Skip to the record
Noosa’s premier civic archive.

Original source · versioned page text

SUPERSEDED NEGOTIATED - OPW25 0042 - REFERENCE DOCUMENT (As Published)

of 180

Page text shows just the words. Original shows the document exactly as it was published.

Page text read automatically using OCR, there may be inaccuracies

Very large file (18.6 MB): the original may take a few minutes to open or download. The page text below is quick to read.

Original PDF page 129, section 1. The text section number identifies this passage in the reader.

     Traffic Management Plan – 25040286

          1. INTRODUCTION
          1.1 Purpose and Scope

     This Traffic Management Plan (TMP) outlines the traffic control and traffic management procedures to be
     implemented by CML Investments to manage potential hazards associated with the traffic environment during
     the project.

     The project involves Trucks turning with hold and release for Tree Clearing And Bulk Excavation job at
     Serenity Close, Noosa Heads

          1.2 Objective and Strategies

     The objectives of the Traffic Management Plan are to ensure:

       • The safety of the road workers.

       • All road users, including vulnerable road users, are safely guided around, through or past the work site.

       • The performance of the road network is not unduly impacted and the disruption and inconvenience to all

          road users are minimised for the duration of the works.
       • Impacts on users of the road reserve and adjacent properties and facilities are minimised.

     In an effort to meet these objectives the Traffic Management Plan will incorporate the following strategies:

       • Providing a sufficient number of traffic lanes to accommodate vehicle volumes.

       • Ensuring delays are minimised.

       • Ensuring all road users are managed including motorists, pedestrians, cyclists, people with disabilities and

          people using public transport.
       • Ensuring work activities are carried out sequentially to minimise adverse impacts.

       • Provision will be made for works personnel to enter the work area in a safe manner in accordance with safety

          procedures.
       • All entry and exit movements to and from traffic streams shall be in accordance with the requirements of safe

          working practices.



          1.3 Engagement

     CMI Investment have engaged AVADA Traffic TMR Registration 0403 to prepare this Traffic Management
     Plan and associated controls for the works.

     The TMP will be implemented by AVADA Traffic TMR Registration 0403




Document Set ID: 24005412
                  23806880 Document MSF-AT-TMP-001| Issued 05 September 2024| Review: 05 September 2025| Owner: Trevor Leggett | Page: 5
Version: 1,
         0, Version Date: 06/08/2025
                          01/01/1900              [UNCONTROLLED IF WHEN PRINTED AFTER 05 September 2024]
Log in to download the original file

SUPERSEDED NEGOTIATED - OPW25 0042 - REFERENCE DOCUMENT (As Published).pdf · 18.6 MB (very large file)

The download may take a few minutes. On mobile data, it is best to wait for Wi-Fi.

The supporting record

Open full page ↗

Source document

Analyse documents ↗Open full page ↗

My Comparisons

Choose two to four records of the same kind. Drag using a handle or use the “Compare” buttons.

Your selected records are saved in this browser for your account. Results use the filters on the page where you choose “Compare selected”.