MCU16/0012 Attach D- Noise Assessment response

of 4

Page text shows just the words. Original shows the document exactly as it was published.

                                                                                                      MRG Environmental
                                                                                       P: 07 3841 0815 F: 07 3841 0817
                                                                                            www.mrgenvironmental.com
                                                                    Ground Level 88 Brandl St, Eight Mile Plains QLD 4113
                                                                                PO Box 6794 Upper Mt Gravatt QLD 4122




7 June 2016


Ref: 0101-L1-01


Creekgold Pty Ltd
c/- Verve Building Design and Concepts
318 Junction Road
Clayfield QLD 4011



Dear Gavin,

RE: 3 Garnet Street, Cooroy – Noise – Response to Council Request for Information

Verve Building Design and Concepts (VerveBD) on behalf of Creekgold Pty Ltd has requested that
MRG Environmental (MRG) review and provide a response to Noosa Shire Council’s (NSC) request for
information dated 15 March 2016 (MCU16/0012).

This letter provides a response to NSC’s request for information (Item 19) and is based on
correspondence between MRG and NSC representative Geoff Atherfold.

Telephone and email correspondence (12/04/2016 and 28/04/2016) were exchanged between MRG
and NSC staff. This correspondence further clarified the details within the report (0101-R1-01 dated
2/02/2016). Mr Atherfold agreed that delivery vehicle hours of operation should be restricted as
proposed within the acoustic assessment.

Mr Atherfold stated that given this additional detail no further information was required, with the
exception of an additional noise assessment of the rooftop plant and equipment. Given that the
exact rooftop plant and equipment details are not known at this time, MRG recommended (email
dated 28/04/2016) that the assessment form part of the conditions package. A condition should be
included which requires the rooftop mechanical plant to be reassessed at detail design stage once
the exact specifications are known.

                                                             <<>>

If you have any further queries please contact me.

Regards,




Matthew Goodfellow
Director
0101-L1-01 VerveBD Garnet Street, Cooroy Noise Letter.docx                                                             1
Letter
Creekgold Pty Ltd | 0101
Log in to download the original file

MCU16_0012 Attach D- Noise Assessment response.pdf · 503 KB (small file)

Searchable page text hides email addresses. Original files are unchanged and may show email addresses.

Full text of the other 3 pages

Page 2

Eddie Venturini
From:                                 Matthew Goodfellow <[email protected]>
Sent:                                 Thursday, 28 April 2016 12:04 PM
To:                                   'Geoff Atherfold'
Cc:                                   'Gavin Nye'; Eddie Venturini
Subject:                              RE: Garnet Street


Thanks Geoff,

The mechanical plant is typically selected during detailed design (post DA) and a revised noise assessment
conducted at that time. Typically a condition covering mechanical plant noise certification may be used to trigger
the assessment during detailed design.

Let me know if you need anything further.

Regards,

Matt

                                                          Matthew Goodfellow
                                                          Director
                                                          P: 07 3841 0815 F: 07 3841 0817 M: 0409 714 336
                                                          Ground Level 88 Brandl St, Eight Mile Plains QLD 4113
                                                          PO Box 6794 Upper Mt Gravatt QLD 4122
                                                          [email protected] | www.mrgenvironmental.com

  This message contains confidential information and is intended only for the individual or company named. If you are not the intended
recipient you should not disseminate, distribute or copy this email. Please notify the sender immediately if you have received this email by
                                               mistake and then delete it from your system.




From: Geoff Atherfold [mailto:[email protected]]
Sent: Thursday, 28 April 2016 11:00 AM
To: Matthew Goodfellow
Cc: Gavin Nye; Eddie Venturini
Subject: RE: Garnet Street

Matthew
Yes if you are satisfied that background levels at the loading dock area (N2) will be a good representation at the
sensitive recivers at S! & S2, then I’m happy to accept those levels.
Restricted hours (7.00am to 6.00pm)for the loading dock delivery and waste pick up times is satisfactory
Please advise plant noise assessment once the plant type is known
Thanks
Geoff


From: Matthew Goodfellow [mailto:[email protected]]
Sent: Thursday, 28 April 2016 10:20 AM
To: Geoff Atherfold
Cc: Gavin Nye; Eddie Venturini
Subject: RE: Garnet Street

Hi Geoff,

Thank you for taking the time last week to discuss the Garnet Street information request (Item 19, MCU16/0012).
                                                                               1

Page 3

As discussed, the noise monitoring locations were selected to provide representative background noise levels given
the limitations surrounding the existing facility onsite.

In addition, the key noise mitigation measures reported include those regarding the delivery dock and mechanical
plant (report Section 4.3 and 5 dot points 1 and 3). These will restrict the operational hours of the dock and ensure
appropriate mechanical plant are installed.

Based on our discussions you advised that you do not require any further information at this time.

Please contact me if you have any queries.

Regards,

Matt

                                                          Matthew Goodfellow
                                                          Director
                                                          P: 07 3841 0815 F: 07 3841 0817 M: 0409 714 336
                                                          Ground Level 88 Brandl St, Eight Mile Plains QLD 4113
                                                          PO Box 6794 Upper Mt Gravatt QLD 4122
                                                          [email protected] | www.mrgenvironmental.com

  This message contains confidential information and is intended only for the individual or company named. If you are not the intended
recipient you should not disseminate, distribute or copy this email. Please notify the sender immediately if you have received this email by
                                               mistake and then delete it from your system.




From: Geoff Atherfold [mailto:[email protected]]
Sent: Tuesday, 12 April 2016 1:37 PM
To: Matthew Goodfellow
Subject: Re: Garnet Street

Matthew
I'm out of office. Back in monday next week
I did have a look at your report so can chat to you early next week
Geoff



Sent from my Samsung GALAXY S5 on the Telstra Mobile network



-------- Original message --------
From: Matthew Goodfellow <[email protected]>
Date: 12/04/2016 8:51 am (GMT+10:00)
To: Geoff Atherfold <[email protected]>
Subject: Garnet Street

Hi Geoff,

Thank you for discussing the Garnet Street information request with me yesterday (Item 19, MCU16/0012).

As discussed, I just wanted to clarify a few items which are within the report:
    • The summary of background noise measurements (Table 3.4) located at N2 (Wimmers Lane), excluded the
        mechanical plant spikes (∼70 dB) that are presented in Figure 3.2.


                                                                               2

Page 4

    •      Receiver S1 and S2 used the background noise level measurements at N2 (Wimmers Lane) to set the LAeq
          criteria.
    •      Hard surfaces have been included (Section 4) for proposed hardstand areas and existing roads and car
          parks.
    •      Refuse vehicles are assumed to be HRV. I apologise as this was not clear within the assessment, but a
          recommendation to restrict their hours of operation has been included based on the modelling.
                    ‘Deliveries and refuse collection should be during the daytime only (7:00 am to 6:00 pm).’

Please let me know if this addresses your concerns or if you would like further information?

Regards,

Matt

                                                          Matthew Goodfellow
                                                          Director
                                                          P: 07 3841 0815 F: 07 3841 0817 M: 0409 714 336
                                                          Ground Level 88 Brandl St, Eight Mile Plains QLD 4113
                                                          PO Box 6794 Upper Mt Gravatt QLD 4122
                                                          [email protected] | www.mrgenvironmental.com

  This message contains confidential information and is intended only for the individual or company named. If you are not the intended
recipient you should not disseminate, distribute or copy this email. Please notify the sender immediately if you have received this email by
                                               mistake and then delete it from your system.




                                                                               3

The supporting record

Open full page ↗

Source document

Analyse documents ↗Open full page ↗

My Comparisons

Choose two to four records of the same kind. Drag using a handle or use the “Compare” buttons.

Your selected records are saved in this browser for your account. Results use the filters on the page where you choose “Compare selected”.