2019-12-16 General Committee Agenda
Text sections have not been matched to the original PDF pages. Use the original document to check page numbers.
GENERAL COMMITTEE MEETING AGENDA 16 DECEMBER 2019
Previous Council Consideration
Ordinary Meeting Minutes, 19 September 2019, Item 9, Page 12
That Council note the report by the Project Coordinator – Flooding, Coastal and Foreshore to the
Services & Organisation Committee Meeting dated 10 September 2019 providing an update on
the development of a Shoreline Erosion Management Plan (SEMP) for Noosa Spit.
Ordinary Meeting Minutes, 20 June 2019, Item 17, Page 16
That Council note the report by the Project Coordinator – Flooding, Coastal and Foreshore to the
Services & Organisation Committee Meeting dated 11 June 2019 providing an update on the
development of a Shoreline Erosion Management Plan (SEMP) for Noosa Spit.
Ordinary Meeting Minutes, 21 March 2019, Item 8, Page 9
That Council note the report by the Project Coordinator – Flooding, Coastal and Foreshore to the
Services & Organisation Committee Meeting dated 12 March 2019 providing an update on the
development of a Shoreline Erosion Management Plan (SEMP) and also note the formation of a
staff Noosa Spit SEMP Project Working Group to oversee that project.
Ordinary Meeting Minutes, 15 November 2018, Item 2, Page 11
That Council note the report by the Project Coordinator – Flooding, Coastal and Foreshore to the
Services & Organisation Committee Meeting dated 6 November 2018 and
A Support the urgent completion of a Shoreline Erosion Management Plan for Noosa Spit
and Noosa Main Beach subject to funding being provided in Budget Review 2; and
B. Provide a status update to Council on a quarterly basis.
Finance
All options proposed within the Noosa Spit SEMP were evaluated for a whole of life cost over a
duration of 20 years, which included any upfront or ongoing costs. The proposed nourishment
option has been costed based on renourishment occurring every seven years, with the total
expenditure in the first year anticipated to be approximately $1.2 million. This cost is inclusive of
all required permits, nourishment, project management, project contingency and monitoring. The
complementary activities (section 3) have not been included in this estimate as they are either
considered business as usual activities, or in the case of revegetation, should be implemented
once the success of the major works has been established.
It is proposed that the project will submitted for consideration in the capital works program for the
2020/21 budget.
Figure 3 below presents a graph of proposed costs over the 20-year lifecycle.
Page 37 of 51
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalLog in to download the original file
Large file: the download may take up to a minute.
Searchable page text hides email addresses. Original files are unchanged and may show email addresses.