132004.240018.9 (23689 DA) - Request to extend currency period

of 9

Text shows just the words. Original shows the document exactly as it was published.

,




    of a bond for the completion of the road works, and delay the completion             of these works
    until the lodgement of the survey plan for Stage 4.

    Unfortunately, due to the range of ownership arrangements for the road and adjoining
    lands together with the state environmental   issues also effecting this locality, the
    advancement of these works and resolution of an appropriate approval and thus way
    forward, has not yet been achieved.

    In light of the above, we thus seek a further extension of time to the currency period in
    order to enable Peet to resolve all outstanding issues and approvals needed in order to
    complete all required external road upgrades.

    In addition to the above, and in consideration of Section 388(1) of the Sustainable Planning
    Act 2009, we provide the following comment:


      Section 388 (1) (a) - (c), Sustainable                           Response

                 Plannina Act 2009
     1.   In deciding a request under section

          383, the assessment    manager must
          onlv have reaard to-
                                                The development    approval in its current form remains
     a)   the consistency of the approval,      consistent   with the current   policies, particularly in
          including its conditions, with the    relation to Council's infrastructure charges policies, The
                                                conditions within the permit ensure that payment of the
          current laws and policies applying    relevant infrastructure charges shall be paid at the rates
                                                applicable at the time of payment.
          to the development, including, for
          example, the amount and type of       The original application sought approval for an urban
                                                residential development within an area zoned for that
          infrastructure contributions, or      purpose. The strategic rationale and planning intent of
          infrastructure   charges payable      the development, together with the associated social and
                                                economic  benefits of the development itself for the
          under an infrastructure charges       township   of Cooroy, assured the support and
                                                subsequent approval of the development by Council. We
          schedule;                             understand the Council support and planning merit in
                                                favour of such an urban development remains.

                                                We note that the original application was Impact
     b)   the community's current awareness     Assessable and as such involved public notification of
          of the development approval;          the development.

                                                As such, the community has previously been made aware
                                                of the development proposal through formal public
                                                notification procedures which in turn provided the
                                                community with the opportunity to make a properly
                                                made submission about the development.

                                                Given this, we believe that the community      maintain   a
                                                current awareness of the develooment aODroval in its




    Page I 2

Used in these records

About this file

File size
2.7 MB (large file)
File type
PDF

No other editions are linked here.

Original file

Log in to download the original file

132004.240018.9 (23689 DA) - Request to extend currency period.pdf · 2.7 MB (large file)

The download may take up to a minute.

The supporting record

Open full page ↗

Source document

Analyse documents ↗Open full page ↗

My Comparisons

Choose two to four records of the same kind. Drag using a handle or use the “Compare” buttons.

Your selected records are saved in this browser for your account. Results use the filters on the page where you choose “Compare selected”.