20210041 Bottlebrush Ave Op Works
Original PDF page 1, section 1. The text section number identifies this passage in the reader.
OP WORKS
ISSUE
RESIDENTIAL UNIT DEVELOPMENT
NOOSA HEADS
27 BOTTLEBRUSH AVENUE, NOOSA HEADS, QLD 4567
Lot 138 RP 88934
CIVIL WORKS
NOTE: VIBRATION EQUIPMENT, TRENCH SHORING ETC AS REQUIRED.
THE FOLLOWING INSPECTIONS MUST BE COMPLETED BY RECOR ENGINEERS BEFORE 11. PRIOR TO THE CONTRACTOR COMMENCING ANY WORKS DETAILED ON THESE DRAWINGS,
THE CONTRACTOR IS TO NOTIFY RECOR AND RECEIVE WRITTEN CONFIRMATION THAT
ENGINEERING CERTIFICATION WILL BE ISSUED. THE CONTRACTOR IS TO PROVIDE A WORKS CAN COMMENCE.
MINIMUM OF 72 HOURS NOTICE TO RECOR FOR REQUIRED INSPECTIONS. SHOULD THE 12. CONTRACTOR TO PROVIDE AS CONSTRUCTED DRAWINGS FOR ALL CONSTRUCTED WORKS
CONTRACTOR FAIL TO REQUEST AN INSPECTION, THE CONTRACTOR WILL BE IN ACCORDANCE WITH LOCAL GOVERNMENT REQUIREMENTS. UNLESS OTHERWISE
ADVISED BY RECOR CONTRACTOR TO NOTE COUNCILS ADAC REQUIREMENTS.
RESPONSIBLE FOR ALL COSTS TO ALLOW FOR THE WORKS TO BE INSPECTED TO THE
13. CONTRACTOR TO UNDERTAKE ALL WORKS IN ACCORDANCE WITH RELEVANT APPROVALS.
SATISFACTION OF RECOR. ANY INSPECTIONS THAT FAIL ARE TO BE RE-INSPECTED WITH
14. CONTRACTOR TO ALLOW TO LIASE/CO-ORDINATE WITH ELECTRICAL, LANDSCAPE AND
ALL REINSPECTION COSTS TO BE PAID BY THE CONTRACTOR. OTHER SERVICE CONTRACTORS THROUGHOUT CIVIL CONSTRUCTION.
a. PRESTART 15. CONTRACTOR TO ORGANISE ALL DEMOLITION PERMITS PRIOR DEMOLITION WORKS
b. EARTHWORKS - FINAL STRIPPING OF TOPSOIL, INSTALLATION OF SEDIMENT AND EROSION COMMENCING ON SITE.
CONTROL MEASURES UNSUITABLE GROUND 16. CONTRACTOR TO ALLOW TO DEMOLISH ALL EXISTING STRUCTURES, ROADS AND
c. SIDE AND CUT OFF DRAINS SERVICES WITHIN LIMIT OF WORKS AND REMOVE FROM SITE U.N.O.
d. STORMWATER PIPE LAID ON BEDDING PRIOR TO BACKFILL 17. CONTRACTOR TO UNDERTAKE DILAPIDATION REPORT FOR ADJOINING PROPERTIES AND
COUNCIL ROADS AND VERGES PRIOR TO COMMENCEMENT OF ANY WORKS ON SITE.
e. STORMWATER TRENCH BACKFILLED PRIOR TO PAVEMENT PLACEMENT
18. CONTRACTOR TO CLEAR AND GRUB ALL VEGETATION ON SITE AS IDENTIFIED IN THE
f. STORMWATER STRUCTURE BASE SLABS APPROVED VEGETATION MANAGEMENT PLAN. CONTRACTOR TO ENSURE ALL TREE ROOTS
g. SEWER RETICULATION AND STUMPS ARE COMPLETELY REMOVED AND BACKFILLED TO LEVEL 1 SUPERVISION.
CONTRACTOR TO ALLOW TO MULCH ALL CLEARED VEGETATION AND STOCKPILE ON SITE
TE
h. WATER RETICULATION OR REMOVE FROM SITE AS DIRECTED. SI
C T
i. PAVEMENT SUBGRADE 19. DRAWINGS TO BE READ IN CONJUNCTION WITH THE FOLLOWING
BJE
j. PAVEMENT REINFORCING CONSULTANTS/CONTRACTORS DRAWINGS: SU
SURVEYOR: SKYLINE SURVEYORS SITE BOUNDARY
k. PAVEMENT PRIOR TO SEALING (PRESEAL)
l. RETAINING WALL FOOTING REINFORCING ARCHITECT: ZEST BUILDING GROUP
m. RETAINING WALL BLOCKWORK PRIOR TO CORE FILL HYDRAULICS: TBC
n. STEEL REINFORCEMENT OF CONCRETE STRUCTURES STRUCTURAL: RECOR
o. PRACTICAL COMPLETION LANDSCAPE: ZEST BUILDING DESIGN
p. ON MAINTENANCE 20. CONTRACTOR TO PREPARE AND HAVE APPROVED BY RELEVANT AUTHORITY: ROAD
OPENING PERMIT AND TRAFFIC MANAGEMENT PLAN FOR ALL WORKS WITHIN COUNCIL
q. OFF MAINTENANCE ROAD RESERVES. CONTRACTOR TO ALLOW FOR ALL COSTS ASSOCIATED WITH
r. ANY OTHER INSPECTION AS SPECIFIED BY LOCAL COUNCIL (REFER DEVELOPMENT IMPLEMENTATION OF THE TMP.
APPROVAL) 21. ALL WORKS TO BE COMPLETED IN ACCORDANCE WITH ALL LOCAL AUTHORITY APPROVALS
s. ANY OTHER INSPECTION AS REQUIRED BY UNITY WATER AND WHERE RELEVANT TO THEIR RECEIVED FOR THE PROJECT AND IN ACCORDANCE WITH OPW APPROVALS BY COUNCIL.
CERTIFICATION SCHEME 22. NO WORKS ARE TO BE UNDERTAKEN ON LAND OUTSIDE OF THE SITE BOUNDARY WITHOUT
FORMAL APPROVAL BY THE OWNER/CUSTODIAN OF THAT LAND INCLUDING BUT NOT 25/02/2022
LIMITED TO PRIVATE PROPERTY, ROAD RESERVE, PARKS/OPENSPACE, EASEMENTS.
GENERAL NOTES EA ID: 2557785
23. THE CONTRACTOR SHALL HAVE AN APPROVED SET OF CONSTRUCTION DRAWINGS AND RPEQ: 26443
1. ALL DIMENSIONS SHOWN ARE IN METERS UNLESS OTHERWISE SHOWN. APPROVALS ON SITE AT ALL TIMES.
2. ALL SETOUT ON SITE IS THE SOLE RESPONSIBILITY OF THE CONTRACTOR. CONTRACTOR DO NOT SCALE, IF IN DOUBT ASK!
24. ALL WATER AND SEWER RETICULATION WORKS TO BE CONSTRUCTED IN ACCORDANCE
TO ALLOW FOR ALL MEANS NECESSARY TO ACCURATELY SETOUT THE WORKS. WITH THE SEQ WATER SUPPLY AND SEWERAGE DESIGN AND CONSTRUCTION CODE (2013).
3. ALL WORKS TO BE CONSTRUCTED IN ACCORDANCE WITH PROJECT SPECIFICATIONS AND
WHERE FURTHER DETAILS ARE REQUIRED THE CONTRACTOR SHALL REFER TO NOOSA
SHIRE COUNCIL DEVELOPMENT GUIDELINES, LOCAL WATER AUTHORITY GUIDELINES, LOCALITY PLAN
ASSOCIATED STANDARD DRAWINGS AND SPECIFICATIONS U.N.O.
NOT TO SCALE
4. SHOULD ANY OF THE CONSTRUCTED WORKS BE CONSTRUCTED OUTSIDE OF THE
TOLERANCES SPECIFIED WITHIN THE PROJECT SPECIFICATION AND LOCAL AUTHORITY
REQUIREMENTS, THE CONTRACTOR WILL RECTIFY AT THEIR COST INCLUSIVE OF ANY
B 22/02/22 UPDATE FOR RFI BRP NW
ADDITIONAL COSTS INCURRED BY RECOR.
A 01/12/21 ISSUED FOR OPW BRP MVP
5. EXISTING SERVICES HAVE BEEN PLOTTED FROM SUPPLIED DATA AND AS SUCH THEIR Rev Date Description By Chk
ACCURACY CANNOT BE GUARANTEED. NO RESPONSIBILITY IS TAKEN BY RECOR OR THE
PRINCIPAL FOR THE ACCURACY AND COMPLETENESS OF THIS INFORMATION. IT IS THE
RESPONSIBILITY OF THE CONTRACTOR TO ACCURATELY ESTABLISH THE LOCATION AND
LEVEL OF ALL EXISTING SERVICES PRIOR THE COMMENCEMENT OF ANY WORKS. ANY
DISCREPANCIES SHALL BE REPORTED TO THE SUPERINTENDENT. CONTRACTOR TO
LOCATE AND PROTECT SERVICES AS REQUIRED DURING PROPOSED WORKS.
6. THE CONTRACTOR IS TO CHECK THROUGH LOCATING, POTHOLING AND SURVEY ALL
CRITICAL CONNECTION POINTS FOR ALL CIVIL WORKS SHOWN ON THE DRAWINGS [email protected]
INCLUDING ANY POTENTIAL EXISTING SERVICES CLASHES PRIOR TO COMMENCEMENT OF 37 MARY ST NOOSAVILLE, QLD
CIVIL WORKS. CONTRACTOR TO IMMEDIATELY REPORT ANY DISCREPANCIES TO RECOR
07 5211 1003
AND AWAIT FORMAL DIRECTION PRIOR TO COMMENCING CIVIL WORKS.
Client
7. ON COMPLETION OF SERVICES INSTALLATION, ALL DISTURBED AREAS SHALL BE NOVATO GROUP
RESTORED TO ORIGINAL LEVEL, INCLUDING KERBS, FOOTPATHS, CONCRETE AREAS, Project Name
GRAVEL AREAS, GRASSED AREAS AND ROAD PAVEMENTS. 27 BOTTLEBRUSH AVE
8. CONTRACTOR SHALL BE RESPONSIBLE FOR REPAIR OF ANY DAMAGE TO NOOSA HEADS
AUTHORITY/COUNCIL'S INFRASTRUCTURE. SUCH REPAIR OR REINSTATEMENT TO BE
CARRIED OUT IMMEDIATELY TO THE SATISFACTION OF INFRASTRUCTURE
OWNER/MANAGER / AUTHORITY/COUNCIL. Title
COVER SHEET
9. CONTRACTOR TO UNDERTAKE ALL WORKS IN ACCORDANCE WITH ALL WORKPLACE
HEALTH AND SAFETY REQUIREMENTS.
10. WHERE ANY EXCAVATION OR CONSTRUCTION WORKS ARE TO BE IN CLOSE PROXIMITY TO
NEIGHBOURING LOT BOUNDARIES OR INFRASTRUCTURE, CONTRACTOR TO ALLOW IN
SCOPE OF WORKS TO PROVIDE ALL MEASURES NECESSARY TO ENSURE THE INTEGRITY
OF EXISTING BOUNDARIES AND INFRASTRUCTURE. THIS MAY INCLUDE THE USE OF LOW Project No. Discipline Status
20210041 CIVIL OPW
Designed By Drawn By Scale
(at
BRP BRP NTS A1)
Drawing No. Revision
C00 B
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalSearchable page text hides email addresses. Original files are unchanged and may show email addresses.