ORDINARY MEETING AGENDA 19 OCTOBER 2017
Stormwater Drainage
22. The site must be provided with a stormwater drainage system connecting to a
lawful point of discharge. The works must be undertaken in accordance with an
Operational Works approval and must include in particular:
a. Connection of any new works on site and in the carparking area to the
existing stormwater drainage system;
b. The works in Webb Road must be generally in accordance with drawing
number 16636-SK01 Revision A prepared by TOD Noosa and include
sufficient detail:
i. To quantify the catchment and calculate runoff to the proposed inlet
and define overland flow component bypassing the inlet in a 1% AEP
event
ii. To demonstrate improved inlet capture
iii. To demonstrate how the adjacent 1in 4 fill batter is to be stabilised to
avoid scour when flows bypass the proposed inlet
iv. To demonstrate that cars parked in the adjacent carparking spaces
will not be flooded in a 1% AEP event
Geotechnical Stability Add for REC: - Subdivisional Requirements
23. All works must be carried out in accordance with a Geotechnical Report (or part
thereof) prepared by a qualified person* and endorsed through an Operational
Works approval.
*(Refer to Advisory Note)
24. Certification must be submitted to Council from a qualified person* which certifies
that the development has been constructed in accordance with the Geotechnical
Report for the development and that the development has a minimum factor of
safety against landslip of 1.5 in the long term.
*(Refer to advisory Note)
Earthworks and Retaining Walls
25. All fill and associated batters must be undertaken in accordance with an
Operational Works approval, and contained entirely within the subject site unless
written permission from the respective landowner(s) is provided to Council.
26. All retaining walls must be designed and constructed in accordance with the
planning scheme and must be certified by an RPEQ where exceeding 1.0m in
height. All retaining walls that are publicly accessible and exceed 1.0m in height
must be fitted with a commercial grade safety fence.
Damage to Services and Assets
27. Any damage caused to existing services and assets as a result of the
development works must be repaired at no cost to the asset owner at the
following times:
a. where the damage would cause a hazard to pedestrian or vehicle safety,
immediately; or
b. where otherwise, upon completion of the works associated with the
development.
Any repair work which proposes to alter the alignment or level of existing services
and assets must first be referred to the relevant service authority for approval.
Page 9 of 22
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalSearchable page text hides email addresses. Original files are unchanged and may show email addresses.