NOOSA COUNCIL IDAS Development Application Decision Notice                                           6 of 24


       Please note, a step between the driveway and the footpath shall be avoided, as it is preferred to have the
       footpath continue at a constant grade to minimise the potential for pedestrians to trip or fall.
33.    All vehicles shall enter and leave the site in a forward direction.
External Roadworks
34.    The applicant shall provide a centre traffic median within the David Low Way extending from the existing
       roundabout splitter island along the entire frontage of the site (up to a point in-line with the northern
       boundary of Lot 1 on RP 152737, #228 David Low Way and the southern boundary of Lot 0 on BUP
       101281, #232 David Low Way) to prevent vehicles from turning right into/from the development.

35.    Any roadworks widening and associated works (including pavement correction to the existing pavement,
       drainage works, modification of the footpath, landscaping, and adjustments to the existing infrastructure)
       that may be required as a result of the new centre traffic median shall be at no cost to Council. In this
       regard, plans detailing this work shall be prepared and submitted to Council for approval prior to obtaining
       a Development Permit for Operational Works.

36.    A safe U-turn facility shall be provided along the David Low Way to the north of the development, and
       within close proximity to the site, to enable northbound traffic the ability to U-turn in order to gain entry to
       the development. The provision of this facility shall be at no cost to Council, as the facility is needed to
       enable patrons of the development the ability to safely turn around. This facility shall be constructed prior
       to the approved use commencing.
       As an alternative to construction of the U-turn facility, Council may elect to enter into an Infrastructure
       Agreement with the applicant for the future roundabout to be constructed at Woodland Drive in
       accordance with the Coastal Major Roads Network Infrastructure Charges Plan (CMRNICP). This
       agreement would need to address, but not be limited to:
            Who pays for the design;
            Who constructs the infrastructure;
            The amount of costs to be borne by each party, recognising that the costs associated with
              constructing the roundabout prior to Council’s programme of 2010 will be the applicant’s;
            Use of CMRNICP contributions paid by this development towards the roundabout cost;
       All costs involved with the preparation of any Infrastructure Agreement will be borne by the applicant..
37.    A pedestrian priority crossing shall be provided in Heron Street between Courtyard E of the new
       development and the existing Peregian Centre on the southern side of Heron Street at no cost to Council.
       This crossing shall be designed as a shared zone and be consistent in design, form and function with the
       two existing shared zones in the precinct. Plans illustrating the design shall be submitted to Council prior
       to obtaining a Development Permit for Operational Works.

38.    To cater for increased pedestrian movements, in a north south direction at the Heron Street / David Low
       Way intersection, kerb ramps shall be installed and a pavement threshold shall be provided in Heron
       Street to define a significant change in road environment to motorists entering Heron Street from the
       David Low Way.

39.    To cater for increased pedestrian movements in a north south direction at the Heron Street / Kingfisher
       Drive intersection, kerb ramps shall be installed.

40.    The northern leg of the roundabout at Heron Street shall be provided with kerb ramps and a safe at grade
       gap in the central median island to facilitate safe pedestrian access in an east west direction.

41.    A raised at grade platform for pedestrians shall be provided in Kingfisher Drive (south of the proposed
       Delivery / Garbage collection bay) at the intersection with Heron Street to enable pedestrians to cross
       safely in an east west direction. This platform will by its physical nature be slow speed and shall fit in with
       the shared zone strategy for the precinct.

42.    A 2m wide pathway shall be provided between the new kerb ramps and the existing / proposed pathway
       network.

43.    A linemarked on road bicycle lane shall be provided on the David Low Way adjacent to the site at no cost
       to Council, the works shall include removal of existing lines and linemarking in accordance with Council
       requirements.




A c:\docume~1\tblogg\locals~1\temp\bcl technologies\easypdf 5\@bcl@6c06e85a\@[email protected]

Used in these records

About this file

File size
339 KB (small file)
File type
PDF

No other editions are linked here.

Original file

Log in to download the original file

05_1917 - SUPERSEDED Compiled Decision Notice [As Published].pdf · 339 KB (small file)

The supporting record

Open full page ↗

Source document

Analyse documents ↗Open full page ↗

My Comparisons

Choose two to four records of the same kind. Drag using a handle or use the “Compare” buttons.

Your selected records are saved in this browser for your account. Results use the filters on the page where you choose “Compare selected”.