174. Notwithstanding these conditions, the Conference Room and Restaurant and Bars (internal
areas and excluding any pool bar) may be used until midnight on any day of the week if the
use is in connection with a conference being held at the Resort.
175. During the operational phase of the Development machinery including forklifts may only be
operated between the hours of 8:00 am and 5:00 pm Monday to Friday unless they are
operated in an enclosed space (eg within a basement) having sound attenuation.
176. Prior to the approval of Building Works, the following additional noise details are required to be
supplied and approved by the Manager of Environmental Health:
176.1 The location of mechanical equipment (air conditioners, refrigeration equipment or
pool pumps etc) and how they will be installed to comply with Noosa Council’s Local
Law No. 12 – Noise Nuisances and the Environmental Protection Regulations 1998.
Trade Waste
177. Liquid waste generated by industry, small business and commercial enterprises is referred to
as Trade Waste and shall comply with the following:
177.1.A trade waste permit shall be obtained prior to the discharge of trade waste to Council’s
sewerage system.
177.2.All trade waste requirements complying with Council’s Trade Waste Policy and including
pre-treatment devices, must be shown on hydraulic plans submitted to Council for
approval prior to issuing the development permit for building work.
177.3.Vehicular access shall be provided to each grease arrestor and/or pre-treatment device
for cleaning and servicing by Council’s contractor, and must allow vehicles to enter and
leave the site in a forward direction as per Qantec McWilliam drawing No. 05B320
SK.03 dated April 2006.
BUILDING SERVICES
178. Fencing to the swimming pool must comply with the Queensland Building Act 1975 Part 3 (as
amended) and Part 5 of Standard Building Regulation 1993 in all respects. Direct access from
the dwelling to the pool enclosure is not permitted. Any pool fencing shall be coloured
charcoal or dark earthy colours, or non-reflective green or grey glass (or clear glass for the
lower level pools).
LAND DEVELOPMENT
Construction
General
179. The Developer shall cause the Principal Contractor to attend a pre-start meeting with the
Manager – Land Development prior to commencement of any work on Site. At the pre-start
meeting the Principal Contractor is to submit a copy of the Workplace Health and Safety Plan
for the Development to Council for Council’s records. The Workplace Health and Safety Plan
shall comply with the provisions of the Workplace Health and Safety Regulation 1997. The
Principal Contractor and supervising engineer are responsible for compliance with the
Workplace Health and Safety Plan. The Developer shall ensure that there is compliance with
the Workplace Health & Safety Plan.
180. The Developer shall ensure the following steps are undertaken prior to commencement of any
works on Site:
180.1.The Principal Contractor shall give the Council Inspector seven days notice of intention
to commence works.
Page 32 of 59
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalUsed in these records
Decision Notice - Change to an Existing Approval - 010.2006.00000823.003 [As Published]Related documentApplication case desk ↗
About this file
- File size
- 329 KB (small file)
- File type
No other editions are linked here.