4.5 Groundwater
No signs of groundwater seepage (‘springs’) were observed during our walk-over. Groundwater was not
encountered in the boreholes at the time of investigation.
Groundwater conditions are expected to be reflective of prevailing weather conditions and seepage may
develop particularly following periods of prolonged or heavy rainfall.
4.6 Surface Drainage
Surface drainage would be expected to follow natural surface contours to the east, draining into
stormwater infrastructure at the east of the property and towards the Henderson Street roadside
drainage system. It is noted that the site has a relatively large catchment; however, most runoff from
upslope of the property is anticipated to be intercepted by the existing stormwater infrastructure
associated with the neighbouring structures and roadside drainage systems along Elanda Street.
Given the sandy nature of the site, rainfall would normally be anticipated to infiltrate the ground surface.
However, as the proposed development will occupy a large part of the block, significant run-off from
hard surfaces will occur. Nevertheless, where directed into swales rather than pipes, such run-off would
be expected to infiltrate into the natural sands relatively rapidly.
No significant surface run-off features were noted during our assessment (e.g. deep rilling or scour/wash
out scars). This indicates that significant overland flow is generally absent during rainfall events.
Recommendations to improve surface drainage as part of the development works are provided in
Section 6.5.
Proposed Unit Development
30 September 2024 | 24265-001-Rev0 7
Document Set ID: 23376055
Version: 1, Version Date: 28/11/2024
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalLog in to download the original file
The download may take up to a minute.