2021-10-18 General Committee Meeting Agenda
Text sections have not been matched to the original PDF pages. Use the original document to check page numbers.
GENERAL COMMITTEE MEETING AGENDA 18 OCTOBER 2021
6 REPORTS DIRECT TO GENERAL COMMITTEE
8 T000054 – TEWANTIN BYPASS STAGE 1 INTERSECTION UPGRADE – TENDER AWARD
Author Designer Capital Works, Aiden Flannery
Infrastructure Services Department
Index ECM/ Project and Contract/ T000054 Tewantin Bypass Stage 1 – Intersection
Upgrade / Council Reports
ECM/ Projects (T1) / Tewantin Bypass – Beckmans Rd – CAP.WORK – 100970
ECM/ Subject/Contract/Road Construction
Attachments 1. Evaluation Spreadsheet
EXECUTIVE SUMMARY
• The design and delivery of the Beckmans Road roundabout as a critical piece of the Tewantin
Bypass is funded by Transport and Main Roads (TMR) with additional funding provided by
Noosa Council.
• Noosa Council have agreed to manage the delivery of the project.
• This is the largest project Council officers have designed in-house.
• A Request for Tender (RFT) was advertised on 24 August 2021 and closed on 22 September
2021.
• Five respondents provided compliant submissions for Council to assess.
• The tender price is within the allocated budget and includes a component of work that is
Council’s responsibility.
• The budget for the component that is Council’s responsibility (upgrade to pavement entering
the roundabout) has been approved by the Capital Works Executive on 30 September 2021
• The remaining tender price is fully funded by the Department of Transport and Main Roads
under the terms of the Funding Agreement.
• The comprehensive assessment of the five tenders resulted in the recommendation to award
the contract to SGQ Pty Ltd.
• Endorsement of the recommendation will allow the contractor to mobilise in November and
complete the project in July 2022 according to requirements.
• Recommendation to approve expenditure of $7,849,520 excluding GST, including contract
value and contingency spend.
RECOMMENDATION
That Council note the report by the Designer Capital Works to the General Committee Meeting dated
18 October 2021 and:
A. Award Contract T000054 for the construction of the Tewantin Bypass Stage 1 – Intersection
Upgrade works to SGQ Pty Ltd for the sum under a schedule of rates contract for the amount
of $5,052,575 excluding GST;
B. Approve expenditure under this Contract up to $7,849,520 excluding GST, including
contingency spend.
Page 5 of 67
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalLog in to download the original file
Large file: the download may take up to a minute.
Searchable page text hides email addresses. Original files are unchanged and may show email addresses.