                                AGENDA


     Services & Organisation
       Committee Meeting

                        Tuesday, 7 May 2024

                         commencing at 1:30 PM
                 Council Chambers, 9 Pelican Street, Tewantin




Committee: Crs Karen Finzel, Jessica Phillips, Frank Wilkie, Nicola Wilson




                            “Noosa Shire – different by nature”




                                                                             Page 1 of 12
Log in to download the original file

54529cf9ea.pdf · 6.1 MB (large file)

The download may take up to a minute.

Full text of the other 11 pages

Page 2

SERVICES & ORGANISATION COMMITTEE MEETING                        7 MAY 2024




1.   ATTENDANCE & APOLOGIES

     1.1.   APPOINTMENT OF CHAIR OF SERVICES & ORGANISATION COMMITTEE

2.   CONFIRMATION OF MINUTES

3.   PRESENTATIONS

4.   DEPUTATIONS

5.   REPORTS FOR CONSIDERATION OF THE COMMITTEE

6.   REPORTS FOR NOTING BY THE COMMITTEE

     6.1.   CAPITAL PROGRAM 2023/24 DELIVERY STATUS

7.   CLOSED SESSION

8.   MEETING CLOSURE




                                                                        Page 2 of 12

Page 3

SERVICES & ORGANISATION COMMITTEE MEETING                                                     7 MAY 2024


6.1       CAPITAL PROGRAM 2023/24 DELIVERY STATUS


Author               Infrastructure Planning Officer , Melissa Shepherd
                     Infrastructure Planning Design & Delivery | Infrastructure Services
                     Department
Index                ECM\Subject\2022-2023 Capital Works Program
Attachments          None


EXECUTIVE SUMMARY
      •   This report provides a status update for the Capital Works Program as at 31 March 2024.
      •   The total budget provision (Budget Review 2) for capital works for 2023/2024 financial year
          is $45.9m, inclusive of carry forwards of $19.5m. Projects in direct control of the Infrastructure
          Team is $37.3m. Other capital projects, such as ICT and fleet, is $8.6m.
      •   As at 31 March 2024, Council has expended a total of $22m (48%) of the 23/24 financial year
          budget with another $10.8m in commitments.
      •   The ongoing reduced availability of contractors, resources, equipment and materials and a
          very busy construction industry continues to add constraints to delivery. Projects continue to
          be managed within overall budget and time limitations to the extent possible.
      •   Exceptional wet weather conditions during the first quarter of 2024 has significantly
          hampered delivery. By way of example, March 2024 experienced rainfall on 28 days.
      •   The road reseal program has expended $4.2m of the $5m budget for 23/24 financial year.
      •   Council has a current forecast of grant funding revenue of $7m while Council’s contribution
          to these projects is $13.1m, while capital projects funded entirely by Council total $25.8m.
      •   The Design Services Team are currently managing 20+ capital design projects and continue
          to provide design and survey support over 60 projects in the 2023/2024 financial year.
      •   The Planning Team is currently supporting key master planning initiatives with multiple sub-
          projects; The estimated value in 2023/2024 is $1.7m with an estimated future project
          investment value of $55m+.
      •   There are currently 53 multi-year projects in various stages of completion.
RECOMMENDATION
That Council note the report by the Infrastructure Planning Officer to the Services & Organisation
Committee Meeting 7 May 2024 providing an update on the delivery of the 2023/24 Capital
Program as at 31 March 2024.

REPORT
This report is to inform Council of the overall status of the Capital Works Program at the end of
March 2024, marking the end of the 3rd quarter of the 2023/2024 financial year.

The report provides key information relating to projects within the Capital Works Program and
confirms the delivery status of some projects undertaken during the 3rd quarter of the financial
year.




                                                                                                       Page 3 of 12

Page 4

SERVICES & ORGANISATION COMMITTEE MEETING                                             7 MAY 2024


It is important to note that the Financial Summary provided in this report is for project lifecycle
progress i.e. a major project funded over multiple years, and which commenced in an earlier
financial year, may be significantly further progressed than the 2023/2024 financials indicate).

This report does not address disaster recovery projects, which are subject to separate reporting.

1. Current Projects
The major focus in the 3rd quarter of the 2023/24 financial year has been:
   • Continuing various stages of construction of major projects including:
           o   Sunshine Beach, Adams Street - Land Slip Design
           o   Noosa Heads – Dog Beach Sand Nourishment Works
           o   Noosa Heads, Garth Prowd Bridge – Renewal
           o   Tewantin, Memorial Park/ Poinciana Avenue Pathway – Upgrade
           o   Noosa Shire - Pathway Renewal Program
           o   Cooroy, Butter Factory Arts Centre – BFAC Renewal


   •   Emergent works within 2023/24 financial year include:
           o   Federal, 1033 Back Mountain Rd - Environmental Land Purcha
           o   Federal, 68 Padilpa Road - Environmental Land Purchase
           o   Federal, Federal Hall - Structural Rectification Works
           o   Federal, Federal State School - Infrastructure Upgrade
           o   Kin Kin, School of Arts - Ceiling Replacement
           o   Noosa Heads, Noosa Drive - CCTV and Street Light Replacement
           o   Noosaville - 90 Goodchap Street - Office Fit-out
           o   Noosaville, Local Disaster Coordination Centre - Building Establishment


   •   Review of tender submissions for a number of major projects also budgeted for delivery this
       financial year have been underway; these include:
           o   Peregian Beach, Skate Park – Design & Construct Upgrade
           o   Sunshine Beach, Belmore Tce - Pathway Renewal
           o   Noosaville, Noosa Leisure Centre - Outdoor Court Upgrade
           o   Noosaville – Noosaville Library – Public Amenities Upgrade


   •   Upcoming tenders also budgeted for construction commencement in the 2023/24 financial
       year include:
           o   Tewantin, Doonella Bridge – Design
           o   Cooroy, Butter Factory Arts Centre – Heritage restoration
           o   Tewantin, Moorindil Street – Ferry Landings/Bank Stabilisation
           o   Sunshine Beach, Belmore Terrace – Pathway Renewal
           o   Noosa Heads, Lions Park – Amenities Upgrade




                                                                                              Page 4 of 12

Page 5

SERVICES & ORGANISATION COMMITTEE MEETING                                         7 MAY 2024


          o   Sunshine Beach, Ed Webb Park - Upgrade


The Design Services Team are currently managing 20+ capital design projects and continue to
provide design and survey support over 60 projects in the 2023/24 financial year, with a
combined design and construction value exceeding $18m.

Design output continues to be impacted by the movement of key staff (currently one vacant full-
time equivalent position).

The road reseal program has expended $4.2m of the $5m budget for 2023/24 financial year.

   •   The following roads on the annual reseal program were undertaken during this quarter
       of 23/24 financial year
          o   Noosa Heads, Arkana Drive from Winbirra Way to Allambi Tce
          o   Noosaville, Gibson Rd - Saltwater Ave to Thomas St
          o   Noosaville, Walter Hay Dr - between Eumundi Noosa Rd and Eenie Ck Rd
          o   Noosaville, William St - Gympie Tce to Noosa Pde
          o   Sunrise Beach, Hardy St - Southern Cross Pde to #10
          o   Sunrise Beach, Heathland Dr - Ben Lexcen to Edward St
          o   Sunshine Beach, Edwards St - Roundabout to Heathland Dr #195
          o   Tewantin, Carramar St - Golf Course to Spey Court
          o   Tewantin, Cedarleigh Dr to Cooroy Noosa Rd
          o   Tewantin, Griffith Ave - Broadleaf Ct to Cedarleigh Dr
          o   Tewantin, Griffith Ave - Cedarleigh Dr to Cooroy Noosa Rd


The new road heavy patching program has expended $1m of the $1.5m budget for the
2023/2024 financial year.

   •   The following roads were undertaken within this program during this quarter of 2023/2024
       financial year:
          o   Cooroibah, Illoura Place
          o   Cooroy, Roberts Drive
          o   Kin Kin, Sister Tree Creek Road
          o   Sunshine Beach, Pacific Ave
          o   Sunshine Beach, Solway Dr


The Shire Wide Pathway Program continued into the 2023/2024 financial year.
   • The following pathways received renewal and upgrade works during this quarter:
          o   Noosa Heads, Claude Batten Drive – Pathway Renewal
          o   Noosa Heads, Noosa Woods – Pathway Renewal
          o   Tewantin, Cullinane Street



                                                                                           Page 5 of 12

Page 6

SERVICES & ORGANISATION COMMITTEE MEETING                                       7 MAY 2024


          o   Tewantin, Jacaranda Place
          o   Tewantin, Memorial Park
          o   Tewantin, Outlook Drive
          o   Tewantin, Yellowood Close


   •   The following pathways are in the planning and procurement stages, in preparation for
       undertaking these works during the 4th quarter of 2023/2024.
          o   Noosaville, Seagull Park - Pathway Renewal
          o   Tewantin, McKinnon Dr - Pathway Renewal
          o   Noosa Shire - Shire Wide - Pathway Renewal Program
          o   Cooran, Queen Street
          o   Cooroy, Elm Street
          o   Kin Kin, Main Street
          o   Noosa Heads, David Street
          o   Noosaville, Armitage Court
          o   Peregian Beach, David Low Way
          o   Pomona, Cooroora Creek Park
          o   Sunshine Beach, Corona Street
          o   Tewantin, Doonella Street


2. Project Updates




Noosa Heads Garth Prowd Bridge Renewal


Works on Garth Prowd Bridge are
progressing with traffic management and
scaffolding in place, in preparation for hydro
blasting works to take place and steel
strengthening plate installation.




                                                                                        Page 6 of 12

Page 7

SERVICES & ORGANISATION COMMITTEE MEETING                                        7 MAY 2024




                                               Photo: Site photo of Garth Prowd bridge works
                                               preparation




Noosa Heads –         Dog    Beach    Sand
Nourishment Works


The dredge arrived to Noosa Spit during Q3,
and has commenced sand nourishment works.
Dredging is programmed for completion in the
first quarter of next financial year.




                                               Photo: Site photo of dredge in Noosa and works
                                               commencing




                                                                                         Page 7 of 12

Page 8

SERVICES & ORGANISATION COMMITTEE MEETING                                       7 MAY 2024


3. Grant Funding
The 2023/2024 financial year Capital Works program includes an unprecedented amount of
grant funding.
Figures 1 and 2 below demonstrate the non-grant funded capital projects compared to projects
with grant funding, as well as Council’s contribution towards grant funded projects.

                                Percentage Value of
Figure 1 Detail
                                of CWP     CWP
Non-Grant funded projects       56%          $25.8m
Projects with grant funding     44%          $20.1


Figure 1




                                  Percentage Value of
Figure 2 detail
                                  of CWP     CWP
Non-grant funded projects         56%        $25.8m
Grant funding revenue             15%        $7m
Council's contribution to projects
                                   29%       $13.1m
with grant funding




                                                                                        Page 8 of 12

Page 9

SERVICES & ORGANISATION COMMITTEE MEETING                                         7 MAY 2024



Figure 2




4. Completed Projects
While the 3rd quarter continues to experience constraints with ongoing contractor, resource and
material shortages, lengthy lead times, ongoing pricing increases, and extensive wet weather
impacts, 48% of the 2023/24 capital budget has been expended.

The Project Control Group and Capital Works Executive have continued to enable staff and
Council to make informed decisions that relate to projects being delivered throughout the year.

This quarter has seen the successful completion of the following key projects:




Tewantin Memorial Park Pathway Upgrade


Pathway upgrade works at Memorial Park were
completed during Q3 of 2023/24




                                              Photo: Site photos of completed pathway works at
                                              Memorial Park




                                                                                           Page 9 of 12

Page 10

SERVICES & ORGANISATION COMMITTEE MEETING                                             7 MAY 2024




Cooroy Butter Factory Arts Centre - BFAC
Renewal Works


The ceiling and associated electrical works at
the Butter Factory are now complete.



                                                 Photo: Internal photo of new ceiling and painted
                                                 beams.
Link to Corporate Plan
Theme No. 2. - Liveability

Liveability encompasses housing, facilities and services, transport, health and wellbeing to enable
an inclusive, connected and vibrant community.

Objective 2.7
Fund and deliver sustainable assets and facilities and associated services responding to the
changing needs of the community and the challenges and opportunities of the future.


Previous Council Consideration
Nil

Finance
The year-to-date capital delivery expenditure as at 31 March 2024 is $22m or 48% of the capital
program current budget.

Figures 3 and 4 below demonstrate the year-to-date budget, actual expenditure and percentage of
program delivered including commitments, broken down for Capital and Other Capital. Other Capital
includes Asset Management, Information Communication and Technology, Fleet, and the Planning
Scheme expansion.


 CWP Budget 23/24                   37,294,612             8,613,331              45,907,943
                                                      Other Capital
                                 Capital                                 Total Capital Works
                                                       (ICT, Fleet)

 Budget Year to Date                27,557,015             5,910,443              33,467,458

 Actuals Year to Date               18,823,399             3,225,243              22,048,642

 *Remaining
 Commitments/contract                8,089,924             2,697,003              10,786,927
 values




                                                                                               Page 10 of 12

Page 11

SERVICES & ORGANISATION COMMITTEE MEETING                                           7 MAY 2024


Figure 3 – Capital Finance data as at 31 March 2024




Figure 4 – Budget Status of Capital Works as at 31 March 2024



Risk & Opportunities
Risks that have presented challenges to delivery of the Capital Works Program include the
increased costs and delays associated with reduced availability of contractors, resources,
equipment, and materials. Recent staff losses have exacerbated this situation. This has
extended the construction program on many projects.
The construction industry is also proving challenging due to market demands and lack of
confidence in the supply chain, resulting in significantly inflated pricing in tenders submitted,
often well in excess of educated estimates.

Strategic delivery mechanisms are continuing to be implemented to optimise project delivery,
including appointment of additional co-ordination staff to direct improved delivery, packaging of
works, outsourcing where feasible, expeditious contract arrangements, delivery program
adaptation, relationship building with contractors and efficient internal resource utilisation.

Construction during the first quarter of 2024 has been severely hampered by unprecedented
wet weather conditions. Ongoing wet weather conditions would further hamper delivery efforts.

Capital Works Program Management and Reporting

The Infrastructure Planning, Design and Delivery team have made substantial advancement in
its monitoring and reporting on the Capital Works Program.



                                                                                           Page 11 of 12

Page 12

SERVICES & ORGANISATION COMMITTEE MEETING                                                   7 MAY 2024



The Capital Works Schedule (CWS) has been rolled out with further advancements over the
coming months. The CWS is enabling improved control and reporting on the delivery of the
Capital Works Program, with particular advantages in forecasting and early identification of
issues.
Project managers across the organisation are become more familiar with the CWS and the
benefits of this project control system are expected to grow as project managers enhance
utilisation of this system to manage delivery of their capital works projects.

Summary

The Infrastructure Services Department is continuing to address staffing shortages with
recruitment underway for a Design Project Officer, Graduate Transport & Traffic Officer and
Transport and Traffic Coordinator.


The 2023/24 capital works program commitments total $10.8m. Large volumes of planning,
design and delivery activities continue to be undertaken in support of the capital works program
which includes unprecedented amounts of grant funding and delivery of disaster recovery
works.


Consultation
External Consultation - Community & Stakeholder
Nil

Internal Consultation
Departments consulted:

      Office of the CEO, Mayor &         Community Services               Corporate Services
              Councillors
         Mayor & Councillors             Director                         Director
         Chief Executive Officer         Community Development       x    Financial Services
         Executive Officers              Sport & Active Lifestyles        Fleet
         Community Engagement            Arts & Culture                   Revenue Services
         People & Culture                Community Connection             ICT
         Governance                      Customer Experience              Procurement

                                                                          Commercial Property

       Strategy & Environment          Development & Regulation          Infrastructure Services
         Director                        Director                    x    Director
         Strategic Land Use Planning     Development Assessment      x    Infrastructure      Planning,
                                                                          Design and Delivery
         Economic Development &          Local Laws                  x    Civil and Asset operations
         Destination Management
         Environmental Services          Environmental Health        x    Waste
         Innovation & Digital Hub        Building & Plumbing         x    Building & Facilities
                                         Property / Permits               Disaster Management




                                                                                                       Page 12 of 12

The supporting record

Open full page ↗

Source document

Analyse documents ↗Open full page ↗

My Comparisons

Choose two to four records of the same kind. Drag using a handle or use the “Compare” buttons.

Your selected records are saved in this browser for your account. Results use the filters on the page where you choose “Compare selected”.