SERVICES & ORGANISATION COMMITTEE MEETING 7 MAY 2024
Figure 2
4. Completed Projects
While the 3rd quarter continues to experience constraints with ongoing contractor, resource and
material shortages, lengthy lead times, ongoing pricing increases, and extensive wet weather
impacts, 48% of the 2023/24 capital budget has been expended.
The Project Control Group and Capital Works Executive have continued to enable staff and
Council to make informed decisions that relate to projects being delivered throughout the year.
This quarter has seen the successful completion of the following key projects:
Tewantin Memorial Park Pathway Upgrade
Pathway upgrade works at Memorial Park were
completed during Q3 of 2023/24
Photo: Site photos of completed pathway works at
Memorial Park
Page 9 of 12
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalLog in to download the original file
The download may take up to a minute.