NOOSA COUNCIL IDAS Development Application Decision Notice                                                   5 of 8


28.   Sediment and erosion control measures must be in place prior to works commencing. If such measures
      are not in place or are not satisfactory, “on the spot “fines may be issued. Such fines can be issued if
      sediments from the site are found to enter or have the potential to enter Council’s stormwater system or
      natural waterways. Although the sediment and erosion control measures have been approved on drawing
      No. 06N498-C02B, Council’s Manager – Land Development may request further controls to be installed
      should approved measures be inefficient.

29.   All stormwater drainage lines including private drainage lines (also known as inter-allotment drainage
      lines) or as otherwise approved by Council’s Manager of Land Development shall be inspected by closed
      circuit television (CCTV) at the completion of all works and immediately prior to acceptance ‘On
      Maintenance’. Council’s Construction Technical Officer shall be advised of the timing of this inspection.

      A report of the CCTV inspection, including photographic records (which includes photos & video
      recordings burnt onto a CD) of the inspection shall be submitted to the Council for approval. Any defects
      or substandard works shall be recorded and accurately illustrated on the drainage plan showing the
      location of the defect(s).

      Substandard work will not be accepted ‘On Maintenance’ and must be rectified at the applicants expense
      with a further CCTV inspection arranged once the rectification works have been completed.

      To this extent all CCTV inspections, including any additional inspections necessary following defect
      identification and rectification, shall be entirely at the applicant’s expense. Any costs incurred by Council
      in reviewing the CCTV inspection results shall also be borne by the applicant.

30.   Prior to acceptance of civil works to become Council assets "On Maintenance", the lodgement of
      satisfactory “As Constructed” records shall be submitted to Council.

      As Constructed drawings and data shall be certified by a qualified experienced Civil Engineer (RPEQ) for
      design intent, and a Licensed Surveyor shall certify the cadastre and the location, level and type of all
      services and structures. All of which shall be submitted to Council for checking and for Council’s records.

      The data must fully detail levels for all engineering works including but not limited to drainage structures,
      finished ground levels and pavement surface levels. The data shall be submitted in the Asset Design and
      As Constructed (ADAC) digital format.            (Guidelines on the use of ADAC are available at
      www.adac.com.au) and Council’s Planning Scheme Policy 5 – Engineering Design Standards – Roads,
      Drainage and Earthworks.
      Approval of works shall not be granted until all As Constructed information has been supplied and
      accepted by Council.
31.   A 5% cost of works to become Council assets or $1,500 bond (whichever is the greater) will be imposed
      on construction works during the maintenance period, which is a minimum period of 12 months duration.
      Such bond must be lodged by, and shall only be accepted from the Developer for the works.

32.   The works to become Council assets will not be accepted "On Maintenance" until the landscaping is
      completed.

33.   These works are also to be in compliance with the relevant conditions of Development Permit No.
      2006/1155.

34.   Notwithstanding that Council has checked the plans with due care, where it is found during construction
      that variations from Council's standards exist, then Council standards shall apply




AOP2 c:\docume~1\aop2\locals~1\temp\bcl technologies\easypdf 5\@bcl@e808ce94\@[email protected]

Used in these records

About this file

File size
34 KB (small file)
File type
PDF

No other editions are linked here.

Original file

Log in to download the original file

0015585E.001.pdf · 34 KB (small file)

The supporting record

Open full page ↗

Source document

Analyse documents ↗Open full page ↗

My Comparisons

Choose two to four records of the same kind. Drag using a handle or use the “Compare” buttons.

Your selected records are saved in this browser for your account. Results use the filters on the page where you choose “Compare selected”.