Planning Report
Attached to the e-mail MCU15/0069 Development Application - 39 Duke St Sunshine Beach.
TRANSPORT, DRAINAGE AND WORKS CODE
A summary of the proposed development’s compliance with the purpose of the Transport Drainage
and Works Code is included below.
The purpose of this code is to ensure:
a) Development is consistent with the intentions of the strategic transport network, which is to--
i. improve the coordination between transport and land use, to avoid excessive motor
vehicle travel;
ii. minimise the environmental and social impacts of transport on the natural and urban
environment;
iii. increase the use of walking, cycling, bus, train and ferry modes and minimise the use of
the private car;
iv. vensure that vehicle access to the development does not compromise the capacity and
safety of the road system;
v. not increase the scale of the road network beyond that currently planned; and
vi. ensure that development appropriately attenuates noise from adjoining roads.
b) Development works are designed and constructed to a standard that meets community
expectations, prevents unacceptable off-site impacts and optimizes whole of life cycle costs;
c) Roads are designed and constructed to satisfy their specified functions and provide an
appropriate level of flood immunity (including local flooding on roads, i.e. through sufficient
kerb storage capacity);
d) Development provides appropriate buffering between noise sensitive uses and the major road
network and rail corridors;
e) Roads are designed and constructed to be compatible with the existing road network and
hierarchy and to provide a safe environment for vehicular traffic, pedestrians and cyclists;
f) Intersections and access points are designed and constructed to retain the low key
development style and slower pace enjoyed by residents and visitors;
g) Road and drainage infrastructure is constructed to a standard that minimizes ongoing
maintenance costs;
h) Drainage systems are designed and constructed with capacity to effectively manage or convey
the design flow;
i) Road and drainage infrastructure is compatible with other infrastructure; and
j) Road and drainage infrastructure does not create any adverse impacts upon environmental
values associated with biodiversity, hydrological cycles, biophysical resources and air quality.
Comment: The proposal will comply with all applicable Specific Outcomes of the Transport Drainage
and Works Code. This code will be addressed in greater detail as a component of a subsequent
operational works application.
WASTE MANAGEMENT CODE
A summary of the proposed development’s compliance with the purpose of the Waste Management
Code is included below.
The purpose of this code is to ensure:
a) The storage, disposal and management of solid and liquid waste are conducted in an safe and
ecologically sustainable manner and without environmental nuisance;