Skip to the record
Mmm.. taste the original NoosaWatch™

Original source · versioned page text

MCU12/0041 - Adopted Infrastructure Charge Notice 509 - Rev 1

of 2

Page text shows just the words. Original shows the document exactly as it was published.

                                                                                 Locked Bag 72, Sunshine Coast Mail Centre, QLD 4560
                                                                                 Phone (07) 5475 7272         Fax (07) 5475 7277
                                                                                 ABN 37 876 973 913



                ADOPTED INFRASTRUCTURE CHARGE NOTICE
To:        Mr Darren John Knowles
           C/- Max Watterson & Associates
           PO Box 639                                                                       Date of Issue:   09 October 2013
           COOROY       4563                                                                Adopted Charge Notice No: 509
                                                                                            Rev No: 1


 LAND TO WHICH THE INFRASTRUCTURE CHARGE APPLIES:
 Planning Scheme:                The Noosa Plan
 Property Description:           Lot 7 MCH 793
 Property Address:               429 Kennedys Rd POMONA QLD 4568

 DEVELOPMENT TO WHICH THE ADOPTED INFRASTRUCTURE CHARGE APPLIES
 The adopted infrastructure charge applies to the following development type: Material Change of Use
 Development Approval/Compliance reference number: MCU12/0041

 AMOUNT OF THE ADOPTED INFRASTRUCTURE CHARGE
      The adopted infrastructure charge has been calculated in accordance with an adopted infrastructure charges resolution
       under the Sustainable Planning Act 2009.
  The amount of the adopted infrastructure charge is to be escalated in accordance with relevant legislation from the date on
       the notice to the date of payment.

  ADOPTED INFRASTRUCTURE CHARGE AMOUNT (@ Jun 2013 index) = $1,680.00

 APPORTIONMENT OF ADOPTED INFRASTRUCTURE CHARGE:

                              Allocation of adopted infrastructure charge to trunk infrastructure networks
      Entity
                                                                                           Charge          Offset / Rebate        Net Payable
                                                                                                                                (@ Jun 2013 Index)

                 Water Supply                                                                     $0.00               $0.00                   $0.00
 Unitywater
                 Sewerage                                                                         $0.00               $0.00                   $0.00
                 Transport                                                                    $1,428.00               $0.00              $1,428.00
                 Public Parks & Land for Community Facilities                                   $252.00               $0.00                $252.00
      Council
                 Stormwater (Residential)                                                         $0.00               $0.00                   $0.00
                 Stormwater (Non-Residential)                                                     $0.00               $0.00                   $0.00
                                                                          TOTAL =
                                                                                              $1,680.00               $0.00              $1,680.00
                                (Subject to indexation applicable at date of payment)

 Basis of rebate:

 PAYMENT OF THE ADOPTED INFRASTRUCTURE CHARGE
      The adopted infrastructure charge is payable in accordance with the Sustainable Planning Act 2009.
      The due date for payment of the adopted infrastructure charge is: Before the Change of Use happens.
      The charge is to be paid to Sunshine Coast Regional Council via the Infrastructure Charges Officer, tel: (07) 5441 8679.
       Please contact Sunshine Coast Regional Council, Infrastructure Policy Branch, prior to making payment.
      Compound annual interest at 11% calculated daily is to be applied on an overdue charge.

 Notice is hereby given under the Sustainable Planning Act 2009 and the Local Government Act 2009 that the adopted infrastructure charge
 notice is levied by the Sunshine Coast Regional Council on the described land. The adopted infrastructure charge is DUE AND PAYABLE BY
 THE ABOVE DATE. The adopted infrastructure charge plus any arrears and interest may be recovered by legal process without further notice if
 unpaid after the expiration of the DUE DATE.
Log in to download the original file

MCU12_0041 - Adopted Infrastructure Charge Notice 509 - Rev 1.pdf · 31 KB (small file)

Searchable page text hides email addresses. Original files are unchanged and may show email addresses.

The supporting record

Open full page ↗

Source document

Analyse documents ↗Open full page ↗

My Comparisons

Choose two to four records of the same kind. Drag using a handle or use the “Compare” buttons.

Your selected records are saved in this browser for your account. Results use the filters on the page where you choose “Compare selected”.