SDA-0913-004403 Our reference: SDA-0913-004403 Your reference: OPW13/0614 Date: 1/11/2013 Sunshine Coast Regional Council Locked Bag 72 Sunshine Coast Mail Centre QLD 4560 Dear Mark Lewis Concurrence agency response—with conditions 4 Russell Street - Noosaville, Sunshine Coast Regional Council - QLD (Given under section 285 of the Sustainable Planning Act 2009) The referral agency material for the development application described below was received by the Department of State Development, Infrastructure and Planning under section 272 of the Sustainable Planning Act 2009 on 09 September 2013. Applicant details Applicant name: Sunshine Coast Regional Council Applicant contact details: c/- Projex Partners Pty Ltd PO Box 1415 Buddina, Queensland, 4575 Site details Street address: 4 Russell Street, Noosaville Real property description: 131 SP143417 Site area: 250sqm (developed area) Local government area: Sunshine Coast Regional Council Application details Proposed development: Approval for sandbagging emergency works under s585 of the Sustainable Planning Act 2009. Aspects of development and type of approval being sought Department of State Development, Infrastructure and Planning Page1
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalFull text of the other 5 pages
Page 2
SDA-0913-004403
Development Permit for Operational Works – Prescribed Tidal Works - Sandbag
revetment wall
Referral triggers
The development application was referred to the department under the following
provisions of the Sustainable Planning Regulation 2009:
Referral trigger Schedule 7, Table 2, Item 13 – Tidal works, or development
completely or partly within a coastal management district.
Schedule 7, Table 2, Item 15 and 15A – Tidal works, or
development completely or partly within a coastal management
district.
Conditions
Under section 287(1)(a) of the Sustainable Planning Act 2009, the department requires that
the conditions set out in Attachment 1 attach to any development approval.
Reasons for decision to impose conditions
Under section 289(1) of the Sustainable Planning Act 2009, the department is required
to set out the reasons for the decision to impose conditions. These reasons are set out in
Attachment 2.
Further advice
Under section 287(6) of the Sustainable Planning Act 2009, the department offers advice
about the application to the assessment manager—see Attachment 3.
A copy of this response has been sent to the applicant for their information.
If you require any further information, please contact Tracey Smith, A/Senior Planning
Officer, on
3882 8409 who will be pleased to assist.
Yours sincerely
Sarah Doring
A/Manager (Planning)
cc: Projex Partners Pty Ltd,
enc: Attachment 1—Conditions to be imposed
Attachment 2—Reasons for decision to impose conditions
Attachment 3—Further advice
Department of State Development, Infrastructure and Planning Page2
Page 3
SDA-0913-004403
Our reference: SDA-0913-004403
Your reference: OPW13/0614
Attachment 1—Conditions to be imposed
No. Conditions Condition timing
1. The sandbag revetment works must be removed or modified Continuous
if the works have or are likely to have a significant effect on
coastal management because the works:
# Cause or increase localised erosion, particularly at
the terminal ends of the revetment
# Are structurally unstable
# Disturb coastal processes
# Increases the coastal hazard risk or scouring to
adjacent areas or properties.
2. Should the sandbag revetment works result in significant Continuous
adverse impacts to coastal management or adjoining properties,
Sunshine Coast Regional Council, or its successor, is
responsible for any rectification works and where necessary, the
removal of the works causing the impacts.
Department of State Development, Infrastructure and Planning Page1
Page 4
SDA-0913-004403
Our reference: SDA-0913-004403
Your reference: OPW13/0614
Attachment 2—Reasons for decision to impose conditions
The reasons for this decision are:
# To ensure compliance with the relevant module of the State Development
Assessment Provisions.
# Revetments only prevent further erosion of the land directly protected by the
structure.
# Revetments halt landward migration of the shoreline, however they can
adversely impact the adjoining land and foreshore.
# Revetment do not provide a coastal management benefit to adjoining areas, or
address the primary cause of erosion.
# The sandbag revetment wall is considered a temporary structure constructed in
an emergency situation under s585 of the Sustainable Planning Act 2009.
Findings on material questions of fact
# Works were required to address the prior public safety issues at the site.
# No information has been provided that demonstrates the revetment structure
will not adversely impact the stability of the bed and banks of the waterway or
adjoining coastal properties.
# No plans or information have been provided showing the exact location of the
tidal works structure on Lot 131 SP143417.
# No plans or information have been provided to demonstrate the tidal works
structure meet the minimum engineering or appropriate Australian standards for
a revetment structure.
# The applicant identifies that the sandbags are intended to be a temporary
installation to maintain safety on the site and that work will be undertaken in a
timely manner to implement a more permanent engineered solution.
Evidence or other material on which the findings were based
# Development application material
# Sustainable Planning Act 2009
# Sustainable Planning Regulation 2009
# State Development Assessment Provisions
# Response to information request from applicant, dated 15 October 2013
# Coastal Protection and Management Regulation 2003
Department of State Development, Infrastructure and Planning Page2
Page 5
SDA-0913-004403 Our reference: SDA-0913-004403 Your reference: OPW13/0614 Department of State Development, Infrastructure and Planning Page3
Page 6
SDA-0913-004403
Attachment 3—Further advice
General advice
1. Ensure that the Prescribed tidal work is designed and constructed in a way to ensure
it is structurally sound. (Specific outcome 12.1 of Schedule 4A Coastal Protection and
Management Regulation 2003)
2. Ensure that the prescribed tidal work is designed and constructed in a way to ensure it
does not adversely affect the stability of the bed and banks of any tidal water. (Specific
outcome 12.3 of Schedule 4A Coastal Protection and Management Regulation 2003)
3. Ensure that the Prescribed tidal work is designed and constructed using materials having a
long life in marine environments. (Specific outcome 12.4 of Schedule 4A Coastal Protection
and Management Regulation 2003)
4. Ensure that the Prescribed tidal work that is a retaining wall, revetment or seawall, is
designed and constructed in a way to ensure it can withstand – (a) any tendency of
overturning or sliding; and (b) any other effects of waves or changes in water levels on
the retaining wall, revetment or seawall. (Specific outcome 19.2 of Schedule 4A Coastal
Protection and Management Regulation 2003)
5. Ensure that the Prescribed tidal work that is a retaining wall, revetment or seawall not
founded upon rock, is designed and constructed to protect the seaward side of retaining
wall, revetment or seawall from erosion. (Specific outcome 19.3 of Schedule 4A Coastal
Protection and Management Regulation 2003)
Department of State Development, Infrastructure and Planning Page4
Used in these records
CAR Letter 4403pdfRelated documentApplication case desk ↗
About this file
- File size
- 44 KB (small file)
- File type
No other editions are linked here.