Original source · versioned page text
MCU21/0110 - SARA response—61 Noosa Springs Drive, Noosa Heads
2107-23530 SRA
Attachment 1—Referral agency conditions
(Under section 56(1)(b)(i) of the Planning Act 2016 the following conditions must be attached to any development
approval relating to this application) (Copies of the plans and specifications referenced below are found at
Attachment 5)
Condition
No. Conditions
timing
Material change of use
Schedule 10, Part 10, Division 3, Subdivision 3, Table 1, Item 1—Koala habitat area in SEQ region—
The chief executive administering the Planning Act 2016 nominates the Director-General of the
Department of Environment and Science to be the enforcement authority for the development to which
this development approval relates for the administration and enforcement of any matter relating to the
following conditions:
1. The development must be carried out generally in accordance with the At all times
following documents:
Proposed Site Plan with Koala Habitat Overlay, prepared by
Marchese Partners International Pty Ltd, dated 12/11/2020, Dwg.
No. SK.01, Revision 1.
2. Clearing is limited to the removal of 19 non-juvenile koala habitat trees At all times
identified with a red ‘X’ on Proposed Site Plan with Koala Habitat Overlay,
prepared by Marchese Partners International Pty Ltd, dated 12/11/2020,
Dwg. No. SK.01, Revision 1.
3. Prior to any building or operational works being undertaken, prepare a Koala (a) to (e) Prior to
Management Plan, which must: any clearing,
building or
(a) Identify the clearing and construction activities that may increase the
operational
risk of stress, injury or death of koalas; and
works being
(b) Detail the management measures that will be implemented during undertaken.
clearing works to prevent the risks identified in part (a) of this condition,
including but not limited to all of the following:
i. Details of pre-clearing inspections of the vegetation to be
cleared;
ii. Measures required under the Nature Conservation (Koala)
Conservation Plan 2017, including the staging and sequencing
of clearing and provisions for a koala spotter during clearing
operations;
iii. Procedures for the recovery of koalas;
iv. Measures for dealing with trapped, injured, orphaned and
deceased koalas;
v. Contact details for the contractor for reports of at risk or injured
koalas;
vi. Procedures for checking machinery for koalas; and
vii. Measures to protect retained koala habitat and vegetation
(including open land) in accordance with Australian Standard
AS4970-2009;
(c) Detail the management measures that will be implemented during
construction works to prevent the risks identified in part (a) of this
condition, including but not limited to all of the following:
i. Procedures for dealing with trapped, injured, orphaned and
State Assessment and Referral Agency Page 3 of 10
[OCR of page images]
Attachment 1—Referral agency conditions
2107-23530 SRA
(Under section 56(1)(b)(i) of the Planning Act 2016 the following conditions must be attached to any development
approval relating to this application) (Copies of the plans and specifications referenced below are found at
Attachment 5)
No.
Conditions
Condition
timing
Material change of use
Schedule 10, Part 10, Division 3, Subdivision 3, Table 1, Item 1—Koala habitat area in SEQ region—
The chief executive administering the Planning Act 2016 nominates the Director-General of the
Department of Environment and Science to be the enforcement authority for the development to which
this development approval relates for the administration and enforcement of any matter relating to the
following conditions:
1.
The development must be carried out generally in accordance with the
following documents:
e Proposed Site Plan with Koala Habitat Overlay, prepared by
Marchese Partners International Pty Ltd, dated 12/11/2020, Dwg.
No. SK.01, Revision 1.
At all times
Clearing is limited to the removal of 19 non-juvenile koala habitat trees
identified with a red ‘X’ on Proposed Site Plan with Koala Habitat Overlay,
prepared by Marchese Partners International Pty Ltd, dated 12/11/2020,
Dwg. No. SK.01, Revision 1.
At all times
Prior to any building or operational works being undertaken, prepare a Koala
(a) to (e) Prior to
Management Plan, which must: any clearing,
(a) Identify the clearing and construction activities that may increase the building or
. . . operational
risk of stress, injury or death of koalas; and .
works being
(b) Detail the management measures that will be implemented during undertaken.
clearing works to prevent the risks identified in part (a) of this condition,
including but not limited to all of the following:
i. Details of pre-clearing inspections of the vegetation to be
cleared;
ii. Measures required under the Nature Conservation (Koala)
Conservation Plan 2017, including the staging and sequencing
of clearing and provisions for a koala spotter during clearing
operations;
iii. Procedures for the recovery of koalas;
iv. Measures for dealing with trapped, injured, orphaned and
deceased koalas;
v. Contact details for the contractor for reports of at risk or injured
koalas;
vi. Procedures for checking machinery for koalas; and
vii. Measures to protect retained koala habitat and vegetation
(including open land) in accordance with Australian Standard
AS4970-2009;
(c) Detail the management measures that will be implemented during
construction works to prevent the risks identified in part (a) of this
condition, including but not limited to all of the following:
i. Procedures for dealing with trapped, injured, orphaned and
State Assessment and Referral Agency Page 3 of 10
Preview the original
The page text is free to read. Previews and downloads of original files need an account.
Log in to previewLog in to download the original (MCU21_0110 - SARA response—61 Noosa Springs Drive, Noosa Heads.msg)
Searchable page text hides email addresses. Original files are unchanged and may show email addresses.