Plans and drawings

This document appears to be plans or drawings. Its page text below holds only the words printed on the drawings, without the drawings themselves, so it may be jumbled or hard to follow. To see the plans as drawn, choose Original above or download the file (both need you to log in).

Log in to see the plans as drawn
                                                                                                  -

                                                                                  APPROVED PLANS
                                                                                   132003.221152.6
                                                                                   NOOSA COUNCIL
                                                                                    19 JULY 2018


Amendment 5)
Above drawing updated to include area of excavation; all work to be restricted to within the
excavated area of the lift and access walkway.




Scaffolding is to be erected within a TPZ as nominated in the above set out plan, where
adequate ground protection such as plywood sheeting or scaffolding boards is installed to
prevent compaction of soils. All boarding must be placed over a layer of mulch and impervious
sheeting to prevent contamination of soils, and branches that conflict with erection of
scaffolding must not be pruned without prior approval by the relevant consent authority.
Branches that may abrade on scaffolding are to be protected with suitable padding or may be
tied back under advice from the project arborist.

The above set out plan will allow for the erection of a 5.2m x 8.6m scaffold platform erected
above the existing driveway to accommodate the hydraulic pump and facilitate the removal
of spoil through a void into a truck below. This is to be supported by the existing rock walls and
driveway. Running from this will be an elevated ramp to support pump lines and facilitate the
removal of spoil; to be erected within the property boundary and on top of existing stonewalls.
Further protective scaffold platforms at 2.4m x 1.2m will be erected to support the drill rig and
adjacent to pile positions, to prevent compaction of soils by foot traffic and drilling operations.

All works within a TPZ must be carried out according to the Australian Standard 4970-2009 and as
permitted in accordance with the prior approval of the Council.




12 PARK ROAD           1A / 357 – 359 Cleveland Street, Redfern, NSW, 2016 | PH +61 2 9699 2622       15

NOOSA HEADS           [email protected] | www.mylesbaldwin.com | ABN 68 139 176 328
Log in to download the original file

Compiled Approved Plans - 132003.221152.8.pdf · 5.8 MB (large file)

Large file: the download may take up to a minute.

Searchable page text hides email addresses. Original files are unchanged and may show email addresses.

The supporting record

Open full page ↗

Source document

Analyse documents ↗Open full page ↗

My Comparisons

Choose two to four records of the same kind. Drag using a handle or use the “Compare” buttons.

Your selected records are saved in this browser for your account. Results use the filters on the page where you choose “Compare selected”.