Council archive · source document
Decision Notice - 010.2007.00001014.001 [As Published] · 142007.1014
NOOSA COUNCIL IDAS Development Application Decision Notice 3 of 8
Noosa Council Conditions
INTEGRATED PLANNING ACT 1997, IDAS DEVELOPMENT APPLICATION
Landscaping
1. The site is to be landscaped in accordance with Council’s Policy on Landscaping Guidelines and the
approved Landscaping Plan which are titled and numbered Ground Floor Plan with Landscaping prepared
by Emma Steward dated March 2005, with the landscaping certified by Kerri-Ann Milsted dated 15 May
2007 and may be amended by these conditions and notations on the plan.
2. The landscaping plans referred to above are to be prepared and certified by a suitably qualified and
experienced Landscape Architect or Horticulturalist.
3. All manholes, inspection pits and grates are to be raised to finished surface levels and kept free of cover
and be visible at all times to ensure prompt access in case of emergency.
4. The landscape construction is to be implemented in accordance with the amended landscape plan,
planting schedule and horticultural industry best practices.
5. All trees must be planted a minimum of 1 metre from all services.
6. Screen planting shall be provided along the full length of the western boundary.
7. The Pandanus species located in the eastern garden shall be retained, or replaced with the same species
in the event it dies due to ill health.
8. Xanthostemon chrisantus species are undesirable plants in the coastal areas of the shire in accordance
with Council’s Planning Scheme Policy and therefore shall be replaced with the following:-
9. along the western boundary, Syzgium australe to achieve screening to a height of 4-6 metres;
and
10. along the eastern boundary, Syzgium australe or other native species in accordance with
Council’s desired plant species for coastal areas under the Planning Scheme Policy.
11. This Development Permit lapses if the development has not happened by 29 November 2009, unless
application to extend the currency is approved by Council.
Land Development
12. The development shall be carried out in accordance with engineering drawings nos 06/206-OP1 dated
May 2007 prepared by John Norden & Associates and 06057-H-GF-01 dated 27 September 2006
prepared by Brian Burnett & Associates or as modified herein.
13. Roof and surface runoff connection to Council’s existing catchpit shall be as shown on drawing No.
06057-H-GF-01.
14. A bikeway/footpath 1.5 metres wide shall be constructed across the full frontage of the development. The
footpath shall have a slip resistant surface. The alignment, of which, shall be determined on site with
Council’s Construction Technical Officer. The expansion joints in any bikeway/footpath shall be “sawcut”
not trowel jointed.
15. Suitable sediment control devices ("in pit” pollution control devices) shall be temporarily installed into the
first existing external downstream stormwater structure.
These devices are to be checked and cleaned on a regular basis and specifically after each rain event.
These devices are to remain in place during the civil works and construction phases of the development.
MSOffice c:\docume~1\shesse\locals~1\temp\bcl technologies\easypdf 5\@bcl@98015328\@[email protected]
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalUsed in these records
Decision Notice - 010.2007.00001014.001 [As Published]Related documentApplication case desk ↗
About this file
- File size
- 32 KB (small file)
- File type
No other editions are linked here.