EMP – CONSTRUCTION PHASE 4-34
12. Wheelbarrows and other mortar/concrete receptacles are to be cleaned out in designated areas
only which are sealed with material removed from site.
13. All brick and concrete cutting by-products are to be collected and removed from site.
14. Clean-up of equipment to be conducted in designated safe areas only. No wash water from
clean-ups will be permitted to enter the stormwater system.
15. Stormwater is to be diverted around storage areas and bunded refuelling areas.
16. All earthmoving equipment held on site is to be parked in a bunded and lined area.
17. No major maintenance is to be carried out on site. Minor maintenance is to be carried out within
the bunded and lined area.
18. The location of areas where waste or other potentially hazardous material is to be stored is to be
determined prior to construction commencing (refer Element D.3). Such areas are to be
appropriately signed.
Performance Requirement: No hazardous substances are released to the surrounding environment.
Monitoring: Regular inspection of storage areas.
Reporting: Site Environmental Officer to report any incidents involving hazardous substances to
appropriate authorities. Monthly report to Superintendent to include records of any incidents and any
corrective action. Hazardous substance register to be available on site at all times.
Corrective Action: Review all hazardous substance handling and storage procedures.
G:\ADMIN\B15184.G.DAH\R.B15184.001.05..DOC 22/7/05 10:07
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalLog in to download the original file
The download may take a few minutes. On mobile data, it is best to wait for Wi-Fi.