BROWN CONSULTING (QLD) PTY LTD —- SUNSHINE COAST

COMMONS.

 

3.0 EXISTING SERVICES

All proposed relocation and adjustments to existing services will be undertaken in accordance with
Sections 3, 4 and 5 of PSP 6 — Engineering Design Standards — Water and Sewerage and Section
4 of PSP 5 -— Engineering Design Standards — Roads, Drainage and Earthworks.

As-constructed data for both water and sewer will be submitted in accordance with Sections 3 and
7 of PSP 6 — Engineering Design Standards — Water and Sewerage.

Easements will be registered in favour of Council for all sewer, water and stormwater infrastructure
in accordance with Council’s requirements.

Proposed Measures for Council's Existing Services Code can be found in Appendix C.

3.1. Water Reticulation

It is proposed that water supply to the site will be obtained via connection to an existing 150mm
diameter water main on the Eastern Side of David Low Way as detailed in the Water Supply
Analysis prepared by John Wilson and Partners (refer Appendix H).

The connection to the existing water main will be made by Council at the developer’s expense and
the external extension of the watermain will be tunnel bored under David Low Way to avoid any
disturbance to the existing road network.

It is proposed that all internal water reticulation will be designed as per AS 3500 - 1998 National
Plumbing and Drainage as this is a group title development.

Proposed Measures for Council's Water Supply and Sewerage Reticulation Code can be found in
Appendix F.

Please refer Drawing Number N0O7046-04 for the Water Reticulation Layout Plan.

3.2. Sewerage Reticulation

The site is currently serviced by sewer lines 1A and 1B. The commercial development towards the
Northeast corner of the site is also currently serviced by this sewer line. /

It is proposed to realign this sewer along the Northern boundary of the site and make adjustments
to the internal sewer reticulation within the commercial site (refer Drawing Number NO7046-04 for
the Sewer Reticulation Layout Plan). Lines 1A and 1B would remain online until such a time as the
proposed sewer is constructed and accepted on maintenance by Council and the live connection
for the commercial property can be made. This would be subject to discussion with the adjoining
property owner but we do not foresee that this will be an issue.

 

"ESSENCE OF PEREGIAN, DAVID LOW WAY, PEREGIAN PaGE 2

Used in these records

About this file

File size
5.2 MB (large file)
File type
PDF

No other editions are linked here.

Original file

Log in to download the original file

20517 App I.pdf [As Published].pdf · 5.2 MB (large file)

The download may take up to a minute.

The supporting record

Open full page ↗

Source document

Analyse documents ↗Open full page ↗

My Comparisons

Choose two to four records of the same kind. Drag using a handle or use the “Compare” buttons.

Your selected records are saved in this browser for your account. Results use the filters on the page where you choose “Compare selected”.