Compiled Approved Plans - 132003.221152.8
Plans and drawings
This document appears to be plans or drawings. Its page text below holds only the words printed on the drawings, without the drawings themselves, so it may be jumbled or hard to follow. To see the plans as drawn, choose Original above or download the file (both need you to log in).
Log in to see the plans as drawn ENVIRONMENT MANAGEMENT PLAN
The method of construction does require the use of a crane. This
offers significant environmental advantages as summarized below:
• By utilizing micro piling to ensure the stability of footings no tracked machine
will be required to access the site. The piling rig can be man handled around
the site after being craned into position utilizing protective temporary
walkways and level platforms installed in accordance with AS 4970—2009
• Manual material handling will be employed throughout the construction to
minimize construction activities and impact on the site, especially existing
vegetation.
• All construction and materials handling will be undertaken beneath the tree
canopy thereby avoiding potential damage to the canopy.
• All significant and protected trees within the work area will be fenced and or
otherwise protected during construction in accordance with the Tree Protection Plan
Rev A 11/08/2017 prepared by Myles Baldwin Design and in accordance with AS
4970—2009
• The Builder is to utilize where possible all trades and workers who were
involved in building the residence on No. 12 Park Road. This will ensure that
all workers understand the sensitivity of the site, the importance of preserving
the vegetation and the need to minimize noise, dust and other building activity
impacts on adjacent home owners and the public.
• The working area will be minimized to protect any significant vegetation
See amendment 5.
All significant and protected trees within the work area will be fenced and or otherwise protected
during construction in accordance with the most recent Tree protection Plan prepared by Myles
Baldwin Design and in accordance with AS 4970—2009 and approved by Noosa Shire Council
(See amendment 2)
REMOVAL OF BUILDING WASTE
Building waste will be collected in a garbage trailer or light truck situated
adjacent to the garage of No. 10 Park Road. Sand spoil will be lowered
daily from the terrace platform to the garbage trailer or light truck located
adjacent to the garage of No.10 Park Road.
EROSION AND SEDIMENT CONTROL
Erosion and Sediment Control is considered for both work areas as
summarised below:
□ The driveway to park Road will require silt fences to be installed to
the perimeter of the works. Sand bags will be placed in the gutters
during excavation and concreting to prevent runoff into the Council
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalLog in to download the original file
Large file: the download may take up to a minute.
Searchable page text hides email addresses. Original files are unchanged and may show email addresses.