BUNNINGS WAREHOUSE. NOOSAVILLE
SURFACE WATER MANAGEMENT PLAN
(.^ C"rwncp
4.3 Outline Suitability Assessment
Each of the techniques described in the previous table is further assessed below, with
regard to the site's specific opportunities and constraints.
Litter Baskets/racks
The primary purpose for litter baskets is to remove medium sized litter and debris from the
site. Significant litter loads are not expected and other measures will be more appropriate
for managing the removal of litter from the site.
Sediment Traps
Sediment traps will be required during the construction phase to limit the transport of
sediment off site. Following construction, sediment levels will return to a low level, and
traps are therefore not considered necessary as a long-term water quality measure.
Gross Pollutant Traps
Gross pollutant traps (GPTs) are predominantly used for the removal of litter and debris -
t although they have been shown to effectively remove coarse sediment and suspended
solids (Brisbane City Council, 1999). Modelling shows that a GPT will be not be required.
Filter Strips/Buffer Strips
Buffer strips are areas of land left in their natural state that act to reduce peak runoff flows
and improve the quality of stormwater runoff. This treatment improves the aesthetic and
biodiversity value of the development and provides significant quality and quantity
improvements.
Grass Swales
Grass swales are considered a highly effective and aesthetic water quality (and to a lesser
extent, water quantity) control measure, when placed in flat areas. In this case, vegetated
swales, described below, are more appropriate.
Vegetated Swales
Vegetated swales require similar conditions as those outlined for grass swales above, and
wherever slopes are sufficiently low they would provide effective stormwater treatment for
the site. They will be employed in the car park areas, but feature a filter media for
treatment: see Bio-retention Systems.
Extended Detention Basin
Extended detention basins are designed to generally store runoff for 1-2 days. Their main
purpose is the reduction of the peak discharge from the site during a storm event, and the
retention of particulate matter. A detention basin is included on site in the southeast
r. corner.
Infiltration Trenches
Infiltration trenches allow pre-treated stormwater runoff to infiltrate into surrounding soils
and groundwater, and as such are not a treatment device in themselves. Where space is
limited, bio-retention systems are preferred.
Bunnings Warehouse Version 1 15 December 2006
J 13501-541WP\SWMP4oc Commercial in Confidence Page 9
f
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalUsed in these records
OPW11/0023 Development Application part 2 of 2 Planning Report and Plans 178 Eumundi Noosa Road NoosavilleRelated documentApplication case desk ↗
About this file
- File size
- 70.0 MB (very large file)
- File type
No other editions are linked here.
Original file
Log in to download the original file
The download may take a few minutes. On mobile data, it is best to wait for Wi-Fi.