f) the natural regeneration of the western part of the site (i.e. outside the bushfire
management area) shall be allowed to occur;
g) any boundary fencing for proposed Lot 1 must be fauna friendly;
h) erosion control measures (standard best practice) to be implemented where
necessary for any earthworks;
i) installation of four nest boxes (e.g. 1 x glider, 1 x possum and 2 x parrot) is
required in trees within the western portion of the site to compensate for the lack
of hollows in the local landscape.
Community Management Statement
32. The community management statement for the proposed development must, at all
times, contain provisions requiring strict compliance by the owners and occupiers of
the proposed lots with the approved FEMP and the maximum building height
requirements. The community management statement must be submitted to the
Council at the time of sealing of the plan of survey.
Owners responsible for Body Corporate
33. The owners of the proposed lots, including successive landowners must, jointly and
severely, ensure that the requirements of these conditions to be carried out by the Body
Corporate or for which the Body Corporate is responsible, are complied with.
Water & Sewer Connections
34. An underground connection to reticulated water and sewerage must be provided to
each lot in accordance with the standards and requirements of Northern SEQ
Distributor–Retailer Authority (Unitywater).
35. A Certificate of Completion from the Northern SEQ Distributor–Retailer Authority
(Unitywater) must be submitted to Council that certifies an underground connection to
reticulated water and sewerage has been provided to each lot OR the development
site (for MCUs).
Boundary Encroachments
36. Certification must be submitted from a Licensed Surveyor which certifies that:
a) the setback/s to any new boundaries for any existing buildings remaining on the
site comply with the relevant provisions of the planning scheme and the Building
Act 1975, unless varied by the development approval;
b) the constructed access and manoeuvring areas (including associated fill batters
and retaining walls) are fully contained within common property, including the 6m
wide by 8m deep turnaround bay required to facilitate efficient access and egress
for emergency services;
c) the fire trail and easement are established inside the perimeter of the Bushfire
Protection Zone on proposed Lot 1;
d) all utility services and connections (e.g. electricity, telecommunications, water,
sewerage) are wholly located within the lot they serve or alternatively included
within an easement;
e) all retaining walls and structures are fully contained within the lot they retain; and
f) any fill, including fill batters, are wholly contained within the subject site and not
Page 11 of 12
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalSearchable page text hides email addresses. Original files are unchanged and may show email addresses.