1911-14440 SPD - Changed referral agency response minor change to development approval

Attached to the e-mail SARA Response - 152006.1999.4.

of 5

Page text shows just the words. Original shows the document exactly as it was published.

RE6-N




Changed referral agency response
Our reference:         1911-14440 SPD



Referral agency response—with conditions
(Given under section 56 of the Planning Act 2016)

Date of original response:         5 July 2013 (Appeal 344 of 2009)
Original reference:                DNRM - 2006/012181
                                   EPA – MCY1951_BNE29922

The development application described below was properly referred to the Department of Natural
Resources and Mines on 6 November 2006 and the Environmental Protection Agency on 8 February
2007.

Applicant details
 Applicant name:                    John Hofmann
 Applicant contact details:         C/- JFP
                                    55 Plaza Parade
                                    Maroochydore QLD 4558

Location details
 Street address:                    191 Hollett Road, Noosaville
 Real property description:         Lot 53 on SP163571
 Local government area              Noosa Shire Council

Application details
 Development permit                 Reconfiguring a lot (40 lots and park)

Referral triggers
The development application was referred to the department under the following provisions of the
Planning Regulation 2017:
 Trigger                 Description                                               Technical agency

 Schedule 10, Part       Development application for reconfiguring a lot that      Department of Environment
 17, Division 3,         is assessable development under section 28, if—           and Science (formally the
 Table 5 (10.17.3.5)     (a) all or part of the lot is within a coastal            Environmental Protection
                         management district and the reconfiguration               Agency)
                         involves—
                         (i) moving a boundary of the lot that is within an
                         erosion prone area; or
                         (ii) moving a boundary of the lot into, or within 30m

                                                                         South East Queensland (North) regional
                                                                         office
                                                                         Mike Ahern Building, Level 3, 12 First
                                                                         Avenue, Maroochydore
 Page 1 of 5                                                             PO Box 1129, Maroochydore QLD 4558
Log in to download the original file

1911-14440 SPD - Changed referral agency response minor change to development approval.pdf · 337 KB (small file)

Searchable page text hides email addresses. Original files are unchanged and may show email addresses.

Full text of the other 4 pages

Page 2

                                                                                                  1911-14440 SPD




 Trigger                   Description                                               Technical agency

                           of, an erosion prone area; or
                           (iii) creating a new lot that has a boundary within, or
                           within 30m of, an erosion prone area.
 Schedule 10, Part         Development application for reconfiguring a lot that      Department of Natural
 3, Division 4,            is assessable development under section 21, if-           Resources, Mines and
 Subdivision 2,            (a) a lot that the application relates to is 5ha or       Energy (formally the
 Table 1 (10.3.4.2.1)
                           larger; and                                               Department of Natural
                           (b) the size of any lot created is 25ha or less; and      Resources and Mines)
                           (c) either-
                           (i) the reconfiguration involves operational work that
                           is assessable development under section 5, other
                           than operational work that is only the clearing of
                           regulated regrowth vegetation; or
                           (ii) on any lot created, accepted operational work,
                           other than operational work that is only the clearing
                           of regulated regrowth vegetation, may be carried
                           out.

Conditions
Under section 56(1)(b)(i) of the Planning Act 2016 (the Act), the conditions set out in Attachment 1 must
be attached to any development approval.

Reasons for decision to impose conditions
The department must set out the reasons for the decision to impose conditions. These reasons are set
out in Attachment 2.

Approved plans and specifications
The department requires that the plans and specifications set out below and enclosed must be attached
to any development approval.

 Drawing/report title               Prepared by                    Date          Reference no.   Version/issue
 Aspect of development: Reconfiguring a lot
 Proposal Plan                      Jones Flint & Pike             26 March      M1775-13        Revision F
                                                                   2020
 Referral Agency Response           Environmental                  12 December   RARP2008/00     Sheet 1 of 2
 (Vegetation) Plan                  Protection Agency              2012          8142

Enc.     Attachment 1—Changed conditions to be imposed
         Attachment 2—Changed reasons for decision to impose conditions
         Approved plans and specifications




 Department of State Development, Manufacturing, Infrastructure and Planning                         Page 2 of 5

Page 3

                                                                                             1911-14440 SPD



Attachment 1—Changed conditions to be imposed


 No.        Conditions of development approval                                   Condition timing

 Reconfiguring a lot

 Schedule 10, Part 17, Division 3, Table 5 —The chief executive administering the Planning Act
 2016 nominates the Director-General of the Department of Environment and Science to be the
 enforcement authority for the development to which this development approval relates for the
 administration and enforcement of any matter relating to the following condition(s):

 1.         The works must be undertaken in accordance with the plan listed below.
            Proposal Plan M1775-02C13 Revision F prepared by Jones Flint & Pike dated 21
            September 200726 March 2020.

 Schedule 10, Part 3, Division 4, Subdivision 2, Table 1 —The chief executive administering the
 Planning Act 2016 nominates the Director-General of the Department of Natural Resource, Mines
 and Energy to be the enforcement authority for the development to which this development
 approval relates for the administration and enforcement of any matter relating to the following
 condition(s):

 2.         Clearing of native vegetation must not occur on the land within the area shown as Area A
            (A1, A2, A3, A4, A5, A6) on Referral Agency Response (Vegetation) Plan
            RARP2006/012181 RARP2008/008142, unless the clearing is-
                  by fire under the Fire and Rescue Emergency Services Act 1990 to reduce
                   hazardous fuel loads or an activity under the Fire and Rescue Emergency Services
                   Act 1990, section 53, 68 or 69; or
                  where it is necessary to remove or reduce the imminent risk that the vegetation
                   poses to serious personal injury or damage to property; or
                  io establish stormwater drainage infrastructure within previously cleared areas; or
                  in accordance with conditions on a concurrence agency response issued by the
                   chief executive administering the Vegetation Management Act 1999 for a
                   development approval; or
                  in accordance with conditions on a development approval where the chief executive
                   administering the Vegetation Management Act 1999 is assessment manager for
                   operational works that is the clearing of native vegetation.

 3.         New infrastructure must not be located in Area A (A1, A2, A3, A4, A5, A6) on Referral
            Agency response (Vegetation) Plan RARP2006/012181 RARP2008/008142, unless the
            infrastructure is:
                  stormwater drainage infrastructure located within previously cleared areas: or
                  in accordance with conditions on a concurrence agency response issued by the
                   chief executive administering the Vegetation Management Act 1999 for a
                   development approval; or
                  in accordance with conditions on a development approval where the chief executive
                   administering the Vegetation Management Act 1999 is assessment manager for
                   operational works that is the clearing of native vegetation.

 4.         New infrastructure must not be located in Area B (81, 81, 82, 83) on Referral Agency
            Response (Vegetation) Plan RARP2006/012181 RARP2008/008142, unless the
            infrastructure is:



 Department of State Development, Manufacturing, Infrastructure and Planning                    Page 3 of 5

Page 4

                                                                                          1911-14440 SPD




No.        Conditions of development approval                                 Condition timing

                 for a fire management line, firebreak, fence, road, driveway, stormwater drainage
                  infrastructure, effluent disposal area, underground services; or
                 in accordance with conditions on a concurrence agency response issued by the
                  chief executive administering the Vegetation Management Act 1999 for a
                  development approval; or
                 in accordance with conditions on a development approval where the chief executive
                  administering the Vegetation Management Act 1999 is assessment manager for
                  operational works that is the clearing of native vegetation.




Department of State Development, Manufacturing, Infrastructure and Planning                  Page 4 of 5

Page 5

                                                                                             1911-14440 SPD



Attachment 2—Changed reasons for decision to impose conditions

The reasons for the decision are:

       Lot 53 on SP163571 supports areas of mapped remnant vegetation shown on the certified Regional
        Ecosystem Map. The clearing of vegetation within these areas is regulated by DNRM under the
        authority of the Vegetation Management Act 1999.
       DNRM has assessed the application against the NRM Concurrence Agency Policy for Reconfiguring
        a Lot 27 June 2005, and has given weight to more recent policies such as the Concurrence Agency
        Policy for Reconfiguring a Lot (RaL) 21 October 2009 and determined that the application satisfies
        the requirements of Criteria Table A within the most recent RaL Policy and Part P of the Regional
        Vegetation Management Code for Southeast Queensland Bioregion - version 2, 6 November 2009
        (RVM Code) with conditions.
       The department has assessed the minor change application against the performance
        outcomes of State code 16: Native vegetation clearing (State code 16) of the State
        Development Assessment Provisions, Version 2.6 and consider that the proposed changed
        development is consistent with the requirements of State code 16 subject to appropriate
        conditions which are necessary to ensure that:
        o     assessable vegetation associated with natural wetlands and watercourses are protected to
              maintain water quality and habitat
        o     the current extent of the of concern regional ecosystems and endangered regional
              ecosystems are maintained
        o     areas of remnant vegetation are retained to maintain ecosystem functioning, remain in the
              landscape despite threatening processes and maintain connectivity to adjacent properties
        o     the current extent of essential habitat is maintained.
        o     DNRM has directed the assessment manager to include conditions in any development
              approval given for the application to ensure that any development approval remains consistent
              with the Ral Policy.
       The department has assessed the minor change application against the performance
        outcomes of State code 8: Coastal development and tidal works (State code 8) of the State
        Development Assessment Provisions, Version 2.6 and consider that the proposed changed
        development is consistent with the requirements of State code 8.



Evidence or other material on which the findings were based

       development application
       State Development Assessment Provisions published by the Department of State
        Development, Manufacturing, Infrastructure and Planning
       Planning Act 2016
       Planning Regulation 2017
       Development Assessment Mapping System (DAMS)




    Department of State Development, Manufacturing, Infrastructure and Planning                  Page 5 of 5

The supporting record

Open full page ↗

Source document

Analyse documents ↗Open full page ↗

My Comparisons

Choose two to four records of the same kind. Drag using a handle or use the “Compare” buttons.

Your selected records are saved in this browser for your account. Results use the filters on the page where you choose “Compare selected”.