Negotiated Decision Notice MCU22 0201

of 45

Page text shows just the words. Original shows the document exactly as it was published.

Page text read automatically using OCR, there may be inaccuracies

                         You should contact the Cultural Heritage Unit to discuss any obligations under the ACH
                         Act.
                         Equitable Access and Facilities
                 2.      The plans for the proposed building work have NOT been assessed for compliance with
                         the requirements of the National Construction Code - Building Code of Australia (Volume 1)
                         as they relate to people with disabilities. Your attention is also directed to the fact that in
                         addition to the requirements of the National Construction Code as they relate to people
                         with disabilities, one or more of the following may impact on the proposed building
                         work:
                         a.      the Disability Discrimination Act 1992 (Commonwealth);
                         b.      the Anti-Discrimination Act 1991 (Queensland); and
                         c.      the Disability (Access to Premises – Buildings) Standards.
                         Advertising Devices
                 3.      All Advertising Devices must comply with Schedule 10 of Subordinate Local Law No.1
                         (Administration) 2015 including both temporary and permanent signage. All
                         freestanding, pylon or pole signs or signage that is illuminated requires approval from
                         Council prior to being installed. All signage identified in s6 of Schedule 10 of Subordinate
                         Local Law No. 1 is prohibited from being erected in the Shire.
                         Building and Construction Industry (Portable Long Service Leave) Levy
                 4.      The QLeave levy must be paid prior to the issue of a development permit where it is
                         required. Council will not be able to issue a Decision Notice without receipt of details that
                         the Levy has been paid.
                         Co-ordination of Operational Works Assessment
                 5.      Additional application fees apply to Operational Work applications where the different
                         aspects of the works are lodged separately. Significant savings in application fees will
                         result if all works are lodged in a single application.
                         Preparation of a Preliminary Construction Management Plan
                 6.      A preliminary Construction Management Plan must be submitted with the Operational
                         Works application and must address the following:
                         a.      traffic management during all aspects of the construction phase including:
                                 i.     a Traffic Management Control Plan in accordance with the Manual of
                                        Uniform Traffic Control Devices (MUTCD) detailing all temporary signage
                                        and traffic control measures prior to construction
                                 ii.    maintenance of safe pedestrian access for the areas affected by the works
                                        during and after daily construction has ceased
                                 iii.   proposed fencing to the site during the construction phase of the
                                        development
                                 iv.    approval of the Traffic Management Control Plan by the Department of
                                        Transport and Main Roads (DTMR) for any works on State controlled roads
                                 v.     provision for worker car parking
                         b.      maintenance and protection of water quality and existing drainage lines through the
                                 construction site, through the implementation of appropriate erosion and
                                 sediment control measures
                         c.      works programme identifying key components of the works and their respective
                                 durations
                         d.      establishment of a communication protocol with the general public, adjoining
                                 owners, emergency services and local businesses to advise of agreed
                                 construction times, impacts on traffic, services and other relevant issues.


                                                                                                            Page 9 of 41
Document Set ID: 23372937
Version: 2, Version Date: 27/11/2024
Log in to download the original file

Negotiated Decision Notice MCU22 0201.pdf · 1.4 MB (small file)

Searchable page text hides email addresses. Original files are unchanged and may show email addresses.

The supporting record

Open full page ↗

Source document

Analyse documents ↗Open full page ↗

My Comparisons

Choose two to four records of the same kind. Drag using a handle or use the “Compare” buttons.

Your selected records are saved in this browser for your account. Results use the filters on the page where you choose “Compare selected”.