1. Development undertaken in accordance with this approval must generally comply with the approved plans
of development. The approved plans are titled and numbered Basement Level, PHAR01_01; Ground
Floor Level, PHAR01_02; North & South Elevations, PHAR02_01; First Floor Level, PHAR01_03; East &
West Elevations, PHAR02_02; prepared by ar+d pte ltd and dated 29 June 2007 and as may be amended
by these conditions.
2. The development must be undertaken and operated in a manner that causes no detrimental effect upon
the amenity of the neighbourhood by reason of the creation of excessive noise, lighting nuisance or other
emissions.
3. All hot water systems installed shall be either solar systems; electric heat pump systems; or gas systems
(LPG or natural).
4. A rainwater storage tank with a minimum capacity of 5000 litres shall be provided on site to service the
detached house. The tank is to be installed to ensure water from the tank can be used both:
4.1. for external use such as watering gardens, irrigation, ornamental ponds or water features, topping
up swimming pools, outdoor cleaning; and
4.2. for use in flushing of toilets internal to the building.
5. Security in the form of a cash bond or trading bank guarantee to the sum of $1,500 must be submitted, to
secure performance of all conditions of this approval, prior to the issue of a Development Permit for
building works. The cash bond or trading bank guarantee will be returned on performance of the
conditions of approval less any costs incurred by Council in respect of enforcing performance of this
permit.
6. The building height shall not exceed 8.0 metres above natural ground level.
7. A verification survey of the building is to be carried out by a Licensed Surveyor and a certificate lodged
with Council at completion of work confirming compliance with the maximum allowable building
height as required by either the conditions of approval or the Planning Scheme.
8. Buildings and structures (including swimming pools, sheds, tennis courts or outbuildings) are not
constructed under overhead electricity transmission lines, or within any easements.
9. A geotechnical report, prepared by a registered professional engineer shall be obtained, and it should
either:-
9.1. certify that the site is not at risk from landslide emanating from the site or from other land; or
9.2. identify methods of stabilising all buildings, accessways and uses areas; and where the
geotechnical report identifies methods of stabilising buildings, accessways and uses areas. The
development shall implement those methods, which are recommended.
10. Sediment and erosion control measures must be in place prior to the demolition of the house. If such
measures are not in place or are not satisfactory, ‘on the spot’ fines may be issued. Such fines can be
issued if sediments from the site are found to enter or have the potential to enter Council’s stormwater
system or natural waterways.
11. The Development Permit for a material change of use lapses if the use has not happened by 15 October
2011, unless an application to extend the currency is approved by Council.
AOP2 c:\docume~1\aop2\locals~1\temp\bcl technologies\easypdf 5\@bcl@f009b738\@[email protected]
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalUsed in these records
Decision Notice - 010.2007.00001541.001 [As Published]Related documentApplication case desk ↗
About this file
- File size
- 26 KB (small file)
- File type
No other editions are linked here.