EARTHWORKS NOTES
1. FOR GENERAL NOTES REFER DWG C01, WHICH IS TO BE REQUESTED AND VIEWED PRIOR TO COMMENCEMENT OF CONSTRUCTION IF NOT
CUT/FILL VOLUMES: SUPPLIED.
N
2. FOR DETAILED GEOTECHNICAL INFORMATION, REFER GEOTECHNICAL INVESTIGATION REPORT BY TECTONIC. IT IS RECOMMENDED THAT THE
(VOLUMES TO FINISHED SURFACE LEVEL) GEOTECHNICAL CONSULTANT BE CONTACTED TO CONFIRM THE SOIL CONDITIONS PRIOR TO EARTHWORKS COMMENCING.
3. GRASS AND TOPSOIL SHALL BE STRIPPED TO A MINIMUM DEPTH OF 100MM OVER THE EXTENT OF THE WORKS UNLESS DIRECTED OTHERWISE
TOTAL CUT: 612.60m³ AND STOCKPILED WHERE REQUIRED FOR FILL OF LANDSCAPING AREAS. TOPSOIL MATERIALS MUST NOT BE USED IN STRUCTURAL FILL.
4. UNSUITABLE NATURAL MATERIALS SUCH AS SATURATED, LOOSE OR SOFT MATERIALS ENCOUNTERED SHOULD BE REMOVED DURING
SUBGRADE PREPARATION FOR BULK EARTHWORKS. ALL UNSUITABLE MATERIAL TO BE REMOVED FROM SITE AT CONTRACTORS EXPENSE.
TOTAL FILL: 64.63m³ 5. COMPACTION OF THE EXPOSED SAND SUBGRADE REQUIRES SUBSTANTIAL VOLUMES OF WATER COMBINED WITH VIBRATORY COMPACTION
TEMPORARY SHORING AND/OR EQUIPMENT(E.G VIBRATING PLATE OR MINIMUM 4 TONNE VIBRATING SMOOTH DRUM ROLLER). CARE MUST BE TAKEN TO ENSURE THERE ARE
BATTERS IN ACCORDANCE WITH BALANCE: 547.98m³ CUT NO IMPACTS ON SURROUNDING STRUCTURES. MATERIAL TO BE COMPACTED IN ACCORDANCE WITH GEOTECHNICAL REPORT AND AS1289.
6. TEMPORARY SWALE DRAINS TO BE PROVIDED ALONG CREST AND TOE OF ANY CUTS AND ABOVE FILL BATTERS GRADING DISCHARGE TO A
GEOTECHNICAL CONSULTANTS CONTROL POINT FOR DISCHARGE TO EXISTING STORMWATER INFRASTRUCTURE IN ROAD RESERVE.
SPECIFICATIONS 7. A MINIMUM 150MM THICK GRANULAR WORKING PLATFORM MAY BE REQUIRED ON SOIL SUBGRADES ALONG HAUL ROADS AND LAYDOWN AREAS
TO IMPROVE TRAFFICABILITY. SPECIFIC PLATFORM DESIGN WOULD BE REQUIRED PRIOR TO MOBILISATION AND TRAFFICKING OF ANY HEAVY
MOBILE PLANT ON THE SITE.
8. IMPORTED GENERAL FILL MATERIAL SHALL BE SUPPLIED AND COMPACTED WHERE UNSUITABLE NATURAL MATERIALS ARE LOCATED AND AS
OTHERWISE NECESSARY TO OBTAIN SUBGRADE/PLATFORM LEVEL. IMPORTED GENERAL FILL MATERIAL SHALL BE CLEAN GRADED MATERIAL
FREE OF ORGANIC MATTER AND STONES, WITH MAXIMUM PARTICLE SIZE OF 100mm AND CAPABLE OF BEING COMPACTED INTO COHERENT
FILLING TO THE SPECIFIED STANDARD. THE MATERIAL SHALL HAVE A MAXIMUM PLASTICITY INDEX OF 15%, A SHRINK-SWELL INDEX OF LESS
THAN OR EQUAL TO 1% AND A MINIMUM C.B.R. OF 10%.
9. ALL EARTHWORKS TO BE CARRIED OUT AT +/- 2% OPTIMUM MOISTURE CONTENT FOR STANDARD COMPACTION.
10. ANY PROPOSED RETAINING WALL WORKS MUST BE WHOLLY WITHIN THE PROPERTY BOUNDARY OF THE SUBJECT SITE, INCLUDING REAR OF
CH28.0 CH27.7 RETAINING WALL DRAINAGE INFRASTRUCTURE FOR RETAINING WALLS IN CUT. RETAINING WALLS ARE TO BE PREPARED IN ACCORDANCE WITH
STRUCTURAL ENGINEERS SPECIFICATIONS, AND IN CONFORMANCE WITH CONSTRUCTION REQUIREMENTS OF GEOTECHNICAL REPORT.
11. REFER ARCHITECT/LANDSCAPE ARCHITECT DRAWINGS FOR CONFIRMATION OF RETAINING WALL COLOUR AND FINISH.
12. ALL EARTHWORKS OPERATIONS SHALL BE CARRIED OUT WITH 'LEVEL 1' SOIL ENGINEERING SUPERVISION IN ACCORDANCE WITH APPENDIX B
OF AS 3798. THE NOMINATED GEOTECHNICAL TESTING AUTHORITY SHALL PROVIDE CERTIFICATION THAT ALL GENERAL EARTHWORKS
OPERATIONS HAVE BEEN CARRIED OUT IN ACCORDANCE WITH THE DRAWINGS AND SPECIFICATIONS AND THE CONTROLLED FILL IS SUITABLE
0 m
1m 3m
2 8m FOR PURPOSE TO THE REQUIRED BEARING CAPACITY UNDER THE PLATFORM/STRUCTURES AS SPECIFIED BY THE GEOTECHNICAL REPORT.
.5 0 .7 . 13. ALL EARTHWORKS FILL AND EXCAVATED AREAS SHALL BE COMPACTED TO 98% STANDARD MAXIMUM DRY DENSITY OR A DRY DENSITY INDEX
-3 -3. -2 -3 14.
OF AT LEAST 75% IN ACCORDANCE WITH THE GEOTECHNICAL REPORT IN LAYERS OF 250MM LOOSE THICKNESS (PRIOR TO COMPACTION).
COMPACTION TESTING TO BE CARRIED OUT AT A MINIMUM OF TWO TESTS PER VERTICAL LIFT WHERE STRUCTURAL FILL HEIGHTS EXCEED
300MM IN ACCORDANCE WITH AS3798. CONTRACTOR TO UNDERTAKE ALL EARTHWORKS TESTING IN ACCORDANCE WITH GEOTECHNICAL
ENGINEER AND LOCAL AUTHORITY REQUIREMENTS.
m 7m 4m
15. FINISHED SURFACES TO ALL DISTURBED AREAS ARE TO BE TREATED IN ACCORDANCE WITH LANDSCAPE DRAWINGS.
m
16. ALL NEW WORKS TO MATCH NEATLY INTO EXISTING LEVELS.
9 6 6 9m -3
.1
-0
. 0 17. ALL WORKS TO BE CONSTRUCTED IN ACCORDANCE WITH APPROVED MANAGEMENT PLANS.
-2. -2
. 7 . 6 18. CONTRACTOR TO ENSURE SUITABLE EROSION CONTROL MEASURES ARE INSTALLED INCLUDING BUT NOT LIMITED TO SHAKE DOWNS, SILT
-2 19.
FENCE ETC IN ACCORDANCE WITH EROSION AND SEDIMENT CONTROL PLAN.
ADEQUATE SAFETY FENCING/BARRIERS TO BE APPLIED TO ALL BATTERS OR RETAINING WALLS (TEMPORARY OR PERMANENT) AS PER
RELEVANT AUSTRALIAN STANDARDS AND LEGISLATION.
20. DUST CONTROL MEASURES ARE TO INCLUDE SPRAYING WATER ON UNPAVED ROADS, ACCESS TRACKS AND STOCKPILES AT A SUFFICIENT
LEVEL TO SUPPRESS DUST GENERATION. ADDITIONALLY CONTRACTORS ARE TO COVER OR ENCLOSE STOCKPILES WHERE REASONABLY
m m 0 m PRACTICAL TO RESTRICT DUST MOVEMENT.
m m 0 5 .2
21. PRIOR TO THE CONTRACTOR COMMENCING ANY WORKS DETAILED ON THIS DRAWING, THE CONTRACTOR IS TO NOTIFY RECOR AND RECEIVE
.0
7 3 . 2 .9 1 WRITTEN CONFIRMATION THAT WORKS CAN COMMENCE.
1 -1
31
. -2
A
-2
22. ALL EXCAVATIONS ARE TO BE CONDUCTED IN ACCORDANCE WITH THE REQUIREMENTS OF THE GEOTECHNICAL ENGINEER AS OUTLINED IN THE
-2
CH42.8
CH0.0
GEOTECHNICAL INVESTIGATION REPORT BY TECTONIC. TEMPORARY UNSURCHARGED CUTS IN LOOSE TO VERY LOOSE SAND TO BE FORMED
AT 1V:2H, AND IN MEDIUM DENSE SAND AT 1V:1H FOR BATTERS UP TO 3M IN HEIGHT. DEEPER CUTS ARE TO BE ASSESSED BY THE
GEOTECHNICAL ENGINEER. PERMANENT CUT AND FILL BATTERS TO BE A MAXIMUM 1V:2.5H.
23. EARTHWORKS FILL BATTERS TO BE MAXIMUM OF 1M IN HEIGHT, OR OTHERWISE RETAINED.
5m 24. WHERE THE ABOVE TEMPORARY BATTER SLOPES CAN NOT BE ACHIEVED, TEMPORARY SHORING WILL BE REQUIRED UNDER THE ADVICE OF A
m .7 SPECIALIST SHORING CONTRACTOR.
8m m 9 -1 m
46 4 25. EXCAVATIONS IN PROXIMITY TO EXISTING STRUCTURES WILL REQUIRE SPECIFIC DESIGN TO PREVENT UNDERMINING WHICH SHOULD BE
1.1 . -1
. . 26 CARRIED OUT BY A SUITABLY QUALIFIED AND EXPERIENCED RPEQ STRUCTURAL ENGINEER.
- -1 -1
26. CONTRACTOR'S RPEQ GEOTECHNICAL ENGINEER IS TO CONFIRM THAT ANY CONSTRUCTED CUT/FILL BATTERS AND RETAINING STRUCTURES
ON THE SITE HAVE ACHIEVED ADEQUATE STABILITY WITH A LONG-TERM FACTOR OF SAFETY AGAINST GEOTECHNICAL FAILURES TO THEIR
SATISFACTION.
27. EARTHWORKS LEVELS SHOWN ARE FINISHED DESIGN SURFACE LEVELS LOWERED BY NOMINAL 200mm TO ALLOW FOR SLAB AND SURFACE
WORKS. CONTRACTOR TO CONFIRM FINISHED EARTHWORKS LEVLS BASED ON STRUCTURAL ENGINEERING DRAWINGS FOR BUILDING SLAB
THICKNESSES AND HYDRAULIC DRAWINGS FOR SUB-FLOOR DRAINAGE TO CONFIRM FINAL EARTHWORKS SURFACE LEVEL.
6m 28. ANY PRELOADING REQUIRED IS TO OCCUR IN ACCORDANCE WITH THE GEOTECHNICAL ENGINEERS REQUIREMENTS. CONTRACTOR TO ALLOW
m 5 m 7m 3 m . 4 FOR THE IMPORT AND REMOVAL OF ALL NECESSARY MATERIAL TO UNDERTAKE THE PRELOADING OPERATIONS.
5 6 .4 5 -0
3 1.
29. REFER ARCHITECTURAL DRAWINGS FOR BUILDING SETOUT.
.
31
. -1
B
-0 -1
CH42.8
CH0.0
DEPTH LEGEND
-3.8 to -3.6
-3.6 to -3.4
-3.4 to -3.2
-3.2 to -3.0
-3.0 to -2.8
-2.8 to -2.6
-2.6 to -2.4
-2.4 to -2.2
-2.2 to -2.0
CH0.0 -2.0 to -1.8
CH0.0 -1.8 to -1.6
-1.6 to -1.4
-1.4 to -1.2
31
D
31
-1.2 to -1.0
C
-1.0 to -0.8
-0.8 to -0.6
-0.6 to -0.4
-0.4 to -0.2
-0.2 to -0.0
0.0 to 0.2
0.2 to 0.4
0.4 to 0.6
0.6 to 0.8
0.8 to 1.0
SCALE: CLIENT: APPROVED BY: PROJECT NAME:
RESIDENTIAL UNITS AT 37 BOTTLEBRUSH AVE
1:100 TITLE: STATUS:
D 15/03/2023 RFI UPDATE BP BP BP BULK EARTHWORKS PLAN MCU / OP WORKS
© ABN 89 647 469 707 C 29/11/22 RFI UPDATE BRP JB BRP
SCALE 1:1000
BOTTLEBRUSH PROPERTY PTY LTD BEN PARRY
B 10/10/22 RFI UPDATE BRP MVP BRP 10 50 100M
37 MARY ST RPEQ: 28084
A 12/05/22 MCU / OPW ISSUE BRP BRP NW
NOOSAVILLE, QLD 4566 CPEng NER DRAWING NUMBER: PROJECT NUMBER: REV:
+61 7 5211 1003 REV DATE DESCRIPTION DWN CHK APP SHEET
DATE: 15/03/2023 SIZE:
RECORCONSULTING.COM REVISIONS C30 20220051 A1 D
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalLog in to download the original file
The download may take up to a minute.