               45.    All stormwater drainage lines including inter-allotment drainage shall be inspected by closed
                      circuit television (CCTV) prior to commencement of the approved Use.
                      CCTV inspection will be carried out by Council's CCTV contractor and arranged by Council
                      following satisfactory completion of construction works. The developer will be responsible
                      for the full cost of CCTV inspection, including any additional inspection necessary following
                      defect identification and rectification. This charge is payable prior to the issue of Operational
                      Works approval and will be determined on the unit rate basis current at the time of approval.
               Sewer Mains
               46.    Prior to endorsement of the Plan of Survey for Stage 1, the new parcel shall be connected
                      to Council’s existing sewerage reticulation systems and be constructed in accordance with
                      Council’s standards and requirements at no cost to Council. This work may be covered by
                      an uncompleted works bond at 150% of the value of the connection that can be in place for
                      a duration agreed to by the Manager Land Development.
               47.    Prior to endorsement of the Plan of Survey for Stage 2, the existing sewer main, rising main
                      and effluent main that traverse the site shall be relocated generally in accordance with Tate
                      Professional Engineers drawing No. C1732/07/J/P04 dated 19/11/07.
               48.    Prior to endorsement of the Plan of Survey for Stage 2, if required the applicant shall upgrade
                      any existing sewer services (including pumps or pump station) at no cost to Council.
               49.    To ensure Council’s sewer main is accessible for maintenance purposes and is protected
                      from risk of damage no structures requiring a building permit (eg. buildings, swimming pools,
                      retaining walls exceeding 1m in height, raised terraces, etc) shall be constructed within this
                      ‘zone of influence’ or within 1.5m of the centreline of the sewer main, whichever is the greater.
                      As such the applicant shall amend Operational Works plans including Building plans to
                      ensure compliance.
               50.    Design for a sewerage system to connect all new lots within the site to Council's existing
                      sewerage reticulation system shall be to the standards and requirements set out in Council’s
                      Engineering Design Standards. If the design requires the construction of a pump station and
                      a rising main, the connection point to Council's existing system will be nominated by the
                      Manager - Land Development.
               51.    All connections to sewer system shall be carried out either by Council or by a Council
                      approved Contractor and at no cost to Council.
               Town Water Supply
               52.    The site shall be connected to Council’s existing town water supply and be constructed in
                      accordance with Council’s standards and requirements at no cost to Council.
               53.    Prior to endorsement of the Plan of Survey for Stage 1, the newly created parcel shall have
                      a single water connection to the water reticulation system, which shall extend to the property
                      boundary and be metered. This work may be covered by an uncompleted works bond at
                      150% of the value of the connection that can be in place for a duration agreed to by the
                      Manager Land Development.
               54.    Prior to endorsement of the Plan of Survey for Stage 2. the development shall be served by:
                      •       A single Body Corporate water meter to measure the total water consumption
                              (including fire hose reels, but excluding fire hydrants and fire sprinkler systems), and
                      •       Individual water meters to each tenement capable of being separately rated, and
                      •       A fire service (fully testable single detector check with metered bypass), where
                              applicable, for flows to fire hydrants and fire sprinkler systems (excluding fire hose
                              reels).
               55.    All fees for the supply of water meters shall be paid to the Council.




                                                                                                         Page 8 of 19
Document Set ID: 24764739
Version: 6, Version Date: 18/05/2026

Used in these records

About this file

File size
216 KB (small file)
File type
PDF

No other editions are linked here.

Original file

Log in to download the original file

Minor Change Existing Approval - 132007.2399.03 (AS PUBLISHED).pdf · 216 KB (small file)

The supporting record

Open full page ↗

Source document

Analyse documents ↗Open full page ↗

My Comparisons

Choose two to four records of the same kind. Drag using a handle or use the “Compare” buttons.

Your selected records are saved in this browser for your account. Results use the filters on the page where you choose “Compare selected”.