BILL OF QUANTITIES

Project        Ozcare Noosa - Fire Access Trail
Job No.        STP24-0253
Date           15-Aug-24
BOQ Rev.       A

                                      CONSTRUCTION COST SUMMARY

 SECTION                                                       ITEM                                                                                              AMOUNT

     1         PRELIMINARIES                                                                                                                                         $35,000

     2         CLEARING & EARTHWORKS (INCL. RETAINING WALLS)                                                                                                        $184,028

     3         ROADWORKS                                                                                                                                            $480,082

     4         STORMWATER RETICULATION                                                                                                                               $58,353

     5         EROSION & SEDIMENT CONTROL WORKS                                                                                                                      $56,555

                                     SUB TOTAL (EXCLUSIVE OF GST)                                                                                                   $814,018
                                                 GST                                                                                                                 $81,402
                                                TOTAL                                                                                                               $895,420

           NOTE: Drawings have not been approved for Operational Works, as a result quantities may change until final approval

                                                  Certified by: Mr Ken Miller
                                                       RPEQ No: 09053

QUANTITIES ILLUSTRATED HEREIN ARE ESTIMATES FOR TENDERERS INFORMATION ONLY. TENDERERS ARE REMINDED THAT THIS IS A LUMP SUM CONTRACT AND ALL QUANTITIES MUST BE CONFIRMED BY THE
                                                                     TENDERER IN THEIR TENDER SUBMISSION.




                                                                                  Page 1 of 6                         STP24-0253 Estimate of Costs-Site Civil Works-Rev A.xls
Full text of the other 5 pages

Page 2

ITEM NO.                                              DESCRIPTION                                                       UNIT QUANTITY              RATE           TOTAL
                                                SECTION 1 : PRELIMINARIES

    1.1        Site establishment & disestablishment                                                                    Item          1         10000.00      $ 10,000.00

    1.2        Insurance                                                                                                Item          1         25000.00      $ 25,000.00



                                                       TOTAL SECTION 1
                                                                                                                                                              $ 35,000.00
                                                        PRELIMINARIES

QUANTITIES ILLUSTRATED HEREIN ARE ESTIMATES FOR TENDERERS INFORMATION ONLY. TENDERERS ARE REMINDED THAT THIS IS A LUMP SUM CONTRACT AND ALL QUANTITIES MUST BE CONFIRMED BY THE
                                                                     TENDERER IN THEIR TENDER SUBMISSION.




                                                                                  Page 2 of 6                         STP24-0253 Estimate of Costs-Site Civil Works-Rev A.xls

Page 3

ITEM NO.                                             DESCRIPTION                                                        UNIT QUANTITY              RATE            TOTAL
                                         SECTION 2 : CLEARING & EARTHWORKS

    2.1        Temporary fence around construction area                                                                  m           166          16.40        $    2,722.40

    2.2        Selective clearing and grubbing to roads and allotments as directed.                                      ha         1.08         6045.00       $    6,528.60

    2.3        (a) Strip topsoil 100mm thick, stockpile as required.
               (Net solid volume of cut)                                                                                 m3          480           7.70        $    3,695.76

               (b) Respread topsoil 100mm thick to verges and distrubed areas as required.
               (Net solid volume of cut)                                                                                 m3          251          17.00        $    4,270.58

               (c) Dispose of excess topsoil off site as required.                                               (Net
               solid volume of cut).                                                                                     m3          229          18.50        $    4,232.02


    2.4        Remove & dispose of redundant infrastructure and surplus material including                              Lump
               concrete kerbing, driveway crossovers, road surfacing etc.                                                                                     $ 30,000.00
                                                                                                                         Sum


    2.5        Remove & dispose of trees complete including removal, cartage, dumping, and
               backfilling and trimming of area with on site material                                                    No          94           255.00      $ 23,970.00


    2.6        Earthworks, No Bulking Factor (Net Solid Volume of Cut)
               (a) On leads to Roads and Drains                                                                          m3          794          15.20       $ 12,068.80
               (b) Imported Fill (20% Bulking Factor)                                                                    m3         1059          60.00       $ 63,540.00

    2.7        Supply and install Design and Construct Sleeper retaining wall complete                                  Lump
                                                                                                                                                              $ 25,000.00
                                                                                                                         Sum


    2.8        Construction water                                                                                       Item          1          8000.00       $    8,000.00



                                                       TOTAL SECTION 2
                                                                                                                                                              $ 184,028.15
                                                        EARTHWORKS

QUANTITIES ILLUSTRATED HEREIN ARE ESTIMATES FOR TENDERERS INFORMATION ONLY. TENDERERS ARE REMINDED THAT THIS IS A LUMP SUM CONTRACT AND ALL QUANTITIES MUST BE CONFIRMED BY THE
                                                                     TENDERER IN THEIR TENDER SUBMISSION.




                                                                                  Page 3 of 6                         STP24-0253 Estimate of Costs-Site Civil Works-Rev A.xls

Page 4

ITEM NO.                                               DESCRIPTION                                                      UNIT QUANTITY              RATE            TOTAL
                                                  SECTION 3 : ROADWORKS

    3.1        Provision for Traffic                                                                                    Item          1          1,780.00      $    1,780.00

    3.2        Roll, grade and trim subgrade                                                                             m2         1178           2.95        $    3,475.10

    3.3        Paving material complete including compaction (Compacted Volume)
               (a) Base Course - Class 2.1                                                                               m3          51           191.80       $    9,839.34
               (b) Sub-base Course - Class 2.4                                                                           m3          177          159.90      $ 28,254.33

    3.4        Concrete pavement as specified, complete including supply, broom, jointing,
               reinforcement, lay, compaction and testing.
               (a) 150mm Thick, N32, SL82 Mesh                                                                           m2          761          233.80       $ 177,921.80

    3.5        Supply and lay concrete kerb and kerb and channel including compaction of
               foundation, trim bedding gravel, complete .
               (a) Layback kerb & channel B1                                                                             m           38           98.10        $    3,727.80
               (b) Barrier kerb B2                                                                                       m           205          78.50       $ 16,081.12
               (c) Edge Restraint ER2                                                                                    m           24           88.30        $    2,119.20
               (c) 900 Wide Channel                                                                                      m           27           175.50       $    4,738.50

    3.6        Concrete pathway, complete in accordance with design drawings
               (a) 100mm Thick, N32, SL72 Mesh                                                                           m2          982          187.10       $ 183,732.20

    3.7        Supply and install rock scour protection to causeway crossings in accordance with
               design drawings complete                                                                                  m2          72           112.30       $    8,085.60


    3.8        Adjustment to services as required                                                                      Lump
                                                                                                                                                              $ 25,000.00
                                                                                                                        Sum


    3.9        Supply and install Kerb Ramp complete in accordance with design drawings                                  No.          2          1,186.00      $    2,372.00

    3.9        Supply and install precast concrete wheel stops                                                           No.         14           52.20        $      730.80

   3.10        Supply and install PWD Bollard complete in accordance with design drawings                                No.          1           224.40       $      224.40

   3.11        Supply and install pavement marking for car park an roads in accordance with the                        Lump
               design drawings                                                                                                                                $ 12,000.00
                                                                                                                        Sum



                                                       TOTAL SECTION 3
                                                                                                                                                               $ 480,082.19
                                                         ROADWORKS

QUANTITIES ILLUSTRATED HEREIN ARE ESTIMATES FOR TENDERERS INFORMATION ONLY. TENDERERS ARE REMINDED THAT THIS IS A LUMP SUM CONTRACT AND ALL QUANTITIES MUST BE CONFIRMED BY THE
                                                                     TENDERER IN THEIR TENDER SUBMISSION.




                                                                                  Page 4 of 6                         STP24-0253 Estimate of Costs-Site Civil Works-Rev A.xls

Page 5

ITEM NO.                                              DESCRIPTION                                                       UNIT QUANTITY              RATE            TOTAL
                                          SECTION 4 : STORMWATER DRAINAGE

    4.1        Supply, lay and joint BlackMAX PE pipes, including trench excavation, bedding and
               surround sand, backfill, compaction and disposal of spoil as specified:-
               (a) 600mm dia                                                                                             m           23           360.70      $ 8,156.51
               (b) 750mm dia                                                                                             m           36           432.90      $ 15,584.40

    4.2        Construct Grated Field Inlet pits grate cover and surround to existing pit as per design
               drawings complete
               (a) 600x600                                                                                               No           1          6,112.00      $    6,112.00
               (c) 900x900                                                                                               No           1          7,640.00      $    7,640.00

    4.3        Supply and install Humeceptor STC-3 GPT complete in accordance with design
               drawings and suppliers specifications                                                                     No           1         25,000.00     $ 25,000.00


    4.4        Modifications to existing inlet pits complete in accordance with design drawings                          No           2          3,820.00      $    7,640.00

    4.5        Modifications to exisitng access chambers complete in accordance with design
               drawings                                                                                                  No           1          4,584.00      $    4,584.00


    4.6        Modifications to existing outlet structures in accordance with design drawings                            No           1          5,500.80      $    5,500.80

    4.7        Supply and install precast concrete headwall to stormwater outlet complete
               (a) 600mm dia                                                                                             No           1          1,875.80      $    1,875.80



                                                     TOTAL SECTION 4
                                                                                                                                                              $ 58,352.60
                                                  STORMWATER DRAINAGE

QUANTITIES ILLUSTRATED HEREIN ARE ESTIMATES FOR TENDERERS INFORMATION ONLY. TENDERERS ARE REMINDED THAT THIS IS A LUMP SUM CONTRACT AND ALL QUANTITIES MUST BE CONFIRMED BY THE
                                                                     TENDERER IN THEIR TENDER SUBMISSION.




                                                                                  Page 5 of 6                         STP24-0253 Estimate of Costs-Site Civil Works-Rev A.xls

Page 6

ITEM NO.                                                  DESCRIPTION                                                   UNIT QUANTITY              RATE            TOTAL
                               SECTION 5 : EROSION AND SEDIMENT CONTROL WORKS

    5.1        Hydromulching to areas as indicated on design drawings inc establishment until on-
               maintenance                                                                                               m2         2512          14.90       $ 37,430.33


    5.2        Supply and install Sediment Fencing and Spill Through Weirs complete (As Required) Lump
               in accordance with design drawings                                                                                                             $ 12,000.00
                                                                                                   Sum

    5.3        Supply and Place Gully Inlet protection complete, in accordance with design drawings
                                                                                                                         No           4           293.40       $    1,173.60


    5.4        Supply and install Sand Bag Check Dams complete, in accordance with design
                                                                                                                         No.          3           234.80       $      704.40
               drawings


    5.6        Supply and place construction entry/exit grate complete, in acordance with design
                                                                                                                         No           1          5,246.70      $    5,246.70
               drawings.



                                                 TOTAL SECTION 5
                                                                                                                                                              $ 56,555.03
                                       EROSION AND SEDIMENT CONTROL WORKS

QUANTITIES ILLUSTRATED HEREIN ARE ESTIMATES FOR TENDERERS INFORMATION ONLY. TENDERERS ARE REMINDED THAT THIS IS A LUMP SUM CONTRACT AND ALL QUANTITIES MUST BE CONFIRMED BY THE
                                                                     TENDERER IN THEIR TENDER SUBMISSION.




                                                                                  Page 6 of 6                         STP24-0253 Estimate of Costs-Site Civil Works-Rev A.xls

Used in these records

About this file

File size
122 KB (small file)
File type
PDF

No other editions are linked here.

Original file

Log in to download the original file

Bill of Quantities.pdf · 122 KB (small file)

The supporting record

Open full page ↗

Source document

Analyse documents ↗Open full page ↗

My Comparisons

Choose two to four records of the same kind. Drag using a handle or use the “Compare” buttons.

Your selected records are saved in this browser for your account. Results use the filters on the page where you choose “Compare selected”.