SITE MANAGEMENT RULES FOR ENVIRONMENTAL PROTECTION – CONSTRUCTION PHASE B-4
G) Erosion and sediment control
1. No sediment is to be discharged to the natural drainage lines or wetland.
2. All on site works and disturbed areas are to be located within areas protected by
sediment and erosion control works.
3. Any damage to water quality, erosion and sediment control structures is to be
repaired immediately.
H) Community Relations
1. Site personnel are to respect the privacy of residents of the area and take actions to
minimise any nuisance.
2. Any complaints are to be reported immediately to the Principal Contractor or SEO.
DECLARATION
I have read, understood and will comply with the Site Management Rules during the construction of
the project.
Name:………………………………
Employer………………………….Signature………………………………Date……..
Authorisation:……………………………………………………………..(signature of Principal
Contractor or SEO and date) (copy of site plan showing management areas to be provided)
(note – the above declaration is to be detachable and copies retained by the employee and Principal
Contractor)
G:\ADMIN\B15184.G.DAH\R.B15184.001.05..DOC 22/7/05 10:07
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalLog in to download the original file
The download may take a few minutes. On mobile data, it is best to wait for Wi-Fi.