NOOSA COUNCIL IDAS Development Application Decision Notice                                                  6 of 12


37.   A new 1.5m wide concrete path shall be constructed along the Edward Street frontage of the site in
      accordance with Council’s design standards and to an alignment that protects any significant vegetation
      or any underground services.

38.   All paths, driveways and parking areas shall be designed and constructed to ensure pedestrian safety
      using non-slip materials, to produce an evenly graded surface finish, and to be in accordance with the
      Disability Discrimination Act 1992 and Australian Standard 1428.1 Design for Access & Mobility.

39.   All redundant vehicular crossings to the site shall be removed and replaced by kerb & channel, footpath
      paving and landscaping such as trees and grasses in accordance with Council’s Standard specifications
      prior to commencement of the use permitted by this permit.
Roof Water & Stormwater Drainage
40.   Roof runoff from any new dwelling shall be directed to a rainwater storage system or tank (minimum
      storage 3000 litres per attached dwelling/unit) that is installed to ensure water from the tank is used for
      external uses (such as watering gardens, irrigation, ornamental ponds, water features, topping-up
      swimming pools, outdoor cleaning, etc) and for use in flushing of toilets internal to the dwelling. All
      rainwater tanks are to be designed and installed in accordance with the Queensland Development Code
      (QDC), Part 25 – Rainwater Tanks, and shall be part of the plumbing application in conjunction with the
      building approval. The location and capacity of the tanks shall be clearly shown on the plans submitted
      for Building Works / Operational Works approval and any overflow shall be directed to the stormwater
      drainage system.

41.   All stormwater drainage (including roof water overflow from the rainwater storage system) shall be
      collected and discharged so there is no net increase in stormwater runoff from the site. Stormwater
      drainage permitted to drain from the site shall be discharged to Council’s kerb & channel street drainage
      system in Edward Street. Plans of the drainage design shall be prepared by a Registered Professional
      Civil Engineer and submitted to Council prior to obtaining a Development Permit for Operational Works.
      The maximum discharge of stormwater drainage allowable to Council’s kerb & channel street drainage
      system at any one location is 25 litres/second.
42.   As the site is proposed to be filled, appropriate stormwater drainage pipes shall be installed within the site
      to collect and discharge stormwater runoff from all adjoining properties to prevent additional
      ponding/flooding on these properties.

43.   Drainage of the site shall be in accordance with the principles of Council’s - Noosaville Master Drainage
      Plan to ensure that the site discharges to the appropriate drainage catchments. This information can be
      obtained from Council’s Technical Officer - Development, by contacting 5449 5263.
Sewer Mains
44.   The site shall be connected to Council’s existing sewerage reticulation systems and be constructed in
      accordance with Council’s standards and requirements at no cost to Council.

45.   The existing sewer main that traverses the site at the rear and the ‘zone of influence’ (taken as the area
      within a 45-degree angle measured from the invert of the sewer main to the finished surface level) shall
      be accurately located and determined by a suitably qualified Licensed Surveyor and shown on all plans
      submitted for Operational Works approval.
      To ensure Council’s sewer main is accessible for maintenance purposes and is protected from risk of
      damage no structures requiring a building permit (eg. buildings, swimming pools, retaining walls
      exceeding 1m in height, raised terraces, etc) shall be constructed within this ‘zone of influence’ or within
      1.5m of the centreline of the sewer main, whichever is the greater. As such the applicant shall amend
      Operational Works plans including Building plans to ensure compliance.

Town Water Supply
46.   The site shall be connected to Council’s existing town water supply and be constructed in accordance with
      Council’s standards and requirements at no cost to Council.

47.   Each individual water connection to the water reticulation system shall extend to the property boundary
      and be metered. All fees for the supply of water meters shall be paid to the Council.

48.   All water meters must be located outside the property boundary and in an easily assessable location to
      facilitate unhindered reading by Council and/or Council’s contracted water meter readers, and not behind
      fences or locked gates. In this regard approval of the water meter configuration and location must be
      obtained from Council’s Water & Sewerage Capital Works Manager prior to lodgement and approval of
      hydraulic drawings.




AOP2 c:\docume~1\aop2\locals~1\temp\bcl technologies\easypdf 5\@bcl@380572d6\@[email protected]

Used in these records

About this file

File size
60 KB (small file)
File type
PDF

No other editions are linked here.

Original file

Log in to download the original file

Decision Notice - 010.2007.00000567.001 [As Published].pdf · 60 KB (small file)

The supporting record

Open full page ↗

Source document

Analyse documents ↗Open full page ↗

My Comparisons

Choose two to four records of the same kind. Drag using a handle or use the “Compare” buttons.

Your selected records are saved in this browser for your account. Results use the filters on the page where you choose “Compare selected”.