132004.240018.9 (23689 DA) - Request to extend currency period
,
of a bond for the completion of the road works, and delay the completion of these works
until the lodgement of the survey plan for Stage 4.
Unfortunately, due to the range of ownership arrangements for the road and adjoining
lands together with the state environmental issues also effecting this locality, the
advancement of these works and resolution of an appropriate approval and thus way
forward, has not yet been achieved.
In light of the above, we thus seek a further extension of time to the currency period in
order to enable Peet to resolve all outstanding issues and approvals needed in order to
complete all required external road upgrades.
In addition to the above, and in consideration of Section 388(1) of the Sustainable Planning
Act 2009, we provide the following comment:
Section 388 (1) (a) - (c), Sustainable Response
Plannina Act 2009
1. In deciding a request under section
383, the assessment manager must
onlv have reaard to-
The development approval in its current form remains
a) the consistency of the approval, consistent with the current policies, particularly in
including its conditions, with the relation to Council's infrastructure charges policies, The
conditions within the permit ensure that payment of the
current laws and policies applying relevant infrastructure charges shall be paid at the rates
applicable at the time of payment.
to the development, including, for
example, the amount and type of The original application sought approval for an urban
residential development within an area zoned for that
infrastructure contributions, or purpose. The strategic rationale and planning intent of
infrastructure charges payable the development, together with the associated social and
economic benefits of the development itself for the
under an infrastructure charges township of Cooroy, assured the support and
subsequent approval of the development by Council. We
schedule; understand the Council support and planning merit in
favour of such an urban development remains.
We note that the original application was Impact
b) the community's current awareness Assessable and as such involved public notification of
of the development approval; the development.
As such, the community has previously been made aware
of the development proposal through formal public
notification procedures which in turn provided the
community with the opportunity to make a properly
made submission about the development.
Given this, we believe that the community maintain a
current awareness of the develooment aODroval in its
Page I 2
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalUsed in these records
132004.240018.9 (23689 DA) - Request to extend currency periodRelated documentApplication case desk ↗
About this file
- File size
- 2.7 MB (large file)
- File type
No other editions are linked here.
Original file
Log in to download the original file
The download may take up to a minute.