Delegated Report - Code - Planning MCU21 0021

of 1

Page text shows just the words. Original shows the document exactly as it was published.

Author	Development Engineer, Diogo Carrico
Development Assessment

APPLICATION DETAILS
Application No.	MCU21/0021 & OPW21/0036
Applicant	Pile-It Pty Ltd
Proposal	Material Change of Use – Landing – Residential and Operational Works – Prescribed Tidal Works – Timber Jetty
Properly Made Date	9 February 2021
Information Request Date	24 February 2021
Information Response Date	30 March 2021
Decision Due Date	20 July 2021
Report Completed Date	14 July 2021
Report Reviewed By	Mark Lewis

PROPERTY DETAILS
Property Address	43 Wyuna Dr Noosaville Qld 4566
RP Description	Lot 21 N 10576
Land Area	621m²
Existing Use of Land	Residential

STATUTORY DETAILS
SEQRP Designation	Urban Footprint
Zone	Low Density Residential
Precinct	Not Applicable
Local Plan Area	Not Applicable
Overlays	Acid Sulphate Soils; Flood Hazard
Assessment Type	Code
PROPOSAL
The application seeks approval for a Material Change of Use – Landing – Residential and Operational Works – Prescribed Tidal Works – Timber Jetty.
The locality and proposal plan are included below.

Figure 1 – Proposal Plan

site details
Background
Applicant seeks approval for the construction of a jetty to service the subject property.
On 1 June 2021, SARA provided its response with conditions.
Site Description

Surrounding Land Uses

assessment
Instruments for Statutory Assessment
Under the Planning Act 2016 the application must be assessed against each of the following statutory planning instruments to the extent they are relevant to the development:
State Planning Policy;
South East Queensland Regional Plan;
Planning Regulation 2017; and
Noosa Plan 2020.
Noosa Plan 2020
The following codes from the Noosa Plan 2020 are applicable to this development:
Waterways Works Code.
It is noted that the proposed jetty is 12 m long which is over the 10m described in the code. Given the property’s location and the fact that the proposed is supported by SARA, council has no concerns.
cONSULTATION
Referral Agencies
The applicant was referred to the following Referral Agencies:
Department of Infrastructure, Local Government and Planning (SARA)
The Department is a referral agency for tidal work or works in a coastal management district.
The Department has responded advising that the application was approved subject to conditions.
Internal Council Referrals
Not applicable
conclusion & reasons for decision
The proposed development generally complies with the requirements of the planning scheme and does not raise any significant issues that cannot be addressed by reasonable and relevant conditions. The application is therefore recommended for approval.
The report is provided in accordance with Section 63(5) of the Planning Act 2016.
RECOMMENDATION
With regard to Application No MCU21/0021 & OPW21/0036 for a Material Change of Use – Landing – Residential and Operational Works – Prescribed Tidal Works – Timber Jetty, situated at 43 Wyuna Dr Noosaville Qld 4566 and described as Lot 21 N10576, it is recommended the application be approved in accordance with the following details for the Decision Notice:
application details
Application No:	MCU21/0021 & OPW21/0036
Street address:	43 Wyuna Dr Noosaville Qld 4566
Real property description:	Lot 21 N 10576
Planning Scheme:	Noosa Plan 2020 (25 September 2020)
Decision details
Council decided to issue the following type of approval:
Development Permit for Material Change of Use – Landing – Residential and Operational Works – Prescribed Tidal Works – Timber Jetty
CURRENCY PERIOD of approval
The currency period for this development approval is stated in the conditions below.
assessment manager conditions
Approved Plans
Development undertaken in accordance with this approval must generally comply with the approved plans of development. The approved plans are listed in the following table unless otherwise amended by these conditions.
Plan No.	Rev.	Plan/Document Name	Date
S01	C6	Drawing Schedule & Transmittal Prepared by Lon View Consulting Engineers	09/03/2021
S02	C1	Structural Notes Sheet Prepared by Lon View Consulting Engineers	10/07/2020
S03	C6	Ste Plan, Framing Plan, Elevations Prepared by Lon View Consulting Engineers	09/03/2021
S04	C2	Jetty Framing Details – Sheet 1 Prepared by Lon View Consulting Engineers	06/10/2020
S05	C1	Jetty Framing Details – Sheet 2 Prepared by Lon View Consulting Engineers	10/07/2021
Currency Period
The Currency Period for this development approval lapses if all conditions have not been complied with by 13 June 2023, unless an application to extend the currency period is approved by Council.
General Conditions
The maximum number of vessels that may be berthed, moored, attached or stored on the structure(s) must not exceed 2.
The use of the jetty must not cause any adverse effects on the amenity of the surrounding area including changes to light, views, air quality and noise.
Vessels berthed/moored at the jetty must be located a minimum of 1.0m from the prolongation of the property boundaries.
Vessels and boatlifting devices must be connected directly to the jetty, and not located side by side or in tandem with another vessel.
All structures must be designed and constructed such that they are free standing within the waterway and are not connected to or behind the revetment wall.
All structures must have no detrimental effects on stormwater drains and/or easements.
Jetties must have a level-walking surface of R.L 1.000 A.H.D or be level with the top of the revetment wall.
A rigid handrail must be fitted on one side of the walkway.
Any handrail located along the walkway servicing the jetty must have a maximum height of 1100mm above the jetty floor.
No posts or vertical supports of the proposed jetty are to extend vertically from the structure unless they provide necessary support for the handrail.
No boatlifting devices are to be attached or moored at the jetty structure for the purpose of elevating a vessel above the water without Council approval.
There must be no electrical reticulation system carrying electricity in excess of 24 volts beyond the revetment wall unless all switches and power outlets are positioned above the 1%AEP flood level.
Lighting associated with the use must be designed, installed, operated, and maintained in accordance with Section 3 of AS4282 Control of the Obtrusive Effects of Outdoor Lighting.
The jetty is to be used for private purposes only with no commercial operations to be undertaken.
Boat repair activities are not permitted on site.
Wastewater and sullage must only be disposed of at approved pumpout facilities.
The mooring facility must not be utilised for live-aboard purposes.
Any construction and post construction activity is not to impact on the condition of the waterway, and is to be conducted so as not to breach the Environmental Protection Act EPA (1994) and the Environmental Protection (Water) Policy 2009.
Certification by a Registered Professional Engineer of Queensland that states that the jetty is constructed in accordance with best practice methods and is structurally sound must be submitted to Council. This certification must be submitted to Council within three (3) months of the completion of the works. A final inspection and approval of the structure by Council’s Inspector is also required. Please contact Council’s Development Assessment Branch on 5329 6500 to arrange the inspection.
This approval lapses where the construction of the jetty has not commenced within two (2) years of the date of issue of the approval, unless application is made and approved by Council for an extension.
After completion, the proposed works must be maintained in a sound state of repair in accordance with the approved plans
referral agencies
The referral agencies applicable to this application are:
Referral Status	Referral Agency and Address	Referral Trigger	Response

Concurrence	SARA at DILGP SARA at DILGP Via MyDAS2 at https://prod2.dev-assess.qld.gov.au/suite/ (for assistance, contact DILGP at 5352 9701 or email:[email protected]	Planning Regulation 2017 Schedule 10, Part 17 – Tidal Works or Work in a Coastal Management District	The agency provided its response on 1 June 2021 (Reference No. 2104-21909 SRA). A copy of the response is attached

Advisory notes
The following notes are included for guidance and information purposes only and do not form part of the assessment manager conditions:
General Advisory Notes
Council has undertaken an audit check of the Operational Works drawings in relations to the proposed works.  A detailed check of the calculations and drawings has not been undertaken, as they have been certified by a RPEQ.  The RPEQ bears full responsibility for all aspects of the engineering design.  Council reserves the right to require further amendments and/or additions at a later date should design errors become apparent.
The approval or conditions do not absolve the owner of the land from complying with all the conditions of this approval and/or relevant Council By-Laws and Policies and/or relevant statues and/or statutory regulations in the execution and/or performance of said works.
Council reserves the right to call up any performance bond held or levy charges against the property, should emergency works be required to be undertaken by Council to make the site safe due to inactivity on the development site for extended periods of time.
Should any changes or modifications to the approved plans be required as a result of construction constraints, a “Request to change an existing approval” under the Planning Act 2016 must be made. Amended plans clearly indicating the changes must be lodged with this application along with the appropriate fees.
property notes
Not applicable.
VARIATION approval details
Not applicable.
further development permits required
Not applicable.
submissions
Not applicable.
RIGHTS OF APPEAL
You are entitled to appeal against this decision. A copy of the relevant appeal provisions from the Planning Act 2016 is attached.
During the appeal period, you as the applicant may suspend your appeal period and make written representations to Council about the conditions contained within the development approval. If Council agrees or agrees in part with the representations, a negotiated decision notice will be issued. Only one negotiated decision notice may be given.
OTHER DETAILS
If you wish to obtain more information about the decision, electronic copies are available on line at www.noosa.qld.gov.au or at Council Offices.

[word/footer1.xml]
Page 7 of 7

[word/header1.xml]
3

[word/header2.xml]
DEVELOPMENT ASSESSMENT DELEGATED REPORT

[Attachment: image2.png (image text)]
Feature Name
J : | Noosaville
Type
| =
4 | SARA Link
| Waste
i a
ace |
Thursday, 2021

[Attachment: image3.png (image text)]
>
Business Centre Precinct
Zones ¥ \
Low Density Residential
Medium Density N
High Density Residential i N
Tourist Accommodation
Major Centre
Centre .
2. 4
Local Centre A
Neighbourhood Centre
Centre a
y
Impact Industry 4 a4
Recreation and Open Space d
ane
Environmental Management and Conserv.
Community Facilities
Innovation
4
Rural Residential
Label Legend
Maps \
Local infrastructure Plan (LGIP) x
Other Plan Maps 4
Superseded 1985 Zone
Superseded 2006 Planning Scheme
@ Draft Noosa Plan 2020
Log in to download the original file

Delegated Report - Code - Planning MCU21 0021.docx · 2.3 MB (large file)

Large file: the download may take up to a minute.

Searchable page text hides email addresses. Original files are unchanged and may show email addresses.

The supporting record

Open full page ↗

Source document

Analyse documents ↗Open full page ↗

My Comparisons

Choose two to four records of the same kind. Drag using a handle or use the “Compare” buttons.

Your selected records are saved in this browser for your account. Results use the filters on the page where you choose “Compare selected”.