NOOSA COUNCIL IDAS Development Application Decision Notice                                                 8 of 12


Erosion and Sediment Control
56.   Any person acting on this permit shall prevent erosion and sediment export from leaving the site. Site
      control measures such as silt fencing, controlled gravel access to the site and controlled disposal of
      waste, will be necessary.
      In this regard plans detailing the methods of controlling erosion and sediment are required to be submitted
      to the Council for approval prior to obtaining a Development Permit for Operational Works.

Contributions Towards Council Infrastructure
57.   Monetary contributions shall be paid to Noosa Council towards the cost of providing and/or upgrading
      various infrastructure at the rates applicable at the time of payment. An estimate only of the contribution
      amounts under the current Council policies and requirements is outlined in the table below:

          Contribution Required For:                                                          Amount:
          PSP12 – Public Open Space Contributions (Park)                                      $811
          PSP16 – Sewerage Headworks Contributions                                            $707
          PSP17 – Water Supply Headworks Contributions                                        $785
          PSP20 – Pathway Trunk Network Contributions                                         $182
          TOTAL Contribution Amount =                                                         $ 2,485
          Please note, that these amounts are all subject to variations in the Consumer Price Index, All
          Groups Brisbane from June 2007 until the date of payment.

      All contributions must be paid prior to the issue of a Development Permit for Operational Works.
      Alternatively a trading bank guarantee shall be submitted to Council plus 20%. Should the contributions
      not be paid at the due time, Council shall call upon the trading bank guarantee in full.
      Processing of bonds for security where specific Council approval has been given for the bonding of
      contributions will incur an administration fee in accordance with Council’s Land Development Commercial
      & Regulatory Fees at the time of lodgement.
      In the event that the Development Permit for Material Change of Use of Premises lapses or is cancelled,
      the trading bank guarantee will be returned.

General
58.   For the following classes of work associated with development, a Development Permit for Operational
      Works must be obtained prior to commencement of works relating to that class of work. The application
      may combine any or all of these classes of work:-
      58.1.    Access and/or Carparking.
      58.2.    Stormwater Drainage.
      58.3.    Frontage Works.
      58.4.    Erosion & Sediment Control
59.   A suitably qualified Registered Professional Engineer shall prepare engineering drawings and
      specifications for all engineering works that will become Council infrastructure, which shall be submitted in
      conjunction with an application for a Development Permit for Operational Works. To avoid conflict with
      underground pipes or services, all existing and proposed services required by the development shall be
      shown on the plans.

60.   Any alteration of any public utility or other facilities necessitated by the development of the land or
      associated construction works external to the site shall be at no cost to Council.

61.   The transportation of all materials to and from the site shall be undertaken in a manner such that no
      particle matter escapes onto a public road. All vehicles carrying materials either to or from the site shall
      be covered to prevent materials including dust being windblown from the vehicle.
Environmental Health
62.   The developer must provide waste storage and disposal facilities in accordance with Planning Scheme
      Policy “Waste Management Multi-Dwellings and Commercial and Industrial Premises”, including an
      external imperviously paved area correctly sized for all refuse and recycling containers and suitably
      screened from public places and neighbouring properties.




AOP2 c:\docume~1\aop2\locals~1\temp\bcl technologies\easypdf 5\@bcl@380572d6\@[email protected]

Used in these records

About this file

File size
60 KB (small file)
File type
PDF

No other editions are linked here.

Original file

Log in to download the original file

Decision Notice - 010.2007.00000567.001 [As Published].pdf · 60 KB (small file)

The supporting record

Open full page ↗

Source document

Analyse documents ↗Open full page ↗

My Comparisons

Choose two to four records of the same kind. Drag using a handle or use the “Compare” buttons.

Your selected records are saved in this browser for your account. Results use the filters on the page where you choose “Compare selected”.