Paving Treatment of Vehicle Movement Areas
31. Alternative materials, patterns, or threshold treatments must be used to articulate the
pavement treatment of vehicle movement areas.
Service Vehicles
32. Service vehicle parking, manoeuvring and standing spaces must be provided on the
site. The works must be undertaken in accordance with an Operational Works approval
and be in accordance with Council’s Planning Scheme Policy 9 – Waste Management.
The development must include in particular delivery/service/waste areas that are
accessible by a 12.5m vehicle.
Pedestrian and Bicycle Facilities
33. Pedestrian and bicycle facilities must be provided for the development. The works must
be undertaken in accordance with an Operational Works approval and must include in
particular:
a. a 1.8 metre wide footpath within the road verge for the entire length of the site’s
frontage to Pelican Street and Doonella Street. The path must be extended to
the existing full width path in Memorial Avenue
b. signage and lighting at strategic locations to direct people to building entries
c. a total of 13 bicycle parking spaces
Stormwater Drainage
34. The site must be provided with a stormwater drainage system connecting to a lawful
point of discharge. The works must be undertaken in accordance with an Operational
Works approval and must include in particular:
a. a stormwater drainage system that collects and discharges runoff such that there
is no net increase in stormwater runoff from the site.
b. the use of gravity stormwater drainage and not surcharge pits.
Stormwater Quality Management
35. A stormwater quality treatment system must be provided for the development. The
works must be undertaken in accordance with an Operational Works approval and
achieve the pollution reduction targets of the State Planning Policy Appendix 2 Water
Quality and be modelled in accordance with the Water by Design MUSIC modelling
guidelines or the Water by Design deemed to comply solutions.
36. Stormwater quality treatment devices must be routinely checked, serviced and cleaned
in accordance with the manufacturer’s recommendations or Water by Design
“Maintaining Vegetated Stormwater Assets” guidelines. Records of all maintenance
activities undertaken must be kept and made available to Council upon request. Where
replacement cartridges or other necessary components for the system become
unavailable, an alternative system is required to be retrofitted into the development to
achieve an equivalent pollutant reduction outcome.
37. All primary stormwater quality treatment devices must be routinely checked, serviced
and cleaned in accordance with the manufacturer’s recommendations. Records of all
maintenance activities undertaken must be kept and made available to Council upon
request.
38. The ongoing maintenance plan for the development must include the operations and
maintenance manual for the water quality device/s and must include the full cost of
maintaining the system. This maintenance plan must be provided as part of the
subsequent operational works.
Page 18 of 22
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalSearchable page text hides email addresses. Original files are unchanged and may show email addresses.