Decision Notice - 010.2007.00000567.001 [As Published] · 132007.567

of 12

Text shows just the words. Original shows the document exactly as it was published.

NOOSA COUNCIL IDAS Development Application Decision Notice                                                4 of 12


15.   A condition survey is to be carried out of adjoining buildings, structures and services prior to any
      demolition works or construction works taking place on site. If distress already exists, a photographic
      survey shall be undertaken, the distress measured and a plan to monitor changes to distress shall be
      implemented.

16.   Infrastructure including reticulated water, sewerage, stormwater, and electricity are to be protected from
      damage and made safe to the standard required by the regulatory authority;

17.   All infrastructure must be disconnected, capped or sealed including:-
             electricity meters removed and electrical wires disconnected; and

             telephone lines are disconnected; and

             high speed data cables and television provider boxes are disconnected and removed to the
             standard required by the regulatory authority;


18.   All building materials containing asbestos, including asbestos cement sheeting or roofing and lagging,
      must be removed from the building and disposed of in accordance with industry best practice.

19.   Waste generated during construction must be stockpiled in a centralised location and covered as required
      to prevent material being blown onto adjoining properties including the road reserve or food waste from
      generating vermin. All site waste must be disposed of to an approved waste disposal facility either directly
      or via an approved waste receptacle and collection service. Storage areas are to be located near the
      temporary access to the site so that access can be gained with out damage to infrastructure.

20.   A temporary crossing must be provided to protect road reserve infrastructure including kerb and channel;

21.   Any damage to footpaths, street plantings, kerb and channel or roadways at the removal site, the
      relocation site or between the sites must be repaired or reinstated to at least pre-existing conditions.

22.   Sediment and erosion control measures must be placed on site prior to the works commencing and shall
      be maintained until all works are complete. The erosion and sediment control measures shall be in
      accordance with the “Best practice guidelines for control of stormwater on building sites” prepared by
      Healthy Waterways (copy attached or available at www.healthywaterways.org).

23.   All disturbed areas must be revegetated or otherwise stabilised at the completion of the works. Disturbed
      areas are revegetated using species identified in PSP3 – Landscaping Plants and Guidelines.

24.   The transportation of all materials to and from the site must be undertaken in a manner such that no
      particle matter escapes onto a public road. All vehicles carrying out materials either to or from the site
      shall be covered to prevent materials including dust being windblown from the vehicle.

25.   A Waste Management Plan shall be submitted for the demolition, to the Land Use Section of the Noosa
      Council prior to the development permit for building works being issued. The Plan shall contain the
      following information:
        MATERIALS ON-SITE                     DESTINATION
                                              Re-use and Recycling             Disposal
        Expected       waste    Estimated     On-site              Off-site           *Specify contractor
        materials               volume        *specify proposed *specify contractor and landfill site
                                (m³)          re-use or on-site and recycling outlet
                                              recycling methods
        Excavation material
        Green waste
        Bricks
        Concrete
        Timber-please
        specify
        Plasterboard
        Metals    -   please
        specify
        Asbestos
        Other    -    please
        specify




AOP2 c:\docume~1\aop2\locals~1\temp\bcl technologies\easypdf 5\@bcl@380572d6\@[email protected]

Used in these records

About this file

File size
60 KB (small file)
File type
PDF

No other editions are linked here.

Original file

Log in to download the original file

Decision Notice - 010.2007.00000567.001 [As Published].pdf · 60 KB (small file)

The supporting record

Open full page ↗

Source document

Analyse documents ↗Open full page ↗

My Comparisons

Choose two to four records of the same kind. Drag using a handle or use the “Compare” buttons.

Your selected records are saved in this browser for your account. Results use the filters on the page where you choose “Compare selected”.