Traffic Management Plan – 25040286
1. INTRODUCTION
1.1 Purpose and Scope
This Traffic Management Plan (TMP) outlines the traffic control and traffic management procedures to be
implemented by CML Investments to manage potential hazards associated with the traffic environment during
the project.
The project involves Trucks turning with hold and release for Tree Clearing And Bulk Excavation job at
Serenity Close, Noosa Heads
1.2 Objective and Strategies
The objectives of the Traffic Management Plan are to ensure:
• The safety of the road workers.
• All road users, including vulnerable road users, are safely guided around, through or past the work site.
• The performance of the road network is not unduly impacted and the disruption and inconvenience to all
road users are minimised for the duration of the works.
• Impacts on users of the road reserve and adjacent properties and facilities are minimised.
In an effort to meet these objectives the Traffic Management Plan will incorporate the following strategies:
• Providing a sufficient number of traffic lanes to accommodate vehicle volumes.
• Ensuring delays are minimised.
• Ensuring all road users are managed including motorists, pedestrians, cyclists, people with disabilities and
people using public transport.
• Ensuring work activities are carried out sequentially to minimise adverse impacts.
• Provision will be made for works personnel to enter the work area in a safe manner in accordance with safety
procedures.
• All entry and exit movements to and from traffic streams shall be in accordance with the requirements of safe
working practices.
1.3 Engagement
CMI Investment have engaged AVADA Traffic TMR Registration 0403 to prepare this Traffic Management
Plan and associated controls for the works.
The TMP will be implemented by AVADA Traffic TMR Registration 0403
Document Set ID: 24005412
23806880 Document MSF-AT-TMP-001| Issued 05 September 2024| Review: 05 September 2025| Owner: Trevor Leggett | Page: 5
Version: 1,
0, Version Date: 06/08/2025
01/01/1900 [UNCONTROLLED IF WHEN PRINTED AFTER 05 September 2024]
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalLog in to download the original file
The download may take a few minutes. On mobile data, it is best to wait for Wi-Fi.