     (a) traffic management during ail aspects of the construction phase including:
             (i) a Traffic Management Control Plan in accordance with the Manual of
                      Uniform Traffic Control Devices (MUTCD) detailing all temporary
                     signage and traffic control measures prior to construction;
             (ii) maintenance of safe access along Hollett Road both during daily
                     construction and after daily construction has ceased;
             (iii) proposed fencing to the site during the construction phase of the
                     development; and
             (iv) approval of the Traffic Management Control Plan by the Department
                     of Main Roads (DMR) for any works on State controlled roads;
     (b) maintenance and protection of water quality and existing drainage lines
            through the construction site, through the implementation of appropriate
             erosion and sediment control measures;
     (c) works programme identifying key components of the works and their
             respective durations;
     (d) establishment of a communication protocol with the general public, adjoining
             owners, emergency services and local businesses to advise of agreed
             construction times, impacts on traffic and services and other relevant issues;
     (e) identification of complaint management procedures including:
             (i) contact details for the on-site manager; and
             (ii) dispute resolution procedures;
     (0 details on the location of external fill sites/sources, the haulage route, type of
             vehicle to be utilised during filling operations and frequency of usage. NB
             any damage to the existing road system as a result of haulage operations
             shall be fully repaired at the applicant's expense; and
     (g) it is acknowledged that the Construction Management Plan will be a draft
               document requiring finalisation upon appointment of the Principal Contractor
               employed to construct the works and a final document will be required to be
             submitted at the Pre-Start Meeting for the project.
     Lawful Point of Discharge
     The applicant is advised that a lawful point of discharge for the development will need
     to be determined and demonstrated as part of a detailed design solution included with
     the Operational Works application.
     Works within a Watercourse
8.   The applicant is advised that the proposal will involve works within a watercourse
     which will require referral to the Department of Environment & Resource
     Management under the Water Act 2000 and Sustainable Planning Act 2009 at the
     time of making an application for operational works.
     Qualified Person
9.   For the purpose of preparing an Acid Soil and Groundwater Management Plan, a
     qualified person is considered to be either:
     (a) a Registered Professional Engineer of Queensland (RPEQ); or
     (b) a soil scientist with a minimum of 5 years experience.
10   For the purpose of preparing a Flood Study and certifying flood levels for the
     development, a qualified person is considered to be a Registered Professional
     Engineer of Queensland (RPEQ) experienced in hydraulics and hydrology.
     For the purpose of certifying acoustic treatments for the development, a qualified
     person is considered to be either:


                                                                                          15

Used in these records

About this file

File size
1.9 MB (small file)
File type
PDF

No other editions are linked here.

Original file

Log in to download the original file

P & E Court Appeal No 344 of 2009 Judgement 5_07_13 - Hofmann.pdf · 1.9 MB (small file)

The supporting record

Open full page ↗

Source document

Analyse documents ↗Open full page ↗

My Comparisons

Choose two to four records of the same kind. Drag using a handle or use the “Compare” buttons.

Your selected records are saved in this browser for your account. Results use the filters on the page where you choose “Compare selected”.