                                                       4




   Any cut in the vicinity of a structure or between a structure and the road kerb will need to be
    stabilised by a retaining wall. The retaining wall design and location is to be submitted to
    Energex for approval.

   Any costs incurred by Energex as a result of the works on the easement are to be met by
    the property Developer / owner.

   Access to the easement and access along the easement must be available to Energex
    personnel and heavy equipment at all times. Energex will require the Developer / owner to
    supply and install gates where fencing prohibits access to and along the easement area.
    To enable travel along the easement at anytime the gates must be series locked with an
    Energex padlock. Both the padlock and a design drawing of an acceptable gate will be
    provided by Energex.

   At all times the following clearance must be maintained from the top of any machinery
    moving in the vicinity of energised conductors:
    -      132kV and 110kV conductors – 4.5m minimum clearance
    -      33kV and 11kV conductors – 3m minimum clearance
    Should it be necessary to transport equipment or extend any equipment, such that these
    clearances cannot be confidently maintained, you are required to contact our office to
    ascertain whether a Safety Officer is required on–site. All operators of machinery are to be
    made aware of the presence of high voltage conductors.

   No planting is permitted in the Easement without prior approval from Energex. If planting is
    proposed, the applicant is required to provide a Detailed Landscape Plan to Energex for
    approval which:
        o Keeps the planting of trees to the outer most edge of the easement and not directly
           under any overhead conductors; and
        o Plots the location of the overhead conductors (accounting for a cross-arm if
           applicable and plotting the powerline on the outmost edge of each side of the cross-
           arm); and
        o Uses         species        included     on        Energex’s     Safetrees         list
           (https://www.energex.com.au/about-us/our-commitment/to-the-
           environment/vegetation/safetree-program); and
        o Ensures a horizontal clearance is achieved between the tree and the outer most
           conductor equal to the mature height of the tree.




Reference: HBD 7661677

                                      Have you seen our fact sheets?
        See the ‘considerations when developing around electricity infrastructure’ section of our website
                                    www.energex.com.au/referralagency
Log in to download the original file

EGX_PROD_n7661677_Wallum_Lane,_Noosa_Heads_L17_SP239726.pdf · 242 KB (small file)

Searchable page text hides email addresses. Original files are unchanged and may show email addresses.

The supporting record

Open full page ↗

Source document

Analyse documents ↗Open full page ↗

My Comparisons

Choose two to four records of the same kind. Drag using a handle or use the “Compare” buttons.

Your selected records are saved in this browser for your account. Results use the filters on the page where you choose “Compare selected”.