BILL OF QUANTITIES
Project Ozcare Noosa - Fire Access Trail
Job No. STP24-0253
Date 15-Aug-24
BOQ Rev. A
CONSTRUCTION COST SUMMARY
SECTION ITEM AMOUNT
1 PRELIMINARIES $35,000
2 CLEARING & EARTHWORKS (INCL. RETAINING WALLS) $184,028
3 ROADWORKS $480,082
4 STORMWATER RETICULATION $58,353
5 EROSION & SEDIMENT CONTROL WORKS $56,555
SUB TOTAL (EXCLUSIVE OF GST) $814,018
GST $81,402
TOTAL $895,420
NOTE: Drawings have not been approved for Operational Works, as a result quantities may change until final approval
Certified by: Mr Ken Miller
RPEQ No: 09053
QUANTITIES ILLUSTRATED HEREIN ARE ESTIMATES FOR TENDERERS INFORMATION ONLY. TENDERERS ARE REMINDED THAT THIS IS A LUMP SUM CONTRACT AND ALL QUANTITIES MUST BE CONFIRMED BY THE
TENDERER IN THEIR TENDER SUBMISSION.
Page 1 of 6 STP24-0253 Estimate of Costs-Site Civil Works-Rev A.xls
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalFull text of the other 5 pages
Page 2
ITEM NO. DESCRIPTION UNIT QUANTITY RATE TOTAL
SECTION 1 : PRELIMINARIES
1.1 Site establishment & disestablishment Item 1 10000.00 $ 10,000.00
1.2 Insurance Item 1 25000.00 $ 25,000.00
TOTAL SECTION 1
$ 35,000.00
PRELIMINARIES
QUANTITIES ILLUSTRATED HEREIN ARE ESTIMATES FOR TENDERERS INFORMATION ONLY. TENDERERS ARE REMINDED THAT THIS IS A LUMP SUM CONTRACT AND ALL QUANTITIES MUST BE CONFIRMED BY THE
TENDERER IN THEIR TENDER SUBMISSION.
Page 2 of 6 STP24-0253 Estimate of Costs-Site Civil Works-Rev A.xls
Page 3
ITEM NO. DESCRIPTION UNIT QUANTITY RATE TOTAL
SECTION 2 : CLEARING & EARTHWORKS
2.1 Temporary fence around construction area m 166 16.40 $ 2,722.40
2.2 Selective clearing and grubbing to roads and allotments as directed. ha 1.08 6045.00 $ 6,528.60
2.3 (a) Strip topsoil 100mm thick, stockpile as required.
(Net solid volume of cut) m3 480 7.70 $ 3,695.76
(b) Respread topsoil 100mm thick to verges and distrubed areas as required.
(Net solid volume of cut) m3 251 17.00 $ 4,270.58
(c) Dispose of excess topsoil off site as required. (Net
solid volume of cut). m3 229 18.50 $ 4,232.02
2.4 Remove & dispose of redundant infrastructure and surplus material including Lump
concrete kerbing, driveway crossovers, road surfacing etc. $ 30,000.00
Sum
2.5 Remove & dispose of trees complete including removal, cartage, dumping, and
backfilling and trimming of area with on site material No 94 255.00 $ 23,970.00
2.6 Earthworks, No Bulking Factor (Net Solid Volume of Cut)
(a) On leads to Roads and Drains m3 794 15.20 $ 12,068.80
(b) Imported Fill (20% Bulking Factor) m3 1059 60.00 $ 63,540.00
2.7 Supply and install Design and Construct Sleeper retaining wall complete Lump
$ 25,000.00
Sum
2.8 Construction water Item 1 8000.00 $ 8,000.00
TOTAL SECTION 2
$ 184,028.15
EARTHWORKS
QUANTITIES ILLUSTRATED HEREIN ARE ESTIMATES FOR TENDERERS INFORMATION ONLY. TENDERERS ARE REMINDED THAT THIS IS A LUMP SUM CONTRACT AND ALL QUANTITIES MUST BE CONFIRMED BY THE
TENDERER IN THEIR TENDER SUBMISSION.
Page 3 of 6 STP24-0253 Estimate of Costs-Site Civil Works-Rev A.xls
Page 4
ITEM NO. DESCRIPTION UNIT QUANTITY RATE TOTAL
SECTION 3 : ROADWORKS
3.1 Provision for Traffic Item 1 1,780.00 $ 1,780.00
3.2 Roll, grade and trim subgrade m2 1178 2.95 $ 3,475.10
3.3 Paving material complete including compaction (Compacted Volume)
(a) Base Course - Class 2.1 m3 51 191.80 $ 9,839.34
(b) Sub-base Course - Class 2.4 m3 177 159.90 $ 28,254.33
3.4 Concrete pavement as specified, complete including supply, broom, jointing,
reinforcement, lay, compaction and testing.
(a) 150mm Thick, N32, SL82 Mesh m2 761 233.80 $ 177,921.80
3.5 Supply and lay concrete kerb and kerb and channel including compaction of
foundation, trim bedding gravel, complete .
(a) Layback kerb & channel B1 m 38 98.10 $ 3,727.80
(b) Barrier kerb B2 m 205 78.50 $ 16,081.12
(c) Edge Restraint ER2 m 24 88.30 $ 2,119.20
(c) 900 Wide Channel m 27 175.50 $ 4,738.50
3.6 Concrete pathway, complete in accordance with design drawings
(a) 100mm Thick, N32, SL72 Mesh m2 982 187.10 $ 183,732.20
3.7 Supply and install rock scour protection to causeway crossings in accordance with
design drawings complete m2 72 112.30 $ 8,085.60
3.8 Adjustment to services as required Lump
$ 25,000.00
Sum
3.9 Supply and install Kerb Ramp complete in accordance with design drawings No. 2 1,186.00 $ 2,372.00
3.9 Supply and install precast concrete wheel stops No. 14 52.20 $ 730.80
3.10 Supply and install PWD Bollard complete in accordance with design drawings No. 1 224.40 $ 224.40
3.11 Supply and install pavement marking for car park an roads in accordance with the Lump
design drawings $ 12,000.00
Sum
TOTAL SECTION 3
$ 480,082.19
ROADWORKS
QUANTITIES ILLUSTRATED HEREIN ARE ESTIMATES FOR TENDERERS INFORMATION ONLY. TENDERERS ARE REMINDED THAT THIS IS A LUMP SUM CONTRACT AND ALL QUANTITIES MUST BE CONFIRMED BY THE
TENDERER IN THEIR TENDER SUBMISSION.
Page 4 of 6 STP24-0253 Estimate of Costs-Site Civil Works-Rev A.xls
Page 5
ITEM NO. DESCRIPTION UNIT QUANTITY RATE TOTAL
SECTION 4 : STORMWATER DRAINAGE
4.1 Supply, lay and joint BlackMAX PE pipes, including trench excavation, bedding and
surround sand, backfill, compaction and disposal of spoil as specified:-
(a) 600mm dia m 23 360.70 $ 8,156.51
(b) 750mm dia m 36 432.90 $ 15,584.40
4.2 Construct Grated Field Inlet pits grate cover and surround to existing pit as per design
drawings complete
(a) 600x600 No 1 6,112.00 $ 6,112.00
(c) 900x900 No 1 7,640.00 $ 7,640.00
4.3 Supply and install Humeceptor STC-3 GPT complete in accordance with design
drawings and suppliers specifications No 1 25,000.00 $ 25,000.00
4.4 Modifications to existing inlet pits complete in accordance with design drawings No 2 3,820.00 $ 7,640.00
4.5 Modifications to exisitng access chambers complete in accordance with design
drawings No 1 4,584.00 $ 4,584.00
4.6 Modifications to existing outlet structures in accordance with design drawings No 1 5,500.80 $ 5,500.80
4.7 Supply and install precast concrete headwall to stormwater outlet complete
(a) 600mm dia No 1 1,875.80 $ 1,875.80
TOTAL SECTION 4
$ 58,352.60
STORMWATER DRAINAGE
QUANTITIES ILLUSTRATED HEREIN ARE ESTIMATES FOR TENDERERS INFORMATION ONLY. TENDERERS ARE REMINDED THAT THIS IS A LUMP SUM CONTRACT AND ALL QUANTITIES MUST BE CONFIRMED BY THE
TENDERER IN THEIR TENDER SUBMISSION.
Page 5 of 6 STP24-0253 Estimate of Costs-Site Civil Works-Rev A.xls
Page 6
ITEM NO. DESCRIPTION UNIT QUANTITY RATE TOTAL
SECTION 5 : EROSION AND SEDIMENT CONTROL WORKS
5.1 Hydromulching to areas as indicated on design drawings inc establishment until on-
maintenance m2 2512 14.90 $ 37,430.33
5.2 Supply and install Sediment Fencing and Spill Through Weirs complete (As Required) Lump
in accordance with design drawings $ 12,000.00
Sum
5.3 Supply and Place Gully Inlet protection complete, in accordance with design drawings
No 4 293.40 $ 1,173.60
5.4 Supply and install Sand Bag Check Dams complete, in accordance with design
No. 3 234.80 $ 704.40
drawings
5.6 Supply and place construction entry/exit grate complete, in acordance with design
No 1 5,246.70 $ 5,246.70
drawings.
TOTAL SECTION 5
$ 56,555.03
EROSION AND SEDIMENT CONTROL WORKS
QUANTITIES ILLUSTRATED HEREIN ARE ESTIMATES FOR TENDERERS INFORMATION ONLY. TENDERERS ARE REMINDED THAT THIS IS A LUMP SUM CONTRACT AND ALL QUANTITIES MUST BE CONFIRMED BY THE
TENDERER IN THEIR TENDER SUBMISSION.
Page 6 of 6 STP24-0253 Estimate of Costs-Site Civil Works-Rev A.xls
Used in these records
Bill of Quantities.pdfRelated documentApplication case desk ↗
About this file
- File size
- 122 KB (small file)
- File type
No other editions are linked here.