Roof Water & Stormwater Drainage
18. The overland flow drainage path within Easement E, as shown on Registered Plan 865301,
must be maintained at all times. In this regard, plans must be submitted with the application for
Building Works Approval that demonstrate the overland flow drainage path will be maintained,
and scour will be prevented within Easement E at all times during and post construction
phase.
19. All stormwater drainage (including roof water overflow from the rainwater storage system)
shall be collected and discharged so there is no net increase in stormwater runoff from the
site. Stormwater drainage permitted to drain from the site shall be discharged to Council’s:
19.1. existing drainage structures in Whale Drive. Plans of the drainage design shall be
prepared by a Registered Professional Civil Engineer and submitted to Council for
approval prior to obtaining a Building Works approval; and/or
19.2. kerb & channel street drainage system in Whale Drive. Plans of the drainage design
shall be prepared by a Registered Professional Civil Engineer and submitted for the
Building Works approval.
The maximum discharge of stormwater drainage allowable to Council’s kerb & channel street
drainage system at any one location is 25 litres/second.
20. Roof runoff from any new building shall be directed to a rainwater storage system or tank that
is installed to ensure water from the rainwater storage system or tank is used for external uses
(such as watering gardens, irrigation, ornamental ponds, water features, topping-up swimming
pools, outdoor cleaning, etc) and for internal (ground floor) use in washing machine cold taps
and toilet cisterns. All rainwater tanks are to be designed and installed in accordance with the
Queensland Development Code (QDC) current at the time of building approval, and shall be
part of the plumbing application for approval. The location and capacity of the tank(s) shall be
clearly shown on the plans submitted for Building Works approval and any overflow shall be
directed to the road frontage/the stormwater drainage system/etc located at Whale Drive.
21. All site stormwater drainage shall be by means of a gravity system.
Services
22. The applicant must provide reticulated water supply and sewerage services to the proposed
development in accordance with The Noosa Plan.
23. The outermost projection of the building (roof fascia) must be located to provide a minimum of 1.0
metre horizontal clearance from the barrel of the Council sewer located on the southern boundary
of the development site. Plans must verify this clearance.
24. The sewer must be accurately located on site prior to building setout to ensure approved
clearances from the Council sewer are maintained.
25. A minimum of 750mm finished cover must be maintained over the Council sewer main where
the proposed driveway crosses the sewer.
26. The building walls, footings, and retaining structures greater than 1.0 metre in height must be
located a minimum of 1.5 metres from Council sewerage infrastructure.
27. The foundations of the building must be designed to ensure no load is placed on the sewer by the
building.
28. A deed of indemnity must be completed by the property owners for the encroachment of the
building eaves within 1.5 metres of the Council sewer.
29. The applicant must ensure that no stormwater, groundwater or sump pump shall be permitted
to discharge to Council’s sewerage system.
Page 4 of 9
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalUsed in these records
Decision Notice - 010.2008.00001546.001 [As Published]Related documentApplication case desk ↗
About this file
- File size
- 65 KB (small file)
- File type
No other editions are linked here.