access shall be in compliance with relevant conditions of approval.                Ongoing   Contractor
                                     Appropriate safety and warning measures to be implemented to ensure that
                                     construction works only cause minor disturbances to surrounding land users.
 Record keeping.                     Ensure all records and reports are made available to relevant administering             Ongoing   Contractor
                                     authorities upon request.
 Corrective actions.                 Should there be non-compliance with the stated performance indicators the following     Ongoing   Contractor
                                     corrective actions are to be implemented:
                                        identification of the cause of the non-compliance;
                                        implementation of appropriate mitigation measures as determined by the
                                         Principal in consultation with the Contractor and relevant experts (where
                                         required); and
                                        relevant validation monitoring to confirm that the nominated corrective
                                         actions have been effective.
                                     The Contractor shall implement the corrective action(s) as required within the agreed
                                     timeframe noted on the CAR.




Noosa Civic                                                                  Version 1                                                   November 2014
Appendix B - Construction EMP.docx                                                                                                            Page 29
Log in to download the original file

MCU14_0106 Appendix E - Engineering Report.pdf · 24.1 MB (very large file)

Very large file: the download may take a few minutes. If you are on mobile data, it is best to wait until you are on Wi-Fi.

Searchable page text hides email addresses. Original files are unchanged and may show email addresses.

The supporting record

Open full page ↗

Source document

Analyse documents ↗Open full page ↗

My Comparisons

Choose two to four records of the same kind. Drag using a handle or use the “Compare” buttons.

Your selected records are saved in this browser for your account. Results use the filters on the page where you choose “Compare selected”.