Attachment B - Code Compliance Assessment

of 159
 Performance Outcomes                             Acceptable Outcomes                         Planning Comment
 Earthworks and Drainage
 PO37                                             AO37                                        Complies
 Filling, excavation and retaining structures     Filling and excavation works are designed   Natural gravity stormwater flows are to be
 do not directly, indirectly or cumulatively      and constructed to ensure overland flow     maintained. Adequate pits are to be
 cause adverse impacts external to the            and/or flooding is not worsened, impeded,   provided to carry water to legal point of
 development site by:                             or otherwise diverted to adversely affect   discharge on Rene Street or direct to
      (a) causing ponding of water on the         other properties or downstream              Council stormwater piping within the
          site or nearby land;                    environments.                               easement that runs through the site.
      (b) increasing flooding, which adversely
          affects the safety or use of any land
          upstream and downstream; or
          adversely affecting the flow of water
          in any overland flow path.


Environment and Heritage                    Table 6.5.1.3 Criteria for assessment (part)

Benchmarks for assessable development including benchmarks for all Industry Precincts (part)

 Performance Outcomes                             Acceptable Outcomes                         Planning Comment
 All activities
 Environment and Heritage
 PO38                                             AO38.1                                      Complies
 Development:                                     Development does not result in sediment     The proposed development will put in
     (a) has minimal impact on the natural        or other material including building        place a construction management plan to
         landform of the site;                    materials or waste products being           mitigate and avoid sediment and other
     (b) does not lead to erosion or the          deposited or released into the road         material including building materials or
         transport of sediments off site; and     reserve, stormwater drain or adjacent       waste products being deposited or
                                                  properties.                                 released into the road reserve, stormwater



jrey.au | (07) 3106 3221 | [email protected]

Log in to download the original (Attachment B - Code Compliance Assessment.pdf)

Searchable page text hides email addresses. Original files are unchanged and may show email addresses.

The supporting record

Open full page ↗

Source document

Analyse documents ↗Open full page ↗

My Comparisons

Choose two to four records of the same kind. Drag using a handle or use the “Compare” buttons.

Your selected records are saved in this browser for your account. Results use the filters on the page where you choose “Compare selected”.