INFRASTRUCTURE & SERVICES COMMITTEE MEETING AGENDA                                         2 FEBRUARY 2016


Civil Operations
2                        COOROY BELLI CREEK ROAD SLIP REPAIR - TENDER ASSESSMENT - 1516T040
DOCUMENT INFORM AT ION




Author                               Civil Operations Technical Officer, Cameron Shields
                                     Planning & Infrastructure Department

Index                                ECM \ Projects (T1) – Cooroy-Belli Crk Road Skip Repair – CAP. WORK
                                     500619
                                     ECM \ Subject \ Contracting \ Contracts Projects
                                     ECM \ Subject \ Contracting \ Roads Construction

Attachments                          1.    Tender Evaluation Matrix 1516T040


EXECUTIVE SUMMARY
Not applicable.

RECOMMENDATION
That Council note the report by the Civil Operations Technical Officer to the Infrastructure and
Services Committee dated 2 February 2016 and award tender 1516T040 to SGQ Pty Ltd for a
contract value of $268,658.00 (excl. GST).


REPORT
An extensive slip occurred on Cooroy Belli Creek Road, Cooroy, during Ex Tropical Cyclone Marcia
in February 2015. Since the event, Council have had extensive design and testing completed.
Several options have been considered for the repair work with the method of soil nailing and wire
mesh considered the most appropriate.

As the slip occurred during a declared disaster event that is recognised by the Queensland
Reconstruction Authority (QRA), Council has received approval for funding for the slip repair under
the National Disaster Relief and Recovery Arrangements (NDRRA).

Under the NDRRA, Noosa Council will be required to contribute 25% of funds once a nominated
cost trigger point of $293,857.00 (excl. GST) is reached, however, QRA will not fund the project if
the trigger point is not reached. The trigger point is determined by the State Government.

The total QRA approval is for $376,725 (excl. GST).

The slip design and report was completed by a local geotechnical consultant, Grinceri & Associates
Geotechnical. The report has recommended that the slip repair be broken down into 3 components:

i)                       Downhill Slip Repair
ii)                      Uphill Slope Stabilisation
iii)                     Culvert Replacement.

A copy of the report has been made available in the Councillors’ Room.




                                                                                               Page 10 of 41
Log in to download the original file

2016-02-02 Infrastructure & Services Committee Agenda(PDF, 2MB).pdf · 2.3 MB (large file)

Large file: the download may take up to a minute.

Searchable page text hides email addresses. Original files are unchanged and may show email addresses.

The supporting record

Open full page ↗

Source document

Analyse documents ↗Open full page ↗

My Comparisons

Choose two to four records of the same kind. Drag using a handle or use the “Compare” buttons.

Your selected records are saved in this browser for your account. Results use the filters on the page where you choose “Compare selected”.