Original source · versioned page text
2020-01-16 Ordinary Meeting Agenda
Text sections have not been matched to the original PDF pages. Use the original document to check page numbers.
ORDINARY MEETING AGENDA 16 JANUARY 2020
Plan No. Rev. Plan/Document Name Date
DA09 18E Unit Type T2, prepared by All Design and Drafting 06.11.2019
DA10 18E Unit Type T3, prepared by All Design and Drafting 06.11.2019
DA11 18E Exterior Materials and Colours, prepared by All Design 06.11.2019
and Drafting
ENGINEERING
Site Access and Driveway
14. Vehicular access driveways to serve the development shall be constructed from
the Olivine Street frontages of the site generally in accordance with the final
approved layout plans and as annotated by Council and amended by the
conditions of this permit and in compliance with the applicable engineering
standards and drawings.
15. Two sealed access driveways must be provided from Olivine Street frontages of
the site to all parking and manoeuvring areas of the development generally in
accordance with the final approved layout plans as annotated by Council and
amended by the conditions of this permit. The works must be undertaken in
accordance with an Operational Works approval and must include in particular:
15.1. Driveway crossovers generally in accordance with IPWEAQ standard
drawings R-049 and R-050, and to grades that prevent vehicles from
scraping and/or bottoming whilst also allowing for compliant grades and
levels that match any existing or proposed pathway and grassed verge
without posing trip or safety hazards to the public.
15.2. For pedestrian safety on the footpath and vehicles exiting the site, the
driveway and any associated fencing or vegetation near the driveway must
comply with the minimum sight line requirements as defined in AS/NZ
2890.1, section 3.2.4.
15.3. The proposed driveway must have a maximum width of 6m at kerb line.
15.4. Driveway must have clearance of 1.0m from a power pole and 0.5m from and
any service pit or manhole (e.g. telecommunication pit, water meter) unless
a written approval obtained from the relevant provider.
24. A new 2.0m wide concrete path must be constructed along the Kauri Street and
Olivine Street frontages of the site in accordance with an Operational Works
approval and to a desirable and smooth alignment for the comfort of users and
protection of trees identified in this permit for retention. The new path must be in
compliance with IPWEAQ standard drawing SEQ R-065 Concrete Pathway
Construction Details. The works must be provided as part of Stage 1 of
development and include:
24.1. A sufficient number of pram ramps to be provided near the intersection of
Kauri Street and Olivine Street where identified by Council to connect to
existing and proposed pathways network.
24.2. A pedestrian pathway connection 1.5m wide from Kauri Street’s public
pathway into the development site to be located north of proposed Unit 9.
The above condition is imposed pursuant to s145 of the Planning Act 2016 being
non-trunk infrastructure
C. Note the report is provided in accordance with Section 63(5) of the Planning Act 2016.
For: Crs Glasgow, Jackson, Wellington and Wilkie
Against: Cr Jurisevic
Carried.
Page 10 of 19
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalSearchable page text hides email addresses. Original files are unchanged and may show email addresses.