Decision Notice OPW26 0086 (As Published)

of 7
                      c.      the latest version of the Healthy Waterways document “Water Sensitive Urban Design
                              Technical Design Guidelines for South East Queensland” for all water quality devices
                              to be constructed on site.
                     Works within Road Reserves
               12.    No removal of street trees is permitted without Council’s prior written approval.
               13.    Safe vehicle and pedestrian access on all streets in the vicinity of the development must be
                      maintained at all times. Should footpath/road closures be necessary to carry out construction
                      works, Council’s Engineering Officer must be notified prior to the proposed closure and all
                      requirements complied with.
               14.    All works must match neatly with existing road and verge/footpath features. Additional works
                      beyond the frontage may be required to provide an acceptable transition to existing road and
                      verge/footpath profiles.
                     Driveways
               15.    Driveway crossovers must be constructed generally in accordance Council’s Standard
                      Drawings RS-056, RS-056.1 and any associated addendum.
               16.    Any existing unnecessary or redundant property accesses must be removed, and the kerb,
                      footpath and verge area reinstated to match the existing footpath and/or verge treatments.
                      Grassed verge areas to be reinstated must be provided with 100 mm topsoil and grass seed
                      or turf, and must be maintained by the developer until established.
               17.    The following must be complied with during the construction of the required
                      crossover/driveway:
                      a.      the driveway surfacing must consist of an approved all-weather purpose material,
                              excluding the first 1.5m of the driveway measured from the existing road pavement
                              which must be sealed to match the pavement of Roberts Drive.
                      b.      the driveway must be in accordance with the requirements of AS2890.1 Off-Street Car
                              Parking for longitudinal and crossfall gradients.
                      c.      the driveway must be constructed so as to not concentrate or direct stormwater runoff
                              onto neighbouring properties
                      d.      underground service conduits for water supply, electricity and any other services must
                              be provided as part of the access driveway
                      e.      where there is an existing pedestrian path, a matching crossfall must be provided for
                              the driveway on the alignment of the path, for the full width of the path
                      f.      have a minimum clearance of 500mm from any Unitywater/Energex/Telstra asset,
                              unless a written approval is obtained from Unitywater/Energex/Telstra and submitted
                              to Council.
                      g.      any stormwater kerb outlet in close proximity to the edge of the new driveway must be
                              provided with an approved kerb adaptor
                      h.      any existing kerb sections requiring removal due to the works must be saw-cut and
                              removed to allow for a smooth and neat finish with the new driveway
               18.    Pavement design for privately owned works must be undertaken in accordance with the
                      relevant standards. Structural integrity of the driveway and car park areas will remain the
                      responsibility of the property owner/developer.
                      Stormwater Drainage
               19.    The constructed driveway must not cause additional ponding on the road formation or the
                      road reserve.




                                                                                                          Page 3 of 7
Document Set ID: 25067743
Version: 2, Version Date: 19/08/2026

Log in to download the original (Decision Notice OPW26 0086 (As Published).pdf)

Searchable page text hides email addresses. Original files are unchanged and may show email addresses.

The supporting record

Open full page ↗

Source document

Analyse documents ↗Open full page ↗

My Comparisons

Choose two to four records of the same kind. Drag using a handle or use the “Compare” buttons.

Your selected records are saved in this browser for your account. Results use the filters on the page where you choose “Compare selected”.